B09_Amendment_3_estimated_cut_and_fill_quantities_0003.pdf
PDF 82 KB Posted
- Attached to
- YELL 326141 YELLOWSTONE MODULAR HOUSING
- Solicitation number
- 140P2026R0078
About this file
This document is a site grading and earthwork quantification summary presenting cubic yard calculations for three distinct project areas: Mammoth, NE Entrance, and Canyon. Each section provides comparative data on rough grading to finish grade (EG) conditions, measuring cut volumes, fill volumes, and net cut or import/export quantities in cubic yards.
The Mammoth area shows a net export of 1,294.79 cubic yards, with 1,717.41 cubic yards of cut and 422.63 cubic yards of fill. The NE Entrance area demonstrates a net export of 1,936.71 cubic yards from 2,293.67 cubic yards of cut and 356.95 cubic yards of fill. The Canyon area requires net fill (import) of 1,819.86 cubic yards, calculated from 1,880.1 cubic yards of cut and 3,699.95 cubic yards of fill. All calculations exclude foundation excavation outside the building envelope and do not account for asphalt, concrete, base, and subbase material quantities. Work scope includes pavement and base section punching, sidewalk preparation, parking areas, curb and gutter work, and v-pans as applicable to each site area.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .