B09-Attachment_1_-_Revised_Final_CD_Specifications_2026_08_18_0002.pdf

PDF 7 MB Posted

Attached to
YELL 326141 YELLOWSTONE MODULAR HOUSING
Solicitation number
140P2026R0078
Issued by

About this file

This is a Project Specifications document for the Yellowstone National Park Modular Housing Units (YELL 326141) project, prepared by the National Park Service Denver Service Center as 100% Final Construction Documents dated August 2026.

The project encompasses procurement and construction of modular employee housing across three government areas within Yellowstone National Park: Canyon Village (northwest of Canyon Village along Grand Loop Road and Norris Canyon Road, Wyoming), Northeast Entrance (3.5 miles west of Cooke City, Montana along US Highway 212), and Mammoth (Mammoth, Wyoming along US Highway 89). The scope includes site improvements such as clearing, grading, roadway construction, drainage, and utility installation for electrical, telecom, potable water, fire suppression, and sanitary sewer systems. Nine standard modular building units and one ADA-compliant unit are required at Canyon; one standard and one ADA-compliant unit at Northeast Entrance; and three standard units plus one ADA-compliant unit at Mammoth. Payment is structured as lump-sum contracts for site improvements and per-unit pricing for modular buildings across the three locations. Key contract requirements include strict environmental compliance with protections for whitebark pine, Ute ladies-tresses, grizzly bears, Canada lynx, yellow-billed cuckoos, wolverines, monarch butterflies, and Suckley's cuckoo bumble bees; adherence to NPS project management software for communication and document sharing; submission of detailed construction schedules using Critical Path Method; and compliance with archaeological resource protection and Native American Graves Protection and Repatriation Act provisions. The contractor must obtain necessary permits, coordinate with multiple utility providers (Northwestern Energy, Flathead Electric, Century Link), and manage construction operations within designated work hours (8:00 a.m. to 5:00 p.m., Monday through Friday) unless approved otherwise. Additional requirements include equipment inspections prior to park entry, material sourcing from recently inspected gravel pits, comprehensive waste management planning, indoor air quality management, stormwater pollution prevention, and bearing of all costs related to bear management actions resulting from improper garbage or food handling. The specifications detail extensive Division 1 general requirements, division-specific work requirements covering concrete, metals, wood, thermal protection, openings, finishes, equipment, and utilities, with appendices containing categorical exclusion documents, biological opinions, geotechnical reports, and environmental permits.

View the file

Other files

File Type Posted
Sol_140P2026R0078_Amd_0004.pdf PDF
B08_Attachment_7_Limitations_on_Subcontracting_Report_0004.xlsx XLSX spreadsheet
B09-140P2026R0078-Amd_4_0004.pdf PDF
Sol_140P2026R0078_Amd_0003.pdf PDF
B09_Amendment_3__Past_Performance_Questionnaire_0003.docx DOCX document
B09_Amendment_3_Questions_and_Answers_0003.pdf PDF
B09_Amendment_3_estimated_cut_and_fill_quantities_0003.pdf PDF
B09_Amendment_3_Yellowstone_NE_Entrance_Project_Report_0003.pdf PDF
B09_Amendment_3_Yellowstone_Mammoth_Project_Report_0003.pdf PDF
B09_Amendment_3__Project_Experience_Questionnaire_0003.docx DOCX document
B09_Amendment_3_General_References_0003.docx DOCX document
B09_Amendment_3_Yellowstone_Canyon_Project_Report_0003.pdf PDF
B09-Attachment_2_-_Revised_Final_Construction_Drawings_2026_08_18_Part3_0002.pdf PDF
Sol_140P2026R0078_Amd_0002.pdf PDF
B09-Attachment_2_-_Revised_Final_Construction_Drawings_2026_08_18_Part1_0002.pdf PDF
B09-Attachment_2_-_Revised_Final_Construction_Drawings_2026_08_18_Part4_0002.pdf PDF
B09-140P2026R0078-Amd_2_0002.pdf PDF
B09-Attachment_2_-_Revised_Final_Construction_Drawings_2026_08_18_Part7_0002.pdf PDF
B09-Attachment_2_-_Revised_Final_Construction_Drawings_2026_08_18_Part5_0002.pdf PDF
B09-Attachment_2_-_Revised_Final_Construction_Drawings_2026_08_18_Part2_0002.pdf PDF
B09-Attachment_2_-_Revised_Final_Construction_Drawings_2026_08_18_Part6_0002.pdf PDF
B08-YELL_326141_MODULAR_HOUSING_Preproposal__0001.pdf PDF
Sol_140P2026R0078_Amd_0001.pdf PDF
Sign_In_Sheet_Page_1_0001.jpg JPG image
Sign_In_Sheet_Page_2_0001.jpg JPG image
Sol_140P2026R0078.pdf PDF
B08-Attachment_2-01_YELL_326141_Final_CD_Plans_2026_07_22_Part6.pdf PDF
B08-Attachment_2-01_YELL_326141_Final_CD_Plans_2026_07_22_Part3.pdf PDF
B08-YELL_326141_pre-proposal_project_overview_and_site_visit_(002).pdf PDF
B08-Attachment_1_-_02_YELL_326141_Final_Specifications_2026_07_22.pdf PDF
B08_Solitation-140P2026R0078_v16_17June2026.pdf PDF
E15_Deliverables_LmtOnSubconRpt_REQD.xlsx XLSX spreadsheet
B08-Attachment_2-01_YELL_326141_Final_CD_Plans_2026_07_22_Part4.pdf PDF
B08-Attachment_2-01_YELL_326141_Final_CD_Plans_2026_07_22_Part2.pdf PDF
B08-Attachment_2-01_YELL_326141_Final_CD_Plans_2026_07_22_Part1.pdf PDF
B08-Attachment_2-01_YELL_326141_Final_CD_Plans_2026_07_22_Part5.pdf PDF
B08-Attachment_1A-03_YELL_326141_Final_Specification_Appendicies_2026_07_22.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

