230800 11-16 COMMISSIONING OF HVAC SYSTEMS.docx

DOCX document 20 KB Posted

Attached to
Z2DA--Proj #: 629-18-127, Remodel Pharmacy for USP 800
Solicitation number
36C25621R0013
Issued by

About this file

This document includes a federal construction contract solicitation and related technical specifications for HVAC system commissioning. The solicitation is for project 629-18-127 to remodel a pharmacy to meet USP 800 requirements at the Southeast Louisiana Veterans Health Care System in New Orleans. The work includes building a new segregated compounding area as a backup and falls between $1 million to $5 million in value. The opportunity is a 100% SDVOSB set-aside that is seeking offers from verified Service-Disabled Veteran-Owned Small Businesses by the specified deadline. The technical specifications cover commissioning requirements and responsibilities for ensuring HVAC systems are properly installed and perform as intended, including construction inspections, pre-functional checklists, contractor testing, and systems functional performance testing witnessed by the commissioning agent. Training for VA operations and maintenance personnel is also required.

View the file

Other files

File Type Posted
36C25621R0013 0002.docx DOCX document
Sign in Sheet - Pharmacy Remodel Project.pdf PDF
36C25621R0013 0001.pdf PDF
054000 Cold-Formed Metal Framing.docx DOCX document
013323 Shop Drawings.docx DOCX document
262921 01-17 ENCLOSED SWITCHES AND CIRCUIT BREAKERS.docx DOCX document
230593 02-15 TESTING ADJUSTING AND BALANCING FOR HVAC.docx DOCX document
000110 TOC.docx DOCX document
EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT.docx DOCX document
General Decision LA 20190041 05-31-2019 Orleans Parish LA Building.pdf PDF
224000 09-15 PLUMBING FIXTURES.docx DOCX document
EXHIBIT A PERFORMANCE RELEVANCY SURVEY (1).docx DOCX document
260526 01-17 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS.docx DOCX document
017419 Construction Waste Management.doc DOC document
102600 Wall and Door Protection.docx DOCX document
220711 09-19 PLUMBING INSULATION.docx DOCX document
234000 2-12 HVAC AIR CLEANING DEVICES.doc DOC document
230541 02-15 NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT.docx DOCX document
230711 02-15 HVAC AND BOILER PLANT INSULATION.docx DOCX document
072113 Thermal Insulation.docx DOCX document
233100 3-13 HVAC DUCTS AND CASINGS .docx DOCX document
Architectural Final.pdf PDF
087113 ADO.docx DOCX document
088000 Glazing.docx DOCX document
260519 01-17 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES.docx DOCX document
092900 Gypsum Board.docx DOCX document
221300 09-15 FACILITY SANITARY AND VENT PIPING.docx DOCX document
230511 8-17 COMMON WORK RESULTS FOR HVAC.docx DOCX document
000115 List of Drawings.docx DOCX document
092216 Non-Structural Metal Framing.docx DOCX document
Fire Protection Final.pdf PDF
099100 Painting.docx DOCX document
232500 02-15 HVAC WATER TREATMENT.docx DOCX document
Exhibit B Past and Present Performance Questionnaire.docx DOCX document
233700 02-15 AIR OUTLETS AND INLETS.docx DOCX document
087100 Door Hardware.docx DOCX document
081113 HM Doors and Frames.docx DOCX document
051200 Structural Steel.docx DOCX document
079200 Joint Sealants.docx DOCX document
262726 01-18 WIRING DEVICES.docx DOCX document
36C25621R0013_2.docx DOCX document
010000 General Requirements.docx DOCX document
075423 Thermoplastic Polyolefin Roofing.docx DOCX document
220523 09-15 GENERAL-DUTY VALVES FOR PLUMBING PIPING.docx DOCX document
260511 01-16 REQUIREMENTS FOR ELECTRICAL INSTALLATIONS .docx DOCX document
096723-30 Resinous Decorative Mortar Flooring.docx DOCX document
078400 Firestopping.docx DOCX document
230923 9-11 DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.doc DOC document
230512 08-17 GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT.docx DOCX document
211313 06-15 WET-PIPE SPRINKLER SYSTEMS.docx DOCX document
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Renovate Pharmacy for USP 800 Requirements 11-1-16 VAMC New Orleans, LA

