This document is a Questions and Answers (Q&A) amendment for a federal solicitation (Solicitation No. 140P2025R0080) for a water infrastructure project at Organ Pipe Cactus National Monument. The solicitation involves replacing and installing two water storage tanks (50,000 and 100,000 gallon capacities), water distribution system improvements, and associated infrastructure work across multiple campground locations. Key details include: the procurement is a full and open competition (not a small business set-aside), with a 390-calendar day performance period, and proposals are to be submitted electronically. The project scope includes water tank demolition and replacement, utility installations, water service line replacements, and related electrical and SCADA system work, with specific considerations for environmental preservation, wildlife protection, and park operations continuity.
The Q&A document addresses numerous technical, procedural, and administrative questions from potential offerors, covering topics such as key personnel requirements, submission guidelines, small business participation, tank specifications, environmental constraints, and construction logistics. Notable points include: key personnel can serve multiple roles with some restrictions, CPARS and previous performance questionnaires are acceptable for past performance evaluation, photo documentation can be submitted via project management software, and there are specific guidelines for handling protected plants and wildlife during construction. The project will require coordination with multiple agencies, including US Border Patrol and Arizona Department of Transportation, and must minimize disruption to the park's primary revenue-generating campground during peak season.
View the file
Other files for this federal contract opportunity
Show all 43
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140P2025R0080 / ORPI
240841 As of 9/18/2025
Question No. Sheet or Reference Question Response Amendment Answered
1 SF1442 Block 13, item A
SF1442, Block 13, item A indicates “Sealed offers in original and 1 copies…” Section L indicates to submit (1) one electronic copy of Volume I and II. Can the NPS please confirm that offerors should follow the instructions in Section L and submit one electronic copy of each volume via email?
Correct follow instructions in section "L". Submit one electronic copy of each volume via email
2 Section B – Price Schedule
Section B – Price Schedule is provided on RFP page 8. Within this section, it states, “Please complete Attachment XX Contract Price Schedule (include this sentence if not using table below).” Can the NPS please clarify if offerors should provide pricing information in Section B or the separately-provided Attachment 5D Excel file? Also, are offerors required to submit the Excel file?
They are the same please use either one
3 Section L, FAR 52.215-20
Section L includes FAR 52.215-20 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA AND DATA OTHER THAN CERTIFIED OR PRICING DATA (NOV 2021) on RFP page 59. However, Section L, Volume II, Section B states, “Also provide a separate Schedule of Values (SOV) for each line item in the Section B Contract Price Schedule.” Can the NPS please clarify if Certified Cost data is required or if the SOV is sufficient?
A Schecule of values is not required to be included in your intial proposal. Certfied cost and price data is not required.
Section L, Subfactor 1B – Key Personnel
Experience
Section L, Subfactor 1B – Key Personnel Experience does not provide any instruction related to the form to be used for this submittal, though we see Attachment 4C Key Personnel Resume Form is provided. Are offerors required to use the Attachment 4C form, or can Key Personnel resumes be provided in a different format?
We did not require a specific format in the first solicitation. Key Personnel Resumes may be submitted in other formats.
Section L, Subfactor 1B – Key Personnel
Experience
Section L, Subfactor 1B – Key Personnel Experience does not provide specific instructions on the key personnel positions that should be submitted within this subfactor of the proposal response. Can the NPS please clarify if offerors should submit key personnel experience for the four positions identified in Section H, Special Requirement 4: Key Personnel (RFP page 17)?
This is what I have in the section L&M from the first solicitation last year: Did we not carry over this language? SUBFACTOR 1B – KEY PERSONNEL EXPERIENCE: Submit resumes for key personnel as identified in Section H of this solicitation and listed below.
All personnel proposed are subject to substitution requirements contained in this solicitation. There is no preprinted form for this submittal.
•Project Manager •Superintendent •On-site Quality Control Specialist •On-site Safety Specialist
Key trades include the following:
•Utility installation •Tank installation •Well development
Section H, Special Requirement 4: Key
Personnel (RFP page 17)
Section H, Special Requirement 4: Key Personnel (RFP page 17) identifies four position requirements for this project: 1) Project Manager, 2) Job Site Superintendent, 3) Quality Control Manager, and 4) Safety Manager. Further, Section 01 40 00, 1.5 Quality Assurance, paragraph B. Contractors Quality Control Staff, item 1 states, “The Contractor’s Quality Control Supervisor may also perform other duties.” Will the NPS confirm that the Quality Control Manager may also serve as the Safety Manager?