YELLOWSTONE NATIONAL PARK

MODULAR HOUSING UNITS

YELL 326141

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE (NPS)

DENVER SERVICE CENTER (DSC)

100% Final CDs

August, 2026

YELL 326141 1

TABLE OF CONTENTS

Yellowstone National Park YELL 326141

TABLE OF CONTENTS

SPECIFICATIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work

01 26 01 Contract Modification Procedures

01 27 00 Definition of Contract Line Items

Supplement � Contract Price Schedule

01 31 00 Project Management and Coordination

01 32 16 Construction Schedule

01 32 33 Photographic Documentation

01 33 23 Submittal Procedures

Supplement � Submittal List

01 35 13 Natural Resources Protection

01 35 13.22 Archeological Resources Protection

01 35 23 Safety Requirements

01 40 00 Quality Requirements

01 42 00 Reference Standards

01 45 33 Special Inspection, Observation, and Testing

Supplement � Contractor�s Statement of Responsibility

01 50 00 Temporary Facilities and Controls

01 57 19.11 Indoor Air Quality (IAQ) Management

01 57 19.12 Noise & Acoustics Management

01 57 23 Temporary Stormwater Pollution Prevention (SWPPP)

01 67 00 Product Requirements

Supplement � Affirmative Procurement Reporting Form

01 71 13 Mobilization and Demobilization

Supplement � Equipment Inspection Contact List

Gravel Pit Inspections Report

01 73 40 Execution

01 74 19 Construction Waste Management and Disposal

01 77 00 Closeout Procedures

01 78 23 Operation and Maintenance Data

Supplement � Equipment Data Sheet

01 79 00 Demonstration and Training

DIVISION 01 SUPPLEMENTS: Project Waste Management Plan Worksheet

Closeout and Operation and Maintenance Requirements

DIVISION 02 � EXISTING CONDITIONS

02 01 00 Maintenance of Existing Conditions

02 41 00 Demolition and Salvage

02 41 19 Selective Demolition

YELL 326141 2

DIVISION 03 � CONCRETE

03 11 13 Void Forms

03 30 00 Cast In Place Concrete

03 30 50 Minor Concrete

03 30 53 Spread and Continuous Footings

03 62 00 Non-Shrink Grout

DIVISION 05 � METALS

05 50 00 Metal Fabrications

05 73 00 Decorative Metal Railings

DIVISION 06 � WOOD, PLASTIC, AND COMPOSITES

06 10 00 Rough Carpentry

06 16 00 Sheathing

06 17 53 Shop-Fabricated Wood Trusses

06 20 13 Exterior Finish Carpentry

06 20 23 Interior Finish Carpentry

DIVISION 07 � THERMAL AND MOISTURE PROTECTION

07 14 16 Cold Fluid-Applied Waterproofing

07 21 00 Thermal Insulation

07 21 19 Foamed-In-Place Insulation

07 26 00 Vapor Retarders

07 41 13.16 Standing-Seam Metal Roof Panels

07 46 46 Fiber-Cement Siding

07 92 00 Joint Sealants

DIVISION 08 � OPENINGS

08 14 33 Stile and Rail Wood Doors

08 16 13 Fiberglass Doors and Frames

08 31 13 Access Doors and Frames

08 36 13 Sectional Doors

08 54 13 Fiberglass Windows

08 71 00 Door Hardware

08 80 00 Glazing

DIVISION 09 � FINISHES

09 29 00 Gypsum Board

09 30 13 Ceramic Tiling

09 65 19 Resilient Tile Flooring

09 68 16 Sheet Carpeting

09 91 13 Exterior Painting

09 91 23 Interior Painting

DIVISION 10 � SPECIALTIES

10 14 00 Signage

10 28 00 Toilet, Bath, and Laundry Accessories

DIVISION 11 � EQUIPMENT

YELL 326141 3

11 30 13 Residential Appliances

DIVISION 12 � FURNISHINGS

12 24 13 Roller Window Shades

12 35 30 Residential Casework

12 36 23.13 Plastic-Laminate-Clad Countertops

DIVISION 13 � SPECIAL CONSTRUCTION

13 34 26 Residential Modular Building Systems

DIVISION 21 � FIRE SUPPRESSION

N/A

DIVISION 22 � PLUMBING

N/A

DIVISION 23 � HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

N/A

DIVISION 26 � ELECTRICAL

26 50 00 Site Electrical

