This document presents Environmental, Health and Safety (EHS) Contractor Requirements established by Collier County for all construction projects, specifically applicable to the 16th Street NE Bridge Project (LAP). The requirements mandate contractor compliance with all applicable federal, state, and local regulations including OSHA, DOT, EPA, DHS, ANSI, FDEP, and NFPA standards, as well as Collier County CMA's standard operating procedures and job safety analysis requirements. Contractors must implement comprehensive site-specific safety plans covering general safety, security, hurricane preparedness, pandemic safety, respirable crystalline silica management, confined space entry, asbestos management, mold remediation, and environmental protection. Additional requirements include proper use of personal protective equipment, powered industrial vehicle certifications, electrical safety compliance, fall protection for work above six feet, and daily incident reporting with weekly internal safety inspections. For work within rights-of-way, contractors must adhere to all FDOT and MUTCD requirements, including ANSI/ISEA 107-2010 compliant high-visibility safety garments and appropriate work zone traffic control measures.
The document further requires contractors to adequately protect all hazardous jobsite locations to prevent public access and inadvertent exposure, including damaged sidewalks, excavations left open overnight, and other identified hazards. All work must meet or exceed standards set forth in the Collier County Vertical Construction Standards and Collier County IT Construction Standards unless specifically exempted in writing by the Facilities Management Division Director and Risk Management Director. Risk management assessments must be incorporated into all pre-construction, construction, and post-construction meetings. These EHS requirements apply to the comprehensive 16th Street NE Bridge Project, which involves constructing a new 147-foot bridge over the Golden Gate Main Canal and widening approximately 3.3 miles of roadway, with a project budget of approximately $26,361,418 and a substantial completion deadline of 520 consecutive calendar days.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Environmental, Health and Safety
Contractor Requirements for all BCC Construction Projects
1. Contractors will be required to understand and comply with all applicable laws and regulations of any governmental entity (OSHA, DOT, EPA, DHS, ANSI, FDEP. NFPA, etc.) and
Collier County CMA’s, EHS Standard Operating Procedures (SOP’s) or Job Safety Analysis
(JSA’s) that that pertain to environmental, health and safety standards and/or work practices applicable to the activities they perform for Collier County. These include but are not limited to:
• Must wear a BCC provided Vendor Badge at all times while on BCC property.
• Powered Industrial Vehicle Certifications (Heavy Equipment, Cranes, etc.)
• Storage, handling, and use of flammable liquids and hazardous materials, including fuels and compressed gas cylinders.
• Daily reporting of any incidents/accidents or any OSHA safety inspections of equipment and worksites.
• Weekly reporting of at least one internal safety inspection of equipment and worksite.
• Use of Personal Fall Protection Devices while working at heights above 6 feet.
• Following Electrical Safety Practices, Arc Flash and Lockout/Tagout procedures.
• Proper use of Personal Protective Equipment. (PPE)
• Proper maintenance and use of ladders and other equipment.
• Guarding of wall and floor openings, open trenches, and excavations.
• Environmental Requirements (Permitting, Tanks, etc.)
2. Required Site EHS Plans for:
• Site Specific Safety Plan
• Site Specific Security Plan
• Site Specific Hurricane Plan
• Site Specific Pandemic Safety Plan (COVID-19) (If Applicable)
• Site Specific Respirable Crystalline Silica Plan (If Applicable)
• Site Specific Confined Space Entry Plan (If Applicable)
• Site Specific Asbestos Management Plan (If Applicable)
• Site Specific Mold Testing and Remediation Management Plan (If Applicable)
• Site Specific Environmental Protection Plan (Spill Cleanup, SPCC, etc.) (If
Applicable)
3. When working within a right-of-way (i.e. roads, sidewalks, bike paths, etc) – All applicable
FDOT and/or MUTCD requirements are to be followed at all times. Specifics include but are not limited to:
• ANSI/ISEA 107-2010 Compliant Class 2 or 3 Hi-Visibility Safety Garments.
• Applicable work zone signage, cones, barricades or barrels, arrow panels, flagging personnel and Stop/Slow Paddles, where necessary, required by law or the BCC.
• An applicable work zone (Maintenance of traffic) plan based on FDOT and/or
MUTCD designs on site.
4. Risk Management is included in all Pre-Activity/Construction, Activity/Construction and
Post Activity/Construction Meetings.
5. Safeguarding construction sites – Protecting the jobsite and preventing or inhibiting public access after activities are finished for the day is equally important. Therefore, all hazardous locations within construction sites and rights-of-ways are to be adequately protected.
Specifics include but are not limited to:
• Damaged, blocked, or missing sections of sidewalks, bike paths or other pedestrian access zones shall be protected with orange barricade fencing, barricades with yellow or red tape (depending on the hazard) or an equivalent means of protection. Sidewalks must also be posted as being closed on both sides with a white sign with black letters.
• Excavations must be protected in a similar manner as listed above if they must be left open overnight, during weekend hours, etc.
• All other hazards shall be evaluated by the contractor to ensure there are no dangerous conditions remaining that could be inadvertently encountered by collier county employees and/or the public while the construction site is not active (i.e., when no construction work is taking place).
6. Contractor must agree that all work must meet or exceed the standards set forth in the
Collier County Vertical Construction Standards and Collier County IT Construction Standards
(if applicable) unless specifically exempted in writing by Facilities Management Division
Director and Risk Management Director.