Yes, the Quality Control Supervisor and Safety Manager can be the same individual.
7 Section L, Subfactor 2B – Schedule
Regarding Section L, Subfactor 2B – Schedule, will the NPS provide an NTP date to be used for the purpose of the proposal?
For the purpose of proposing you schedule assume a NTP date of : March 1, 2026.
Section H, Special Requirement 4: Key
Personnel (RFP page 17)
Are offerors required to complete and return Section H, Special Requirement 4: Key Personnel (RFP page 17) with our proposal response? If so, can the NPS please clarify what volume and section/subfactor of our response should include this page?
If it is structured like the first solicitation this should be under subfactor 1B Key Personnel Experience.
9 Section L, Factor 4
– Past Performance
Regarding Section L, Factor 4 – Past Performance, will the NPS respectively consider allowing offerors to submit CPARS evaluations and/or previously completed Past Performance Questionnaires from our client references to satisfy the requirements outlined in Factor 4? Requesting the completion of a separate, duplicate Past Performance Questionnaire for each contract we pursue places an undue burden on our client references. Thank you in advance for your consideration.
Yes, CPARs and/or previously completed Past Performance Questionnaires will be considered.
Section L, paragraph F, Volume II –
Business and Price, item 2. Organization
Section L, paragraph F, Volume II – Business and Price, item 2. Organization states, “Include a Table of Contents with tabs for hard copy formats…” Per Section L, paragraph D, it states, “Proposals shall be submitted via email.”
Can the NPS confirm that no hard copies are required despite this reference to “hard copy formats”?
No hard copies of the proposal are required.
11 Section L/M Volume I
Section L references Volume I as “Technical Proposal” while Section M references Volume I as “Non-Price Proposal.” Can the NPS please clarify how offerors should refer to Volume I?
Volume 1 will be refered to as "Techinal Proposal" 4
Question No. Sheet or Reference Question Response Amendment Answered
Section L/M, Small
Business Participation
Section L, Small Business Participation, states, “All Offerors (both other than small businesses and small businesses) shall submit Small Business Participation documentation that address the evaluation criteria defined in the Small Business Participation factor contained in section M of this solicitation.” However, Section M states the same requirements: “All Offerors (Other than small businesses) shall submit a Small Business Participation Document that addresses the evaluation criteria in the Small Business Participation Factor contained in Section M of this solicitation.” Can the NPS provide additional criteria/instructions to allow offerors to prepare a response for Small Business Participation?
If an offeror is a large business they are required to submit a Subcontracting Plan only. If an offeror is a small business they are only required to submit a Small Business Participation Plan. Large Businesses are not required to submit a Small Business Participation Plan and Small Businesses are not required to submit a Subcontracting Plan.
Section L, Small Business
Subcontracting Plan, RFP page 66, Section L, Small Business Subcontracting Plan, RFP page 66, provides NPS subcontracting goals for FY2024. Can the government please provide current subcontracting goals?
FY 24 goals are correct. The Dept did not release an update for FY25.
14 Attachment_5E The RFP files include B08_Attachment_5E_LmtOnSubconRpt_REQD; however, there are no instructions in Section L related to this form. Can the NPS please clarify if this form is required with proposal responses or if it is a post-award reporting requirement?
This is a report that is used post award when submittting invoices. No action required for solicitation.
15 Amendment 0004, Q&A #5, Section L
Amendment 0004, Q&A response number 5, references personnel positions and key trades, which are not currently included in Section L. We concur that this information was previously included in Solicitation No. 140P2024R0150;
however, the Section L provided with the new solicitation (140P2025R0080) does not include the same level of detail for Subfactor 1B – Key Personnel Experience or most of the other Factors/Subfactors (e.g., Subfactors 1A, 2A, 3A, 3B and Factor 4). It appears that Section L has been replaced with the exact same language as Section M. Please advise if we should follow the new Section L or if the detailed requirements will be added.
