American Embassy London UNCLASSIFIED U.S. Department of State
EXHIBIT C
Chillers Statement of Work
I. GENERAL INFORMATION:
The United States Embassy in London requires professional services and contractor cost proposals to perform preventive maintenance services of the facility’s Chillers to include two water-cooled chillers, one dedicated heat recovery modular chiller and one air-cooled modular chiller.
II. PROJECT REQUIREMENTS:
DESCRIPTION OF EQUIPMENT *:
*Please see EXHIBIT A for the equipment schedule and details.
III. GENERAL REQUIREMENTS:
The Contractor under this SOW shall be responsible for labor, tools, and materials required to carry out all preventive maintenance as outlined in this SOW. The Government has the following manuals:
O&M manuals can be provided for all the equipment quoted on EXHIBIT A on request.
IV. SCOPE OF WORK - - CHILLERS MAINTENANCE
Contractor shall provide all materials, supervision, labor, tools and equipment to perform preventive maintenance. All personnel working in the vicinity shall wear and /or use safety protection while all work is performed. Any questions or injuries shall be brought to the attention of the Post Occupation Safety and Health Officer (POSHO) immediately. Material Safety Data Sheets (MSDS) shall be provided by the Contractor for all HAZMAT materials.
Copies shall be provided to the COR for approval.
The Contractor shall inventory, supply and replace expendable parts (e.g., filters, belts, hoses, gaskets) that have become worn down due to wear and tear. The Contractor shall maintain a supply of expendable and common parts on site so that these are readily available for normal maintenance to include: hoses, belts, oil, chemicals, coolant, filters (Air, Fuel, Oil), grease, sealant, thermostat, fuses; in addition to the appropriate tools, testing equipment, safety shoes and apparel for technicians, personal protective equipment (hands, hearing, eye protection), MSDS, cleaning material and oil spill containment kits. The contractor should inventory the supply after each visit and order replacement supplies and have them delivered on site.
Maintenance materials shall be unused and are to be industry standard and intended for the task to be performed. Parts are to be OEM approved. Refrigerants are to meet the AHRI_Standard_700-2015 or most recent AHRI Standards.
Refrigerants, parts and maintenance materials delivered to the post are to be new and unused.
Reclaimed refrigerants are not to be delivered to posts. Reclaimed refrigerants within post
Solicitation 19GE5018R0023 compounds are to be retained and stored and may be used if not contaminated. Refrigerants shall be stored in containers clearly indicating the refrigerant type.
SAFETY AND SPECIAL INSTRUCTIONS:
1. Follow site safety procedures and supervisor’s instructions.
2. Schedule outage with operating personnel.
3. Use extreme caution when climbing access ladders.
4. Perform applicable lockout/tag out steps of site safety procedures.
5. Lockout and disconnect the main power before tightening the main supply lugs in order to avoid the hazard of electrical shock, which could result in serious personal injury or death.
6. Record and report equipment damage or deficiencies.
7. Review and follow the manufacturer’s O&M instructions.
8. Record results in the equipment history log.
9. Allow only qualified personnel to do maintenance work on this equipment.
10. Record results in the equipment history log.
11. Check manufacturer’s specifications for the maximum number of plugged tubes.
12. Allow only qualified personnel to do maintenance work on this equipment.
CHILLERS
MAINTENANCE PROCEDURES:
Air Cooled Chiller (modular):
The contractor shall refer to the relevant O&M document for the daily, weekly and monthly checks and preventive maintenance activities related to this equipment.
Water Cooled Chiller:
The contractor shall refer to the relevant O&M document for the daily, weekly and monthly checks and preventive maintenance activities related to this equipment.
Modular Chiller: 7 modules
The contractor shall refer to the relevant O&M document for the daily, weekly and monthly checks and preventive maintenance activities related to this equipment.
Spare Parts and Expendables Inventory. The following is the minimum required expendable and common parts to be maintained on site by the contractor for normal maintenance to include:
hoses, belts, oil, chemicals, coolant, filters (Air, Fuel, Oil), grease, sealant, thermostat, fuses.