DIVISION 28 � ELECTRONIC SAFETY & SECURITY

N/A

DIVISION 31 � EARTHWORK

31 11 00 Clearing and Grubbing

31 13 00 Selective Tree and Shrub Removal and Trimming

31 23 00 Excavation and Fill

31 23 19 Dewatering

31 25 00 Erosion and Sedimentation Controls

31 37 00 Riprap

31 50 00 Excavation Support and Protection

DIVISION 32 � EXTERIOR IMPROVEMENTS

32 00 00 Tree Protection

32 11 00 Base Courses

32 12 00 Flexible Paving

32 16 00 Concrete Curbs, Walks, Aprons, and Pads

32 17 00 Paving Specialties

32 17 13 Parking Bumpers

32 32 00 Retaining Walls

32 90 00 Restoration

32 92 00 Grasses

DIVISION 33 � UTILITIES

33 14 00 Water Utility Transmission and Distribution

YELL 326141 4

33 30 00 Sanitary Sewerage

33 40 00 Stormwater Utilities

APPENDICES

Appendix A Categorical Exclusion Documents

Appendix B USFWS Programmatic Biological Opinion for the Effects to Whitebark Pine from the Parkwide Housing Projects in Yellowstone National Park, Park and

Gallatin Counties, Montana and Park and Teton Counties, Wyoming, May 23, Appendix C Geotechnical Engineering Report Canyon Housing Upgrades, Terracon

Consultants, Inc., November 23, 2020

Appendix D Geotechnical Engineering Report Northeast Entrance Housing Upgrades, Terracon Consultants, Inc., November 23, 2020

Appendix E Geotechnical Investigation Proposed Four-Plex Mammoth Hot Springs

Yellowstone National Park, WY, Braun Engineering Testing, Inc., February 22, Appendix F Wyoming Public Works Standard Specifications, 2023 Edition

Appendix G Northwestern Corporation (Northwest Energy) Authorization for Electric Service

END OF TABLE OF CONTENTS

YELL326141 01 11 00 - 1

112723 SUMMARY OF WORK

Yellowstone National Park YELL 326141

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Work Phases

3. Work Under Other Contracts

4. Government-Furnished Materials

5. Contractor Use of Site

6. Public Use of Site

7. Access During Construction

8. Occupancy Requirements for Buildings

9. Conduct of Operations

10. Work Restrictions

11. Special Construction Requirements

12. Soils and Geotechnical Investigation Reports

13. Unexpected Discovery of Archeological Resources

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Yellowstone National Park:

1. Canyon Government Area: Northwest of Canyon Village along Grand Loop Road and

Norris Canyon Road, Wyoming.

2. Northeast Entrance Government Area: 3.5 miles West of Cooke City, Montana along US

Highway 212 near the existing Northeast Entrance Station.

3. Mammoth Government Area: Mammoth, Wyoming along US Highway 89 near the

Mammoth Community Center

B. The Work consists of:

1. The project includes procurement and construction of modular housing for employees working in the area. Site construction will include grading, roadway construction, drainage, and utility installation including electrical, telecom, potable water, fire suppression and sanitary sewer.

2. Contractor shall be aware of in-person equipment inspection requirements for Yellowstone National Park. Additionally, Contractor shall adhere to material sourcing requirements which require material to be procured from a gravel pit that has passed recent inspections.

Refer to Section 01 71 13 �Mobilization and Demobilization�.

C. Project will be constructed under a single prime contract.

YELL326141 01 11 00 - 2

1.3 WORK PHASES

A. The Work shall be conducted in one phase.

1.4 WORK UNDER OTHER CONTRACTS

A. General: Cooperate with separate Contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate Work of this Contract with work performed under separate contracts.