Follow the new Selection L
16 SF30 Forms
All four amendments (0001–0004) show the same effective date of 08/06/2025 in Block 3 of the SF30 form, even though they were actually issued on different dates in August. When offerors complete Block 19 of the SF1442 to acknowledge the amendments, should we list 08/06/2025 for each one (as shown on the SF30) or use the actual issue dates posted on SAM?
The effective dates for Amendments 01-04 are as follows:
Amendment 0001: August 13, 2025 Amendment 0002: August 19, 2025 Amendment 0003: August 21, 2025 Amendment 0004: August 27, 2025
17 Section 331623.01 - Section 331623.02
Section 01-1100-1 Summary of Work 1.2 B The Work includes the following “two welded stainless steel water storage tanks.” However, Sections 331623.01 Steel Storage Tank – 50,000 gallon and Section 331623.02 Steel Storage Tank – 100,000 gallon both reference in Section B Design Requirements “tank shall confirm to the AWWA Standard for “Welded Carbon Steel Tanks for Water Storage.” Please confirm the material of construction for the 50K and the 100K tanks.
Refer to the plans and technical specifications (div 33) for specific requirements, not the summary of work.
18 We'd like to request a 2-week extension on the due date so we can review RFIs responses and prepare an accurate price proposal for this solicitation.
A due date extension will be provided by amendment. 5
19 Is this project small business set as side? No This is a full and open solcitation 5
Section L, Factor 1
– Experience & Factor 4 - Past
Experience
For Volume 1, Subfactor 1A and Factor 4, how many projects are we permitted to showcase? 3 Projects
Section L/M, Small
Business Participation
Is there a specific form that needs to be completed for the Small Business Participation Plan, or should this be submitted as a narrative response? If a form is required, could you please provide it?
Please see Amendment 05
22 SF1442 Block 13, item A
For clarification regarding email submission: Can both volume attachments be included in a single email, or should they be sent separately?
Either approach is acceptable. 5
B08_Attachment_4 D_Solit_PSD_Vol_
1_PastPerf
Would it be possible to receive a Word document copy of the Past Performance document (Attachment 4D)? Please see Amendment 05
24 Tank Demo drawings
Do the existing water tanks have concrete ring walls? If so, please provide details. No 5
25 Tank Demo Drawings
Do the existing water tanks have sand and gravel beneath them? If so, please provide details. Historical drawings for the tanks indicates a sand custion underneath. No dimensions were found for the 50K gallon tank. For the 100K gallon tank, the original as builit drawing shows the sand cushion under a slope at the tank bottom where it is 4" thick at the walls and 9" thick at the tank center. This information was not independently verified during design of this project.
26 C704, C705, C706, C713, C714, C715
Please provide the scale for drawings C704–C706 and C713–C715. This information is not available at this time. You may use the available dimensions on the drawings for estimation purposes.
27 C711 Drawing C711 does not provide an elevation based on the topography for the new 100,000-gallon tank. Instead, it uses an arbitrary elevation of 100.00 for the tank floor. Please provide the actual elevation relative to the topography shown on C711.
This information is missing from the plans. However, the approximate elevation found on the site plan and the dimensions in the drawing details are believed to be sufficient for bidding purposes. Survey and control point information can be set after contract award. 5
28 C701 & C702 Drawing C701 notes an existing 4" AC pipe to be protected in place, while drawing C702 indicates it should be removed. Is this line to be removed, or is it mislabeled? C702 shows two existing lines descending the slope, whereas C701 shows three. Please clarify.
Sheet C701 is correct that the 4" AC pipe may be protected in place except as noted in sheet G103 note 5. Sheet C701 shows the new 6" campground distribution line, while sheet C702 shows existing lines only. 5
29 C702 Drawing C702 does not provide an elevation based on the topography for the new 50,000-gallon tank. Instead, it uses an arbitrary elevation of 100.00 for the tank floor. Please provide the actual elevation relative to the topography shown on C702.
This information is missing from the plans. However, the approximate elevation found on the site plan and the dimensions in the drawing details are believed to be sufficient for bidding purposes. Survey and control point information can be set after contract award. 5
30 Several drawings Where the phrase "Bypass Existing" is used, do you mean "Existing Bypass"? Is "bypass" intended as a noun or a verb?
Verb 5
31 Contract Price Schedule
The schedule does not mention "North Water" or "South Water," although drawings with these names exist. Are these included in the base bid?