SECTION 23 08 00

COMMISSIONING OF HVAC SYSTEMS

PART 1 - GENERAL

1.1 DESCRIPTION

A.The requirements of this Section apply to all sections of Division 23.
B.This project will have selected building systems commissioned. The complete list of equipment and systems to be commissioned is specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS. The commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 00 GENERAL COMMISSIONING REQUIRMENTS. A Commissioning Agent (CxA) appointed by the VA will manage the commissioning process.

1.2 RELATED WORK

A. Section 01 00 00 GENERAL REQUIREMENTS.

B. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

C. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

1.3 SUMMARY

A.This Section includes requirements for commissioning the Facility exterior closure, related subsystems and related equipment. This Section supplements the general requirements specified in Section 01 91 00 General Commissioning Requirements.
B.Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for more details regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members.

1.4 DEFINITIONS

A. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for definitions.

1.5 COMMISSIONED SYSTEMS

A.Commissioning of a system or systems specified in Division 23 is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel in accordance with the requirements of Section 01 91 00 and of Division 23, is required in cooperation with the VA and the Commissioning Agent.
B.The Facility exterior closure systems commissioning will include the systems listed in Section 01 91 00 General Commissioning Requirements.

1.6 SUBMITTALS

A.The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.
B.The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 Construction inspections

A. Commissioning of HVAC systems will require inspection of individual elements of the HVAC systems construction throughout the construction period. The Contractor shall coordinate with the Commissioning Agent in accordance with Section 01 91 00 and the Commissioning plan to schedule HVAC systems inspections as required to support the Commissioning Process.

3.2 PRE-FUNCTIONAL CHECKLISTS

A. The Contractor shall complete Pre-Functional Checklists to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional Performance Testing. The Commissioning Agent will prepare Pre-Functional Checklists to be used to document equipment installation. The Contractor shall complete the checklists. Completed checklists shall be submitted to the VA and to the Commissioning Agent for review. The Commissioning Agent may spot check a sample of completed checklists. If the Commissioning Agent determines that the information provided on the checklist is not accurate, the Commissioning Agent will return the marked-up checklist to the Contractor for correction and resubmission. If the Commissioning Agent determines that a significant number of completed checklists for similar equipment are not accurate, the Commissioning Agent will select a broader sample of checklists for review. If the Commissioning Agent determines that a significant number of the broader sample of checklists is also inaccurate, all the checklists for the type of equipment will be returned to the Contractor for correction and resubmission. Refer to SECTION 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for submittal requirements for Pre-Functional Checklists, Equipment Startup Reports, and other commissioning documents.

3.3 CONTRACTORS TESTS

A. Contractor tests as required by other sections of Division 23 shall be scheduled and documented in accordance with Section 01 00 00 GENERAL REQUIREMENTS. All testing shall be incorporated into the project schedule. Contractor shall provide no less than 7 calendar days’ notice of testing. The Commissioning Agent will witness selected Contractor tests at the sole discretion of the Commissioning Agent. Contractor tests shall be completed prior to scheduling Systems Functional Performance Testing.

3.4 SYSTEMS FUNCTIONAL PERFORMANCE TESTING:

A. The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems Functional Performance Test procedures for review and approval by the COR. The Contractor shall review and comment on the tests prior to approval. The Contractor shall provide the required labor, materials, and test equipment identified in the test procedure to perform the tests. The Commissioning Agent will witness and document the testing. The Contractor shall sign the test reports to verify tests were performed. See Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS, for additional details.

3.5 TRAINING OF VA PERSONNEL

A. Training of the VA operation and maintenance personnel is required in cooperation with the COR and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the requirements of Section 01 91 00. The instruction shall be scheduled in coordination with the VA COR after submission and approval of formal training plans. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS and Division 23 Sections for additional Contractor training requirements.

----- END -----