1.5 GOVERNMENT-FURNISHED MATERIALS

A. Government-Furnished Materials:

1. None anticipated.

1.6 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to work in areas indicated on drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine construction operations to limits of disturbance shown on the Drawings.

2. All staging areas shall be approved by the Contracting Officer.

3. Limit site disturbance, including earthwork and clearing of vegetation, to limits shown on the Drawings.

B. Storage of Materials: Confine storage of materials to designated staging areas as shown on the Drawings or in coordination with the Contracting Officer.

C. Parking: Confine parking to areas as shown on the Drawings or in coordination with the Contracting Officer. Parking off road or on non-vegetated areas is not allowed unless approved by the Contracting Officer.

D. Stockpiling: Confine stockpiling to designated staging areas as shown on the Drawings or in coordination with the Contracting Officer. Maximize the use of previously disturbed areas for stockpiling to minimize ground disturbance.

E. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with

Contracting Officer and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

YELL326141 01 11 00 - 3

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

6. Whitebark pine trees require protection and shall not be disturbed unless authorized by Contracting Officer. Any whitebark pine trees that require relocation shall require approval by Contracting Officer prior to any disturbance. Refer to Section 32 00 00 �Tree Protection�.

F. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

G. Construction Camp:

1. Establishment of housing camps will not be allowed in the Mammoth or Northeast

Entrance Government Areas.

2. Establishment of housing camps will be permitted near Canyon Village. The Contractor has been assigned 15 trailer sites which will have electric, water and sewer hookups.

Activation of water and sewer service is dependent on weather.

a. The Contractor will be responsible for paying rental fees for these sites to the NPS, which will be determined for each construction season (generally May through October). The 2026 rates will be $485.74 / month. The Contractor would also be responsible for paying for the electricity to these sites.

b. Adhere to Park rules, animal deterrent policies, cleanliness policies, and return Site to previous condition at completion of work. These requirements also apply to all Contractor�s employees who may, with prior approval, establish their own camping facilities. The use of campgrounds or other in-park commercial lodging is prohibited.

H. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Contractor shall obtain current rules and regulations for vehicular traffic on park roads from the Park�s Visitor Services Office, which can be reached at (307) 344-2107. Overweight vehicles generally need to be discussed with the Visitor Services Office and Federal Highways Administration (FHWA). FHWA will evaluate capacities of bridges in the Park and inform Contractor if there is an acceptable path for the Contractor to take through the Park and if there are any specific requirements they have to follow. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

1. Contractor is required to submit a travel control plan and haul route for oversize or overweight vehicles to the Visitor Services Office and Contracting Officer for approval.

I. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.

J. Rare, threatened or endangered species: The Contracting Officer will ensure that all project related employees, such as contract employees, be given orientation on how to avoid disturbing or encountering wildlife and how to minimize unavoidable effects or encounters. Orientation will include information about park regulations regarding food storage, disposal of garbage and other

YELL326141 01 11 00 - 4

wildlife attractants, approaching or harassing wildlife, and endangered species protection (plants and wildlife).

K. To minimize possible petrochemical leaks from construction equipment, the Contractor will regularly monitor and check construction equipment to identify and repair any leaks. Equipment will not be serviced or refueled near streams. Storage and refueling of equipment and construction parking shall be at least 150 feet from streams or riparian areas in designated staging areas, unless otherwise approved by the Contracting Officer.

L. Pressure wash and clean all construction vehicles and equipment as specified in Section 01 50 00, �Temporary Facilities and Controls�. Inspections of vehicles and equipment by NPS are required prior to entering the Park.

M. The following conditions shall apply during the Contractor�s stay at the Park:

1. The Contractor shall supply a list of all Contractor and subcontractor employees to the

Contracting Officer.

2. To prevent unnatural attractants to bears, no food, garbage, drinks, trash, or food and drink containers shall be placed outside trailers or buildings, except during actual use. Store lunch pails and all food inside vehicles or job trailers.

3. All trash cans that are not of bear-resistant design shall be located inside trailers or buildings.

4. Waste produced by the Contractor is the responsibility of the Contractor and may not be put in NPS containers.

5. All work site food and drink trash shall be placed in trash cans.

6. All barbecue units shall be stored in trailers and buildings when not in use.

7. Bird feeders are prohibited.

8. Pets are prohibited.

9. Feeding of any wildlife is prohibited.

10. Any mishandling of garbage, food, trash or other bear attractants described above will result in the responsible party receiving a citation subject to a fine and/or court appearance before the United States Magistrate.