A summary of locations included in each CLIN in the bid schedule is shown on sheet C102, with delineation between CLINs 3 and 4 shown on the plan & profile sheets. 5
32 Contract Price Schedule
Please indicate the limits of each bid item directly on the drawings or provide clarification. A summary of locations included in each CLIN in the bid schedule is shown on sheet C102, with delineation between CLINs 3 and 4 shown on the plan & profile sheets. 5
33 C-206 Detail A Detail A indicates two 8" gate valves, but only one is shown. Where is the second valve located? *Internal Note: Detail shows a 4" gate valve before 8x4 reduce, plan calls out 8" gate valve at same location.* one 8" gate valve is upstream of 8x8tee, one gate valve is stub side of tee
34 C502 Drawing C502 shows the fiber optic conduit under the pavement, while the IC drawings show it off the pavement.
Which is correct?
Sheet C502 refers to a shared trench with the water main, as called out on sheet IC104-IC106. Sheet IC112 includes trench detail for direct bury conduit only. 5
35 C503 Are water meters included on all 1" service lines? No. The drawings call out which 1" service lines require meter installation. 5
36 C303 & C503 Note 2 on drawing C303 states the agency will remove and replace the spigots and refers to drawing C503. However, the term "spigots" is not used on C503. Please clarify.
"Spigot" is. see detail 01C503 - Accessible Water Spigot 5
37 C210–C213 & C222 Drawings C210–C213 include Note 5, which states to place the water meter vault at the end of the 2" fire line. This note does not appear on drawings C208, C209, or C222. Are meter vaults required for the fire lines on these pages?
No meter vaults on C208,C209
38 C222 The two 2" fire service lines have no associated notes. Are these lines to be connected to anything? Yes, notes on C222 "Tie-in to existing 2" fire SVC, "2" fire svc connect to existing backflow preventer", etc. 5 40 C302 The 2" water service and 2" fire line do not show any valves or meters. Is this intentional? Yes 5 41 C507 The second part of Note 46 appears inappropriate. Please explain. End of note 44 - Anchored adjustable pipe support bolted to pole w/ 2 ea. 5/8" lag bolts 5
42 C508 Detail B If a 3" blind flange is attached to the bottom of the 3" riser pipe, how is the 3" support pipe (part of the brace system) connected?
Assume a flanged connection between the tee and the 3" pipe. 5
43 C507 Please provide a detail showing the 2" galvanized steel pipe penetration through the fiberglass cover. See Detail F page C508 5 44 C507 Please provide a detail of the 2" galvanized steel pipe pentration through the fiberglass cover. See Detail F page C508 5
45 C508 Detail D To fasten the 2" pipe strap to the 7/8" bolt, a 1/2" hole must be drilled through the bolt, leaving 3/16" of curved bolt on each side. Is this acceptable?
Means and methods are up to the contractor provided they do do not conflict with plans or specifications. 5
46 C507 Section 1 After welding the knee brace to the galvanized pipe, can spray galvanizing be used to touch up the welded area? Means and methods are up to the contractor provided they do do not conflict with plans or specifications. 5 47 C507 Section 1 Please provide specifications for the required signs, including size, lettering dimensions, and color. Should have 10 14 00 within specs? 5 48 C508 Are the bollards required to be painted? Per C507, yes. "Traffic yellow" 5
50 C412 & C413 Several notes reference the "edge of pavement," but there is no indication that the roads are asphalt. Drawings C408 and C409 show pavement in part of the campground. Please provide a drawing showing all asphalt pavement areas.
Reference Legend on G103, See sheets C206-C304 & C404-C411
51 C410 & C411 These drawings are labeled "South Water." Are they part of CLIN 3, Twin Peaks Campground? See Sheet C403 which shows interface for CLIN 3 and CLIN 4. 5
52 C412 & C413 A note states to remove the existing pipe when exposed in the new trench. What type and size is the existing pipe? The original campground water system had a 4" line down the center of the campground, branching to 2" lines to comfort stations and
3/4" lines to hydrants. The location of existing lines was located and shown on the plans, but the size of all lines was not independently verified during design of this project.
53 C412 & C413 The term "shut-off valve" is used, but no detail is provided. Do you mean a buried Corp Stop or a Corp Stop with valve box?
