1502000 F Facility Investment CATHODIC.pdf

PDF 145 KB Posted

Attached to
AST/UST/Cathodic Protection Maintenance and Repair
Solicitation number
N40085-20-R-3006
Issued by

About this file

This document outlines deliverables and reporting requirements for a cathodic protection maintenance and repair contract. The contractor must submit certifications and licenses within 15 days of award, provide a preventive maintenance plan within 30 days, and submit various monthly, annual, and ad hoc reports detailing work completed, materials used, labor hours, and inspection findings. Reports include a service order summary, monthly preventive maintenance schedule, maintenance summary, and aboveground and underground storage tank inspection forms. The contractor must notify the Environmental Engineer of any major violations within 4 hours. This contract supports cathodic protection, automatic tank gauging, and fuel management systems testing and repair for aboveground and underground tanks at the Naval Submarine Base New London in Groton, Connecticut.

View the file

Other files

File Type Posted
N4008520R3006 002.pdf PDF
J-1502000-10 UNDERGRD STORAGE TANK INSP FORM MONTHLY-ANNUAL.pdf PDF
Amendment 1_site_visit.pdf PDF
J-1502000-9 STI 6th AST Annual.pdf PDF
J-150200-12 ELINS cathodic 2020.xls XLS spreadsheet
J-0200000-09 Charc Meter Reading.xlsx XLSX spreadsheet
J-0200000-08 Specification Information.xlsx XLSX spreadsheet
20R3006_Cathodic Protection.pdf PDF
J-0200000-07 Asset Information.xlsx XLSX spreadsheet
J-0200000-11 SPCC Plan.pdf PDF
J-020000-05A Quality Inspection and Surveillance report.xlsx XLSX spreadsheet
1502000 C Facility Investment CATHODIC.pdf PDF
0200000 F Management and Administration v2.8.pdf PDF
J-1502000-06 Service Order Summary Report.xlsx XLSX spreadsheet
J-020000-05B On site Labor Summary Report (1).xlsx XLSX spreadsheet
0200000 C Management and Administration v2.9.pdf PDF
J-1502000-05 CATHODIC INVENTORY.xlsx XLSX spreadsheet
1502000 J Facility Investment CATHODIC.pdf PDF
0100000 C General Information Cathodic Protection.pdf PDF
J-1502000-03 BASE MAP 2019.pdf PDF
J-1502000-08 ABOVEGROUND STORAGE TANK INSP FORM MONTHLY.pdf PDF
J-0200000-04 Invoice Form.pdf PDF
NEPA_AST_UST_Cathodic2020_signed.pdf PDF
J-1502000-07 Maintenance Summary Report - Copy.xlsx XLSX spreadsheet
J-0200000-06 - Ser Provider Info.xlsx XLSX spreadsheet
1502000 FAP Facility Investment CATHODIC.pdf PDF
0200000 J Management and Administration v2.6.pdf PDF
J-1502000-10 STI 6th AST Monthly.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1502000 – Facility Investment

SECTION F: DELIVERIES OR PERFORMANCE

DELIVERABLES

Annex/

Spec Item

Form

Attachment

Number Deliverable Title

Date (s) of

Submission

Distribution

Frequency

Original/

Copies

Number of

Copies

(including original)

1502000/

2.2.1

N/A

Certification and

Licenses

Within 15 days after award or as requested by the

KO

KO/PAR 1 Once for initial submittal, then as requested

1502000/

3.1

J-1502000-06 Service Order

Summary Report

First work day of each month

KO/PAR

/ENV

2 Monthly

1502000/

3.2

N/A

Preventive

Maintenance

Program Plan

30 calendar days after contract award

KO/PAR

/ENV

2 Annually

1502000/

3.2

N/A Monthly PM Work

Schedule

Five work days prior to the beginning of each month

KO/PAR

/ENV

1 Monthly

1502000/

3.2

J-1502000-07 Monthly

Maintenance

Summary Report

Within 5 work days after month ending

KO/PAR

/ENV

1 Monthly

1502000/

3.2

J-1502000-08 Monthly Above ground Storage

Tank Inspection

Form

Within 5 working days after monthly inspection ending

KO/PAR

/ENV

2 Monthly

1502000/

3.2

J-1502000-09 Annually Above ground Storage

Tank Inspection

Form

Within 5 working days after option year inspection ending

KO/PAR

/ENV

2 Annually

1502000/

3.2

J-1502000-10 Underground

Storage Tank

Inspection Form

Within 5 working days after month/option year inspection ending

KO/PAR

/ENV

2 Monthly/

Annually

NOTE: Copies of monthly reports shall be sent to the PAR and to our Environmental Engineer in charge of the tank program. Any major violations found of codes or regulations, contractor shall notify the Environmental Engineer in charge of the tank program as soon as possible but no longer than 4 hours from the time of identification.

Deliverables Form Preparation Instructions

Deliverable Title: Service Order Summary Report

Form Attachment No.: J-1502000-05

Government Approval Required: X Yes ___ No

Media: Hard Copy X Electronic ___ Direct System Input

Instructions:

The report shall be prepared using Microsoft Office Word software.

The Service Order Summary Report shall be a compilation of the previous months service order reports with the following information:

a. Detailed description of work actually completed, problems encountered and recommended follow-up actions required.

b. Brief description of material and parts used, including quantities and cost.

c. Date and time work began.

d. Date and time work was completed.

e. Total hours of labor (by craft) expended, including travel time.

f. Name of person accepting the work and any comments written on the service order ticket.

g. Last name and first initial of the Contractor employee(s) performing the work.

Submit a copy of the summary report via email to KO for Government review and comment.