N. All costs for bear management actions directly related to mishandling of garbage, trash, foods or other bear attractants shall be at no additional cost to the Government.

O. The Contractor, all employees, and their families present at the Park shall be required to attend bear orientation sessions presented by the NPS.

1.7 PUBLIC USE OF SITE

A. Contractor shall conduct his operations to ensure the least inconvenience to public and current residents of the Canyon, Mammoth and Northeast Government Areas. All traffic on Park Roads must be permitted to pass. If excavation, backfill or paving operations require a temporary closure of a street, the Contractor shall submit a Traffic Control Plan and route traffic on a clearly signed and marked detour. The Contractor will be required to provide, place and maintains signs for all detours.

YELL326141 01 11 00 - 5

1.8 ACCESS DURING CONSTRUCTION

A. Seasonal road closures occur in the Park. Adverse weather may cause short-term closures of the Park. See http://www.nps.gov/yell/planyourvisit/parkroads.htm for the latest information.

B. The Contractor is responsible for clearing snow from the site within the work areas indicated on Drawings and as required to complete the Work. Contractor shall not conduct snow removal activities on Park main roads. Prior to any winter shutdown, all equipment, materials, and stockpiles must be located and adequately marked so they can be easily identified during snow plowing operations. All excavation must be backfilled prior to a winter shutdown.

C. Access into the Park will only be allowed upon presentation of proper identification with prior notification to the Park officials, or by securing gate passes or stickers.

1.9 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Partial Government Occupancy: Government will occupy premises during entire construction period, with exception of areas under construction. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform Work so as not to interfere with Government�s operations.

Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer.

B. New Buildings

1. Government Occupancy of Completed Areas of Construction: Government reserves right to occupy and to place and install equipment in completed areas of building, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the entire project.

a. Contracting Officer will prepare a Beneficial Occupancy letter for each specific portion of the Work to be occupied before Government occupancy.

b. Obtain a Certificate of Occupancy from National Park Service (NPS) before Government occupancy.

c. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed.

d. On beneficial occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of building.

e. On beneficial occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of building.

YELL326141 01 11 00 - 6

1.10 CONDUCT OF OPERATIONS

A. Construction Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 4 business/calendar days in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements, except those specified herein, shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.11 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 8:00 a.m. to 5:00 p.m. local time zone, Monday through Friday, except when otherwise indicated.

1. Alternate Work Hours: Contractor may use alternate work days and hours, including holidays, nights and weekends, for the duration of the Project only if approved in advance by the Contracting Officer.

B. Existing Utilities

1. Existing Utilities: Prior to excavation the Contractor shall first contact One-call of Wyoming and Montana, then the Yellowstone Branch of Information System Management. The Contractor shall have the One-call ticket number ready to provide the Yellowstone Branch of Information System Management.

2. Notify Contracting Officer and utility companies of proposed locations and times for excavation.

3. Construction Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

4. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

5. Utility Contact List:

a. One-call of Wyoming (800) 849-2476

b. One-call of Montana (800) 424-5555

c. Yellowstone Branch of Information Systems Management, Mammoth

1) Phone (307) 344-2470

2) Fax (307) 344-2067

d. Northwestern Energy (Canyon and Mammoth Government Areas) � https://northwesternenergy.com.

e. Flathead Electric (Northeast Entrance Government Area) -https://flatheadelectric.com. (406) 751-4483.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

YELL326141 01 11 00 - 7

1. Notify Contracting Officer not less than four (4) business days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer�s written permission.

3. Hours and length of Utility Shutdowns: Shutdown durations may vary seasonally and for each site. Unless otherwise approved by Contracting Officer, limit shutdown duration to no more than 24 hours during low flow months and no more than 12 hours during high flow months. Low flow months are October through April and high flow months are May through September).

D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within the project site.

1.12 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Management and Communication Software: Software administered by the National Park Service (NPS) shall be used to manage communication and document sharing during construction.

1. See Section 01 31 00 "Project Management and Coordination" for requirements on using NPS project management and communication software.

B. The Contractor is responsible for maintaining appropriate safety measures to secure the site and ensure the safety of visitors and Park staff in areas adjacent to Work.

C. Install tree protection and temporary fencing to protect trees impacted by construction, unless otherwise designated for removal by the Contracting Officer. Tree protection shall be completed in accordance with the Drawings and Section 32 00 00 � �Tree Protection�.

