0100000 C General Information Cathodic Protection.pdf
PDF 226 KB Posted
- Solicitation number
- N40085-20-R-3006
About this file
This performance work statement outlines preventative maintenance services for cathodic protection systems at Naval Submarine Base New London in Groton, Connecticut. The contractor shall provide all labor, materials, equipment, supervision, and management to test, calibrate, adjust, and repair cathodic protection, automatic tank gauging, and fuel management systems on above-ground and underground tanks, piers, quay walls, and associated equipment at various locations supported by the base. The contractor will also perform required services at additional locations as needed. The work will be carried out under an indefinite delivery indefinite quantity contract comprised of recurring and non-recurring work items. The Navy seeks to adopt industry best practices and maintain state-of-the-art service delivery by evaluating performance objectives.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0100000 – General Information
Spec Item Title
1 General Information
1.1 Outline of Services
1.2 Project Location
1.3 Acquisition of Additional Work
1.4 Background Information
1.5 Verification of Workload and Conditions
1.6 Climate Patterns
1.7 Related Information
1.8 Navy Approach to Service Contracting
1.8.1 Partnering Philosophy
1.8.2 Contractor's Knowledge
1.8.3 Industry Best Practices
1.9 Standard Template
1.10 Navy PBSA Approach
1.11 Technical Proposal Certification
Spec Item Title Description
1 General Information The intent of this solicitation is to provide Preventative Maintenance to
Cathodic Protection systems located at the Naval Submarine Base (NSB)
New London, Groton, CT (SUBASE NLON) and its tenant commands and activities at various locations.
1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services outlined below and described in this Performance Work
Statement (PWS) at NSB New London in Groton, CT and outlying areas supported by this installation under an Indefinite Delivery Indefinite
Quantity type, performance-based contract that is comprised of both
Recurring Work and Non-Recurring Work Items.
The PWS is organized into annexes. Annex 1 is "General Information".
Annex 2 contains the on-site project management and administration requirements. Annexes 3 through 18 contain the technical requirements.
The annex numbers are identified as 1 through 18 in the description column, but the full expanded annex numbers include seven digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page
Annex 1 General Information
Annex 2 Management and Administration
Annex 3 Command and Staff NA
Annex 4 Public Safety NA
Annex 5 Air Operations NA
Annex 6 Port Operations NA
Annex 7 Ordnance NA
Annex 8 Range Operations NA
Annex 9 Health Care Support NA
Annex 10 Supply NA
Annex 11 Personnel Support NA
Annex 12 Morale, Welfare and Recreation Support NA
Annex 13 Galley NA
Annex 14 Housing NA
Annex 15 Facilities Support
1502000 – Facility Investment
Annex 16 Utilities NA
Annex 17 Base Support Vehicles and Equipment NA
Annex 18 Environmental NA
1.2 Project Location The work shall be performed at various locations and could vary from location to location throughout and nearby Naval Submarine Base New
London, Groton CT.
1.3 Acquisition of
Additional Work
The Government reserves the right to acquire additional services at additional locations, within the scope of the annexes and areas included in
Spec Item 1.1 Outline of Services, in addition to the services and locations identified in the requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the non-recurring work provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.
1.4 Background Information Naval Submarine Base New London is the Navy’s first Submarine Base and the “Home of the Submarine Force.” In 1868, the State of Connecticut gave the Navy 112 acres of land along the Thames River to build a Naval
Station. Although physically located in Groton, CT, the base had their main offices and housing in the larger city of New London, hence was christened as Naval Submarine Base New London. Following World War
I, the Navy established schools and training facilities at the base. Today, SUBASE NLON, located on the east side of the Thames River in Groton, CT, proudly claims its motto to be “The First and Finest.” The main base currently occupies more than 687 acres and “homeports” sixteen attack submarines and the Navy’s nuclear research deep submersible NR-1. The base also supports more than 70 tenant commands including Commander
Navy Region Northeast (CNRNE), Commander Submarine Group 2
(CSG2), Naval Submarine School (SUBSCOL), Naval Submarine Support
Facility (NSSF), three Submarine Squadron staffs, and the housing and support facilities for more than 21,000 civilian workers, active-duty service members and their families.
