233700 02-15 AIR OUTLETS AND INLETS.docx

DOCX document 23 KB Posted

Attached to
Z2DA--Proj #: 629-18-127, Remodel Pharmacy for USP 800
Solicitation number
36C25621R0013
Issued by

About this file

This document contains a federal contract solicitation and related technical specifications for renovating a pharmacy. The solicitation requests proposals to remodel an existing pharmacy compounding area and build a new segregated compounding area to meet USP 800 requirements at the Southeast Louisiana Veterans Health Care System in New Orleans, Louisiana. The procurement is set aside only for verified Service-Disabled Veteran-Owned Small Businesses. Offerors must be registered in the System for Award Management and all mandatory information entered prior to submitting a proposal. The magnitude of the construction project is estimated between $1,000,000 to $5,000,000. The technical specifications outline requirements for air outlets and inlets to be installed as part of the pharmacy renovation, including HEPA filtered supply diffusers, exhaust registers, and performance testing procedures.

View the file

Other files

File Type Posted
36C25621R0013 0002.docx DOCX document
Sign in Sheet - Pharmacy Remodel Project.pdf PDF
36C25621R0013 0001.pdf PDF
054000 Cold-Formed Metal Framing.docx DOCX document
013323 Shop Drawings.docx DOCX document
262921 01-17 ENCLOSED SWITCHES AND CIRCUIT BREAKERS.docx DOCX document
230593 02-15 TESTING ADJUSTING AND BALANCING FOR HVAC.docx DOCX document
000110 TOC.docx DOCX document
EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT.docx DOCX document
General Decision LA 20190041 05-31-2019 Orleans Parish LA Building.pdf PDF
224000 09-15 PLUMBING FIXTURES.docx DOCX document
EXHIBIT A PERFORMANCE RELEVANCY SURVEY (1).docx DOCX document
260526 01-17 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS.docx DOCX document
017419 Construction Waste Management.doc DOC document
102600 Wall and Door Protection.docx DOCX document
220711 09-19 PLUMBING INSULATION.docx DOCX document
234000 2-12 HVAC AIR CLEANING DEVICES.doc DOC document
230541 02-15 NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT.docx DOCX document
230711 02-15 HVAC AND BOILER PLANT INSULATION.docx DOCX document
072113 Thermal Insulation.docx DOCX document
233100 3-13 HVAC DUCTS AND CASINGS .docx DOCX document
Architectural Final.pdf PDF
087113 ADO.docx DOCX document
088000 Glazing.docx DOCX document
230800 11-16 COMMISSIONING OF HVAC SYSTEMS.docx DOCX document
260519 01-17 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES.docx DOCX document
092900 Gypsum Board.docx DOCX document
221300 09-15 FACILITY SANITARY AND VENT PIPING.docx DOCX document
230511 8-17 COMMON WORK RESULTS FOR HVAC.docx DOCX document
000115 List of Drawings.docx DOCX document
092216 Non-Structural Metal Framing.docx DOCX document
Fire Protection Final.pdf PDF
099100 Painting.docx DOCX document
232500 02-15 HVAC WATER TREATMENT.docx DOCX document
Exhibit B Past and Present Performance Questionnaire.docx DOCX document
087100 Door Hardware.docx DOCX document
081113 HM Doors and Frames.docx DOCX document
051200 Structural Steel.docx DOCX document
079200 Joint Sealants.docx DOCX document
262726 01-18 WIRING DEVICES.docx DOCX document
36C25621R0013_2.docx DOCX document
010000 General Requirements.docx DOCX document
075423 Thermoplastic Polyolefin Roofing.docx DOCX document
220523 09-15 GENERAL-DUTY VALVES FOR PLUMBING PIPING.docx DOCX document
260511 01-16 REQUIREMENTS FOR ELECTRICAL INSTALLATIONS .docx DOCX document
096723-30 Resinous Decorative Mortar Flooring.docx DOCX document
078400 Firestopping.docx DOCX document
230923 9-11 DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.doc DOC document
230512 08-17 GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT.docx DOCX document
211313 06-15 WET-PIPE SPRINKLER SYSTEMS.docx DOCX document
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Renovate Pharmacy for USP 800 Requirements 02-01-15 VAMC New Orleans, LA

SECTION 23 37 00

AIR OUTLETS AND INLETS

PART 1 GENERAL

1.1 DESCRIPTION

A.Roof Curbs.
B.Air Outlets and Inlets: Diffusers, Registers, and Grilles.