D. Minimize noise and artificial light during nighttime hours to reduce disturbance to wildlife.

E. The Contractor shall adhere to the mitigations listed in the Categorical Exclusion Documents included with these Contract Documents as Appendix A. These mitigations include, but are not limited to, the following:

1. Wetlands to be avoided will be marked on the Drawings and flagged prior to start of work.

Contact Contracting Officer and YNP Vegetation Program to schedule flagging. There is one wetland area at the Canyon Government Area that will be impacted by the road construction. This disturbance is covered under U.S. Army Corps of Engineers Nationwide Permits and all conditions associated with that permit shall be adhered to by the Contractor.

2. UTE LADIES'-TRESSES Conservation Measures: Herbicide spot treatments for infrastructure activities will maintain a minimum distance of 3.3 ft from Ute ladies-tresses.

Ground-based broadcast applications will maintain a minimum distance of 10 ft from Ute Ladies-tresses. Train project personnel to identify the species to ensure project activities do not result in adverse effects. Limit soil disturbance and compaction by limiting the use of mechanical equipment such as heavy equipment and vehicles. Control runoff of soil during project activities and avoid using machinery in wet soils and areas prone to ruts.

Minimize creation of dust when using mechanical equipment (heavy equipment and vehicles).

3. YELLOW-BILLED CUCKOO: Contractor will participate in orientations on how to avoid disturbing or encountering a yellow-billed cuckoo and other wildlife, including regulations regarding vehicle speed limits, food storage, disposal of garbage and other attractants, and approaching or harassing wildlife. Any observation of a yellow-billed cuckoo shall be reported to the Contracting Officer and appropriate action taken to reduce potential effects.

YELL326141 01 11 00 - 8

4. GRIZZLY BEAR Conservation Measures: Contractor will participate in orientations on how to avoid disturbing or encountering bears and other wildlife, including regulations regarding vehicle speed limits, food storage, disposal of garbage and other attractants, and approaching or harassing wildlife. Unless authorized, workers in YNP will avoid designated closure areas that have high historic use by grizzly bears during spring and summer, as well as closure areas around active bear dens to minimize wildlife disturbance and human-wildlife interactions. During and after management activities, managers will take prevention and restoration measures to avoid the introduction of exotic invasive species and discourage the establishment of herbaceous foods such as clover.

5. CANADA LYNX Conservation Measures: Contractor shall participate in orientations on how to avoid disturbing, approaching, or harassing lynx and other wildlife. Any observation of Canada lynx shall be reported to the Contracting Officer and appropriate action would be taken to reduce potential effects.

6. WHITEBARK PINE Conservation Measures: See Section 1.12 F below.

7. SUCKLEY�S CUCKOO BUMBLE BEE Conservation Measures: To the extent feasible, no nectar feeding plants or host plant species for Suckley�s Cuckoo Bumble Bee will be removed. If habitat disturbance is necessary, adjust the timing of activities in areas containing plants used by Suckley�s Bumble Bee to avoid interfering with breeding or feeding. To the extent feasible, avoid using pesticides or herbicides in Suckley�s cuckoo bumble bee habitat that could result in direct mortality or eliminate host and nectar plants.

If pesticide application is necessary near Suckley�s cuckoo bumble bee habitat, select chemical formulations specific to the targeted pest, time applications to avoid activity periods, establish buffers, and minimize drift to non-target areas by direct ground application. All chemical formulations shall be approved by the Contracting Officer.

8. MONARCH BUTTERFLY Conservation Measures: To the extent feasible, no nectar feeding plants or host plant species for monarch butterflies or caterpillars will be removed during management activities. If habitat disturbance is necessary, adjust the timing of activities in areas containing plants used by monarchs to avoid interfering with breeding or feeding. To the extent feasible, avoid using pesticides or herbicides in monarch butterfly habitat that could result in direct mortality or eliminate host and nectar plants. If pesticide application is necessary near monarch butterfly habitat, select chemical formulations specific to the targeted pest, time applications to avoid monarch activity periods, establish buffers, and minimize drift to non-target areas by direct ground application. All chemical formulations shall be approved by the Contracting Officer.

9. WOLVERINE Conservation Measures: Contractor shall participate in orientations on how to avoid disturbing or encountering wolverines and other wildlife, including regulations regarding vehicle speed limits, food storage, disposal of garbage and other attractants, and approaching or harassing wildlife. \Any observation of wolverines within the proposed action area shall be reported to the Contracting Officer and appropriate action would be taken to reduce potential effects.

10. All equipment and tools shall be cleaned completely prior to entering the work zone to prevent the spreading of invasive species. Equipment shall be inspected for compliance.

11. All erosion and sediment control devices shall be adequately maintained to ensure continued performance of their intended function. Those that have sustained damage or have reached their capability shall be replaced or maintenance performed.

12. All material brought into the Park from outside sources must be certified weed-free fill from a recently certified facility. Please contact Yellowstone Center for Resources for the most up to date list of certified facilities.