This refers to a valve installed at each lateral to allow branch to be shut off by operators if needed. 5
54 C505 Can internal restrained couplings (e.g., Eagle Loc900, Certa Lok, Diamond Lok21) be used instead of the external retaining system?
For the purpose of the bid, follow the plans and specifications. During performance of the contract, use of comparable products can be requested in accordance with 01 67 00. 5
55 C412 & C413 Are all service lines in the campground (excluding the Comfort Station) the same length from the main line? See sheet C414 which provides lengths of pipe sections and coordinates for branches in the campground. 5
57 C413 The third row from the top shows a 2" x 1" service line pointing to two comfort stations, but does not mention the station lines. Are there two lines at each comfort station? Please ensure consistency across drawings.
There is one service line for each comfort station. 5
58 C410 At stations 41+07 and 42+47, new services with spigots are indicated, but the same locations also show removal and replacement of spigots. Please clarify.
Removal of service and spigot and replacement of service and spigots is the intention. 5
60 South Water System You state there are currently two parallel waterlines, one of which is to be removed and replaced with a new 6" C900 pipe. What is the size and type of the pipe being removed, and what is the distance between the two existing pipes?
Per sheets C404-C407, existing distribution line is 4" C900.
61 C407, Note 5 To properly bid this scenario, an additional line item should be added to the Contract Price Schedule Template to address the cost if CLIN 3 is not funded. 5
62 General What type of pipe is used for the existing services? Typically the existing water service lines are 1-inch PVC. 5
63 C701 & C702 Drawing C702 notes removal of the 3" Campground Distribution Line, while drawing C701 states to protect it in place. Please clarify.
Removal of this section of AC pipe is not required except as noted in sheet G103 note 5. 5
64 C704, Item 17 Item 17 should specify a 6" gate valve, not a 4" gate valve. Sheet C704 item 17 should refer to a 6" gate valve due to the size of the pipe. 5
65 C406 At station 14+97.73, a blow-off is referenced, directing to Drawing C504, Detail 2. However, Detail 2 appears to show a fire hydrant, not a blow-off. Please confirm whether a separate blow-off detail is available or provide the appropriate detail for the blow-off installation.
Blowoff hydrant is detail 1 on sheet C506
Section M, C Evaluation Factors,
3. Volume II, G.
Small Business Sub
Plan
Please provide the required Small Business Subcontracting Plan form to be completed and submitted with Volume 1. See Amendment 05
Section M, C Evaluation Factors,
3. Volume II, F.
Small References
Please provide the General References form that must be complete and submitted with Volume 1. See Amendment 05
68 Can excess spoils from excavations be left onsite or do they need to be hauled offsite for disposal? Per 01 74 19, transport waste materials off Government's property and legally dispose of them. 5
Box 11 of the Solicitation, Offer, and Award document indicates 577 calendar day completion period but Section F – Deliveries and Performance 52.211-10 Commencement, Prosecution and Completion of Work states 390 calendar days. Please confirm the number of allowed for the contract performance.
390 days.
70 33 16 23.01 and 33 16 23.02
Please see the bid document “Basis of Design Report”. This document is attached for your convenience. The documents states: “Tanks will be glass-fused steel tanks”. Please see specification sections 33 16 23.01 and 33 16
23.02. Both spec sections are headed “Welded Steel Water Storage Tank”. Please verify that welded steel is the preference.
The basis of design report is a preliminary design document. The project plans and specifications provide the requirements for the storage tank. 5
33 16 23.01 – 50K Tank - g. 3 – 1.5
Quality Assurance B:
This indicates that the tank and finish have a 10-year warranty. See pg. 4 – 1.8 Guarantee A:
- This states that the tank and various appurtenances be guaranteed for a period of one (1) year.
- We can only warrant the tank and coating for a period of one (1) year after the tank is filled with water.
It is anticipated that the tank manufacturer's warranty would provide coverage beyond the installing contractor's warranty.
Pg. 5 – 3a:
“Aluminum Access Ladder”
This indicates an aluminum exterior ladder. We would prefer to build the exterior ladder with A36 carbon steel and paint it with the same system and color as the exterior. Please Verify.
For the purpose of the bid, follow the plans and specifications. During performance of the contract, use of comparable products can be requested in accordance with 01 67 00. 5
Pg. 7 – 3.2 A 5 – “Seal Weld All
Water Compartment Joints”.