1.5 Verification of
Workload and
Conditions
Throughout the PWS, the workload data is generally referred to as being located in Sections C and J. Section C provides data such as descriptions, specifications, and the statement of work. Section J provides data such as system descriptions, inventories, maps, floor plans, and tables to represent the type, quantity, and location of services to be provided.
As prescribed in FAR 52.237-1, offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
1.6 Climate Patterns Connecticut has a humid continental climate. The average yearly temperature along the coast is 51° F. Recorded temperatures in
Connecticut range from –32° F, in 1943 at Falls Village, to 105° F, in 1926 at Waterbury.
Throughout most of the state, yearly precipitation varies between about 44 and 48 in. Annual snowfall on the coast is about 27” with inland accumulations averaging 53”. Violent storms in the state are rare, but several hurricanes have struck along the coast. A tornado, rare for this region, touched down North of Hartford in 1979 and did extensive damage.
1.7 Related Information There are four types of Related Information that can be found in the
Description and Related Information columns of the specification as follows:
Informational Notes as used throughout this PWS provides additional information to offerors to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked
“Informational Notes” throughout Annexes 1 through 18 is subject to this disclaimer. Offerors may not rely upon the "Informational Notes" as material representations of the Government. Information provided in
"Informational Notes" does not create a contractual requirement on either party to this contract.
Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.
Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.
Requirement Information further describes client requirements associated with each Performance Objective.
1.8 Navy Approach to
Service Contracting
The Department of Navy (DoN) spends over $1 billion in annual obligations to meet global requirements for facility operations and maintenance provided through Facility Support Contracts (FSC) and additional billions to provide other base operations support services
(OBOS). The Head of the Contracting Activity (HCA) of the Naval
Facilities Engineering Command (NAVFAC) has focused increased attention on re-engineering FSC contracts in response to customer and industry feedback, budget constraints, and the impact of a variety of contracting, program management and financial management regulations.
The Navy also supports the following principles:
1.8.1 Partnering Philosophy The first principle is that the Navy views its contractors as partners and not just abstract service providers. The Navy wants its contractors to succeed because partners' success drives the Navy's successful mission completion.
Within the bounds of acquisition policy the Navy intends to work to find solutions that will be beneficial to both the Government and its partners.
1.8.2 Contractor's Knowledge The second principle is that the Navy will receive insightful management from its contractors. This management will include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The
Navy's use of performance-based objectives evidences this principle.
Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.
1.8.3 Industry Best Practices The third principle is that the Navy will adopt industry best commercial practices and maintain state-of-the-art service delivery. To that end, the
Navy's emphasis will be in evaluating performance objectives (end results).
1.9 Standard Template Key to implementing a programmatic approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs. This contract conforms to the standard template and has been tailored for this solicitation. NAVFAC intends to use this template-based approach for future service contracts. Offerors should develop an understanding of the template as part of performing due diligence in reaching an understanding of the Navy’s requirements and expectations.
The standard template contains 18 standard annexes. Annex 1 will always contain information that is relevant to the entire scope of the contract.
Annex 2 contains on-site project management and administration requirements that are relevant to the entire scope of the contract. Annexes
3 through 18 contain the technical information and requirements peculiar to that technical annex. Within each technical annex, the organization of information and requirements are also standardized. Specification Item 1 will always contain General Information. Specification Item 2 will always contain the management and administrative requirements. Specification
Item 3 will always contain the Recurring Work requirements.
Specification Item 4 will always contain the Non-Recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item
3 standards apply to all recurring work specification items. Specification
Item 3.1 is applicable to all 3.1 subordinate specification items.
Specification Items 3.2 and 3.3 are not considered subordinate to 3.1. All costs associated with Annexes 1 and 2 and Specification Items 1 and 2 must be priced and their price must be allocated across the Exhibit Line
Items.
1.10 Navy PBSA Approach The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts which are 1) performance outcomes, 2) measurable standards, 3) consideration of incentives, and 4) performance assessment plan.
1.11 Technical Proposal
Certification
The Contractor warrants that its proposal incorporated herein by reference will meet or exceed the performance objectives set forth in this contract.
File details come from the government source that posted it. Updated .