13. Work crews shall adhere to bear safety and food storage regulations.

YELL326141 01 11 00 - 9

14. If previously unknown archeological or paleontological resources are discovered, all ground disturbing activities within the immediate vicinity (300 ft) shall be halted and the Park Archaeologist and Contracting Officer notified immediately.

15. In the event human remains or other items that fall under the purview of the Native American Graves Protection and Repatriation Act (NAGPRA) are discovered, all work on the Project must stop and the Contracting Officer and Park Archeologist contacted immediately. As required by law, the coroner will be notified first. All provisions outlined in the NAGPRA (1990) will be followed.

16. To avoid impacts to migratory birds during the nesting season, vegetation or tree removal activities shall occur outside of March 1-August 15th for raptors and May 1-August 15th for songbirds. If within the March 1 � August 15th window a nest is suspected, because of observed structures or behaviors (e.g. large collections of sticks or smaller plant material in trees, birds carrying food into nest-like structures), the Contracting Officer shall be notified to ensure coordination with the NPS Bird Program Manager.

17. Project shall comply with NPS and Yellowstone National Park lighting guidelines. This will include but is not limited to low-level lighting, minimized glare, downward focused light fixtures, and energy efficient light sources.

18. To minimize the amount of ground disturbance, staging and stockpiling shall be located in previously disturbed areas if possible. All staging and stockpiling areas shall be approved by the Contracting Officer and returned to pre-construction conditions following construction. Fencing is required around construction zones and staging areas.

19. To the extent practical, work shall be scheduled to avoid construction activity and construction related delays during peak visitation times. No holiday or night time work shall be allowed. Weekend work shall not be allowed unless authorized in writing by the Contracting Officer and Park Superintendent.

20. Project shall comply with NPS and Park lighting guidelines to reduce impacts to the night sky and wildlife. This will include, but not be limited to, low-level lighting, minimized glare, downward focused lighting fixtures, and energy efficient light sources such as low-pressure sodium lamps.

21. Line located must be completed before any excavation work begins. The Contractor is responsible for calling 811.

F. The Contractor shall adhere to the Whitebark Pine and General Conservation Measures listed in the United States Fish and Wildlife Service (USFWS) Programmatic Biological Opinion for the Effects to Whitebark Pine from the Parkwide Housing Projects in Yellowstone National Park, Park and Gallatin Counties in Montana, and Park and Teton Counties in Wyoming; dated May 23, 2025 included with these Contract Documents as Appendix B. These measures include, but are not limited to, the following:

1. Pre-project surveys and marking will be conducted by NPS to identify whitebark pine. The

Contractor shall be aware of all marked whitebark pine.

2. Ground disturbance from heavy equipment shall be avoided within whitebark pine stands and within 10 meters of known whitebark pine trees.

3. If using heavy equipment in a whitebark pine stand cannot be avoided, equipment shall be used sparingly and will be cleaned before entering and leaving work sites to prevent the spread of invasive species, pathogens, and pests.

4. Avoid off road motorized travel in whitebark pine habitat.

5. When working in whitebark pine stands, work will not introduce or spread Ribes species that are an alternate host for white pine blister rust.

6. Herbicide spot treatments for infrastructure activities shall maintain a minimum distance of 1 meter from a whitebark pine tree. Ground-based broadcast applications shall maintain a minimum distance of 3 meters from the trunk of a whitebark pine tree.

YELL326141 01 11 00 - 10

7. Train project personnel to identify the species regardless of the whitebark pine age class to ensure project activities.

8. Wherever possible, avoid removing or damaging healthy, unsuppressed whitebark trees.

Limit soil disturbance and compaction by limiting the use of mechanical equipment.

Control runoff of soil during project activities and avoid using machinery in wet soils and areas prone to ruts.

9. Minimize creation of dust when using mechanical equipment (heavy equipment and vehicles).

1.13 SOILS AND GEOTECHNICAL INVESTIGATION REPORTS

A. Geotechnical Reports appended to this Project Manual are intended to supplement rather than serve in lieu of Contractor�s own investigations. They are provided for Contractor�s information and convenience as appendices, but are not part of the Contract Documents.

1. Canyon Government Area: The Geotechnical Engineering Report Canyon Housing

Upgrades, dated November 23, 2020 prepared by Terracon Consultants, Inc.

2. Northeast Entrance Government Area: Geotechnical Engineering Report Northeast

Entrance Housing Upgrades, dated November 23, 2020 prepared by Terracon Consultants, Inc.