The AWWA code requires that the lapped surfaces of the tank roof be welded on the top side. The underside of the lapped roof is not welded. The underside of the tank roof is coated and is a minimum of 12” above the high-water level. We ask that AWWA be adhered to.
Comply with AWWA D100 Section 8 for welding procedures and requirements as stated in 33 16 23 paragraph 3.2.A.1.
75 Pg. 8 – 3.4 C1:
We suggest using AWWA C652 Method II. This is a 200 ppm, high concentration of chlorine, sprayed on the submerged surface of the tank walls and floor. It must sit for 30 minutes before introducing chlorinated water into the tank. After the bac-t’s are taken the tank can be put immediately into service. The important factor to this method is that the water does not need to be removed and wasted; it can go immediately into the system.
For the purpose of the bid, follow the specifications. During performance of the contract, an alternate method may be proposed as value engineering.
See Specification Section 33 16 23.02
– 100K Tank - Pg. 3
– 1.5 Quality Assurance B:
This indicates that the tank and finish have a 10-year warranty. See pg. 4 – 1.8 Guarantee A: - This states that the tank and various appurtenances be guaranteed for a period of one (1) year. - We can only warrant the tank and coating for a period on one (1) year after the tank is filled with water.
It is anticipated that the tank manufacturer's warranty would provide coverage beyond the installing contractor's warranty.
Pg. 5 – 3a:
“Aluminum Access Ladder”
This indicates an aluminum exterior ladder. We would prefer to build the exterior ladder with A36 carbon steel and paint it with the same system and color as the tank exterior. Please verify.
For the purpose of the bid, follow the plans and specifications. During performance of the contract, use of comparable products can be requested in accordance with 01 67 00. 5
Pg. 7 – 3.2 A5 – “Seal Weld all
Water Compartment Joints”
The AWWA code requires that the lapped surfaces of the tank roof be welded on the top side. The underside of the lapped roof is not welded. The underside of the roof is coated and is a minimum of 12” above the high-water level.
We ask that AWWA be adhered to.
Comply with AWWA D100 Section 8 for welding procedures and requirements as stated in 33 16 23 paragraph 3.2.A.1.
79 5
80 Pg. 8 – 3.4 C1:
We suggest using AWWA C652 Method II. This is a 200 ppm, high concentration of chlorine, sprayed on the submerged surface of the tank walls and floor. It must sit for 30 minutes before introducing chlorinated water into the tank. After the bac-t’s are taken the tank can be put immediately into service. The important factor in this method is that the water does not need to be removed and wasted. It can go immediately into the system.
For the purpose of the bid, follow the specifications. During performance of the contract, an alternate method may be proposed as value engineering. 5
81 Do the Superintendent, SSHO, and QC Manager need to be three separate individuals? The Superintendent and the QC manager should not be the same individual. The SSHO and QC manager may be the same individual. 5
82 Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions?
This type of request can be addressed with the Contracting Officer after award. 5
83 Are soil boring reports available? If not, can the Contractor assume excavation will be clear of rocks and obstructions?
No additional soil boring reports are available. 5
84 Please provide the site visit attendee sign-in sheet. Sign in sheet from site meeting will be attached to the amendment. 5 85 Do we need to provide any computer hardware, or are there existing workstations and/or servers? There is an existing operator workstation with a Windows computer in the Maintenance building. 5
86 For SCADA software, both Wonderware and FactoryTalk are listed. Is there existing software in use, or will this be a new system entirely?
No, there is no existing system. 5
87 SF1442 Block 13 requests “sealed offers in original and 1 copy,” but Section L requests one electronic copy of Volumes I & II via email. Please confirm electronic only.
Electronic only. 5
88 Section L submission requirements call for the subject line to include solicitation number, PMIS, and total number of emails, but the example omits solicitation number and email count. Please confirm stated requirements govern.
Contracting to answer 5
89 Section L Subfactor 1A – Confirm “Project Experience” form is only the first page of Attachment 4B, with the remainder being the Past Performance Questionnaire.