1.2 RELATED WORK

A.Section 23 05 11, COMMON WORK RESULTS FOR HVAC.
B.Section 23 05 41, NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT.
C.Section 23 05 93, TESTING, ADJUSTING, AND BALANCING FOR HVAC.

1.3 QUALITY ASSURANCE

A.Refer to article, QUALITY ASSURANCE, in Section 23 05 11, COMMON WORK RESULTS FOR HVAC.
B.Fire Safety Code: Comply with NFPA 90A.

1.4 SUBMITTALS

A.Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and SAMPLES.
B.Manufacturer's Literature and Data: Diffusers, registers, grilles and accessories.
C.Coordination Drawings: Refer to article, SUBMITTALS, in Section 23 05 11, COMMON WORK RESULTS FOR HVAC.

1.5 APPLICABLE PUBLICATIONS

A.The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
B.Air Diffusion Council Test Code:
1062 GRD-84Certification, Rating, and Test Manual 4th Edition
C.American Society of Civil Engineers (ASCE):
7-2016Minimum Design Loads for Buildings and Other Structures
D.National Fire Protection Association (NFPA):
90A-2017Standard for the Installation of AirConditioning and Ventilating Systems

PART 2 PRODUCTS

2.1 AIR OUTLETS AND INLETS

A.Materials:
1.Aluminum or stainless steel as scheduled. Provide manufacturer's standard gasket.
2.Exposed Fastenings: The same material as the respective inlet or outlet. Fasteners for aluminum may be stainless steel.
3.Contractor shall review all ceiling drawings and details and provide all ceiling mounted devices with appropriate dimensions and trim for the specific locations.
B.Performance Test Data: In accordance with Air Diffusion Council Code 1062GRD. Refer to Section 23 05 41, NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT for NC criteria.
C.Air Supply Outlets:
1.See air device schedule on drawings for selected basis of design. If providing items other than basis of design ensure all performance data is included in submittal to allow COR to evaluate the proposed units.
2.Ceiling Diffusers: Suitable for surface mounting, exposed Tbar or special tile ceilings, offwhite finish, square or round neck connection as shown on the drawings. Provide plaster frame for units in plaster ceilings.
a.All devices in USP 797 / 800 spaces shall be 99.99% HEPA filtered high volume laminar flow diffusers with integral face adjustable volume control device that does not change laminar flow delivery pattern. Basis of design as scheduled for special hard ceiling use. Coordinate with ceiling manufacturer. Filter shall be removable from the face of the diffuser.
1)Base bid shall be Camfil Farr Model Pharmaseal – no substitutions allowed.
2)Deductive alternate shall be Titus Model TLFR-SS or approved equal.
b.Device in non-USP 797 spaces shall be square louvered face as scheduled for lay-in mounting and with opposed blade balancing damper.
D.Exhaust Registers and Grilles:
1.Device mounted in ceiling is 1/2” x 1/2” x 1/2” egg crate face return/exhaust grill for mounting in hard ceiling. Coordinate with ceiling type. Provide with opposed blade volume damper.
2.Devices mounted in walls are fixed bar grills with opposed blade dampers accessible from unit face.
3.Device in non-USP 797 spaces as indicated on drawings shall be 1/2” x 1/2” x 1/2” egg crate, perforated face or fixed bar for lay-in mounting and with opposed blade balancing damper. See schedule.

part 3 - execution

3.1 INSTALLATION

A.Comply with provisions of Section 23 05 11, COMMON WORK RESULTS FOR HVAC, particularly regarding coordination with other trades and work in existing buildings.
B.Protection and Cleaning: Protect equipment and materials against physical damage. Place equipment in first class operating condition, or return to source of supply for repair or replacement, as determined by COR. Protect equipment during construction against entry of foreign matter to the inside and clean both inside and outside before operation and painting.
C.Install HEPA filtered supply diffusers with DOP testing provisions as detailed.

3.2 testing, adjusting and balancing (tab) A. Refer to Section 23 05 93, TESTING, ADJUSTING, AND BALANCING FOR HVAC. Ensure DOP testing is completed in presence of COR.

3.3 operating and performance tests A. Refer to Section 23 05 11, COMMON WORK RESULTS FOR HVAC.

E N D 23 37 00 - 1