3. Geotechnical Investigation Proposed Four-Plex Mammoth Hot Springs Yellowstone National Park, WY dated February 22, 1989 prepared by Braun Engineering Testing, Inc.

is available as an appendix with this package and is provided for the Contractor�s information only.

B. In case of conflict between report and drawings or specifications, the drawings and specifications govern.

1.14 UNEXPECTED DISCOVERY OF ARCHEOLOGICAL RESOURCES

A. The Contractor is not expected to encounter archeological remains in the area. However, if any concealed archaeological or paleontological resources are encountered, the Contractor must cease work within 50 feet of the discovery immediately and notify the Contracting Officer and Park Archeologist immediately. The Site and the artifacts need to be assessed to determine if an archeological site has been unexpectedly uncovered. Work in the discovery area cannot resume until Contractor obtains approval from the Contracting Officer. Work may proceed outside of the discovery area.

B. Any and all historic objects discovered during this Project shall be turned over immediately with provenience information to the Contracting Officer.

C. In the event that human remains are discovered during construction activities, all activities in the vicinity of the discovery must stop and the Contracting Officer shall be contacted immediately.

If the remains are determined to have no forensic value and are of Native American descent or an historical person, all provisions outlined in the Native American Graves Protection and Repatriation Act (1990), as amended, will be followed.

YELL326141 01 11 00 - 11

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

YELL 326141 01 26 01 - 1

012721 CONTRACT MODIFICATION PROCEDURES

Yellowstone National Park YELL 326141

SECTION 01 26 01 � CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Costs incurred in support of all of a contractor�s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager (PM), Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

YELL 326141 01 26 01 - 2

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.

The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: The hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:

1) Social Security

2) Medicare

3) Workers Compensation � Policy and company calculation to be made available.

4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.

YELL 326141 01 26 01 - 3

5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.

6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.

Include as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder�s Risk Insurance: Covers the contractor�s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may

YELL 326141 01 26 01 - 4

utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government�s form.

3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor�s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.

5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. Labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for work being performed.

2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.

3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

YELL 326141 01 26 01 - 5

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.

6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.

8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.

Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead������10% Profit������8.25%

2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

YELL 326141 01 26 01 - 6

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 012601

YELL 326141 01 27 00 - 1

012721 DEFINITION OF CONTRACT LINE ITEMS

Yellowstone National Park YELL 326141

SECTION 01 27 00 � DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. This section explains in general, what is and is not included in a contract line item, and limits or cut off points where one item ends and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 GENERAL

A. The Contractor shall perform all work necessary to construct and deliver to NPS a complete

Project conforming to the Contract Documents. Details not shown or provided in the Drawings and Specifications, but required for a complete and operational Project, shall be included in the

Contract Price as approved by NPS.

B. The contract line items of work described hereunder, paid pursuant to the Agreement for the

Contract items of work identified in the Pricing Schedule, shall constitute full compensation for furnishing all labor, materials, tools, equipment, services, and incidentals as necessary to perform all work in the manner and time prescribed in the Contract Documents, inclusive of all provisions in the Contract Documents, complete and in place as shown on the Drawings, and as otherwise may be directed by NPS.

C. Progress Payments will be made as work progresses, conforming to the provisions of the Contract

Documents.

3.2 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item Number [0001] Canyon Government Area Site Improvements

1. This item consists of site improvement work indicated on the Contract documents including clearing and grubbing, temporary facilities and controls, erosion control, mobilization and demobilization, earthwork and grading, riprap placement, concrete and asphalt work, utility work, and soil preparation for restoration.

YELL 326141 01 27 00 - 2

2. Measurement for payment will be determined on percent of construction complete.

3. Payment will be made at the contract lump sum price.

B. Contract Line Item Number [0002] Canyon Government Area, Standard Modular Building Units

1. This item consists of modular building units as indicated on Drawings.

2. Measurement for payment will be per unit.

3. Payment will be made at the contract price per unit.

C. Contract Line Item Number [0003] Canyon Government Area, ABAAS-Compliant Modular

Building Units

1. This item consists of ABAAS-compliant modular building units as indicated on Drawings.

2. Measurement for payment will be per unit.

3. Payment will be made at the contract price per unit.

D. Contract Line Item Number [0004] Northeast Entrance Government Area Site Improvements

1. This item consists of site improvement work indicated on the Contract Documents including clearing and grubbing, temporary facilities and controls, erosion control, mobilization and demobilization, earthwork and grading, riprap placement, concrete and asphalt work, utility work, and soil preparation for restoration.

2. Measurement for payment will be determined on percent of construction complete.

3. Payment will be made at the contract lump sum price.

E. Contract Line Item Number [0005] Northeast Entrance…

This is the start of the file's text. The full file is on GovTribe.