An example form can be provided. 5
90 Section L Subfactor 1B – Confirm Attachment 4C is optional, and resumes may be submitted in free form. Resumes may be submitted in any format. 5
91 Confirm whether the QC Manager may also serve as Superintendent and/or SSHO. The Superintendent and the QC manager should not be the same individual. The SSHO and QC manager may be the same individual. 5
92 Section L Subfactor 2B – Confirm fictitious NTP date of 10/1/24 remains applicable for proposal evaluation. Question was answered in Amendment 04. 5
93 Section L Factor 4 – Confirm CPARS evaluations may be submitted in lieu of Past Performance Questionnaires (not just PPIRS).
Yes. 5
94 Section L Factor 4 / Attachment 4D – Factor 4 requires completing “Sections I and II,” but Attachment 4D shows “Sections A and B.” Please confirm A & B should be completed.
Yes. 5
95 Will NPS accept previously completed Past Performance Questionnaires in lieu of requesting new ones? Yes. 5 96 Please provide Attachments 4B & 4D in Microsoft Word (or other editable format). An example form can be provided. 5
97 Section L Other Submittals – “Proposed Equals” and “Hazardous Materials Identification Listing” are referenced but not attached. Please provide.
Contracting to answer 5
98 Section L, Vol I & II Organization – References “Table of Contents with tabs for hard copy formats,” but proposals are email only. Please confirm no hard copies required.
Proposals will be submitted electronically. No hard copies are required. 5
99 Division 33 – Confirm whether continuous water service is required during construction, or if short outages are acceptable.
Short utility interruptions are allowable under the procedures of 01 11 00 1.8B. 5
100 Division 33 – During demolition/replacement of 100k & 50k tanks, will temporary storage or bypass tanks be required?
As shown on sheet C102 and C500, a bypass can be used to take the 100K gallon tank out of service and and allow only the 50K gallon tank to distribute water to the residences / NPS buildings during replacement of the larger tank. 5
101 Division 26 – Confirm APS’ scope ends at transformer secondary lugs, with Contractor furnishing downstream panels, SCADA power, and controls.
Correct, installation of panels and SCADA components is by the contractor, not the utility provider. 5
Division 02 – If AC pipe is made friable during construction, is Contractor responsible for full abatement/disposal?
Will NPS allow abandonment in place with flowable fill?
The Generator of regulated material is responsible for the identification and proper handling, transportation, and disposal of the material.
If the actions of the contractor cause the material to become friable, the material becomes subject to regulations, and the contractor becomes the Generator. The current threshold for state agency notification is removal of 260 linear feet of asbestos cement pipe which on removal will become friable. Methods of disposal or abandonment that meet state and federal regulations would be considered acceptable.
103 Division 21/33 – Confirm interior sprinkler system installation is not part of scope; only exterior hydrants and service stubs.
Scope is limited to what is provided in the plans and specifications. See Sheet C204, note 1 for a description of where fire service lines will connect to existing systems or terminate within 3 feet of the building for future systems. 5
104 CLIN 5 / Division 26 – Confirm Option CLIN 5 is limited to empty conduit with pull string, no wiring/terminations/devices.
That is correct. 5
105 Division 03 / Tank Foundations – Confirm Contractor responsible for final foundation design based on geotech recommendations.
Foundation detail provided on sheet S101 to be confirmed based on tank manufacturer's design per 33 16 23 specifications. 5
106 Division 33 / Truck Fill Station – Please confirm configuration (hydrant style vs. metered station) and whether a standard NPS design detail applies.
See sheet C507 for truck fill station details. 5
107 C503 Detail 3 Detail 3 shown on sheet C503 "Water Service Detail" shows a meter lid with frost proof cover over a meter vault, What is the MOC of the Meter Vault? Will one be installed at all 1" DOM Water SVC? Are dimensions provided?
The detail applies to all new domestic service lines to buildings. The material for the meter pit has not been specified.
108 Sheet C413 The duplex residence only shows a 2-inch fire line on the east side of the duplex. Other duplex buildings have 1-inch domestic and 2-inch fire lines in pairs for each side of the building. Please confirm the configuration for this building.
A 2-inch fire service line was omitted on the drawing for the west side of the building, however a 2-inch line is required on both sides of the building. 5
109 01 32 33 Does photo documentation have to be provided via DVD or can project management software be used for this? Submit photo documentation via Project Management Software rather than DVD 5
110 01 35 25 This specification and selective demolition refer to blasting. Where is blasting expected to be required for the project?
Blasting is not required. This specification section will not apply. 5
111 09 97 13 3.2.J.1 requires color samples for white internal tank color. This requirement is repeated in 33 16 23 paragraph 1.4.C.5. Is this required?
Physical samples of the internal tank color will not be required. 5
112 09 97 13 The specification section color to match existing water tank. What is the color of the existing water tank. Tanks will be painted in a flat/matte color that blends with landscape. Park would need samples for approval. Colors will be selected during the submittal process and final selection may not match the existing color. 5
113 ES1.5
The photo of the power pole with the transformer on this sheet appears to be from a different pole on the north side of the loop road. How should power be supplied to the tank area given that the transformer is not in the location shown as 01001?
There is no existing power for the proposed SCADA system at 100k tank. A transformer will have to be mounted on an APS power pole, or a pad mount transformer and electrical pedestal could be installed at the base of an APS power pole. Then a trench will have to be dug from that point, then wire install inside conduit run to the 100K tank.
114 C407 How will service be maintained to the duplex residence outside the campground if the campground water system is out of service during construction?
There is a 6” isolation valve that needs to be replaced on the campground feed line that will allow water to remain supplied to Duplex 47 and 48 during construction. 5
01 11 00, preservation of natural features
Will the contractor be permitted to trim trees and vegetation? Removal/trimming of protected plants will be done under the direction of the Natural Resource Staff. This would include ironwood trees, saguaros, ocotillos, and Organ Pipe Cacti. 5
01 11 00, preservation of natural features
If protected plants are found that conflict with construction operations, what is the process? Larger and medium sized cacti (> 2 feet or > 8 inch diameter at breast height) and small trees will need to be relocated if encountered within the construction area. This will need to be done through the use of a preferred vendor (a list can be provided with contact information). An estimated number of plants is up to: 12 Saguaro cacti, 7 organ pipe cacti ,7 ocotillo , and 5 ironwood trees
01 11 00, preservation of natural features
Are there any protected wildlife in the project area that will impact the project? To ensure compliance with the Migratory Bird Treaty Act, the project area will be surveyed weekly by the NPS from February 15 to July 15 for nesting birds. If an active bird nest is discovered during construction, work will need to be modified, shortened, or delayed. A biological monitor may need to be provided if a nest is located by park staff.
One endangered species (Cactus Ferruginous Pygmy Owl) occurs in the general area but does not current overlap the project area. If found during construction, work will need to be modified, shortened, or delayed during the nesting period of March 15 to July 15. A biological monitor may need to be provided if a nest is located by park staff.
Contractors will need to notify park staff if they encounter snakes or lizards. Park staff will relocate the animals.
118 01 11 00 Are there any requirements to minimize conflict with wildlife? Food and waste management - NPS receptacles may not be used for garbage, recyclables, or construction waste. Do not mix food waste in 5
119 01 11 00, 1.5C The specifications state that the contractor should avoid closures of the campground from January-March. Is this a suggestion or a requirement that must be adhered to in the proposed schedule?
The campground is the Park's primary source of revenue and closures must be minimized during the peak season. Winter season is busiest (Oct – April), with peak visitation from Jan – March. 5
120 01 31 00, 1.8 The language says the contractor shall, at no additional expense to the government, be responsible for obraining any necessary licenses and permits. There several are contractor furnished permits listed as likely potential permits in 1.8B. Are these allowable costs?
Permits that are legally required may be added to the contractor's schedule of values for reimbursement. Licenses are the responsibility of the contractor. 5
121 General Is the road work outside the park expected to occur during the project? Arizona Department of Transportation (ADOT) will be conducting pavement rehabilitation operations on State route 85 from Elota Avenu 5
122 General
Are there any restrictions on loads coming through the US Border patrol checkpoints? There are two US Border Patrol checkpoints for traffic coming to the park from the direction of Phoenix or Tucson AZ, and one additional checkpoint on SR 85 northbound from Ajo, AZ. When scheduling deliveries to the construction site, coordination with the US Border Patrol may be required to ensure that loads and equipment will meet height and width restrictions and can be accommodated at these checkpoints.
123 01 11 00 Paragraph 1.8 indicates there are no restrictions for early morning hours - what does this mean? That statement is incorrect. Work outside of the regular business hours defined in 01 11 00 1.8A requires a written request for approval to the Contracting Officer in advance. To avoid disturbances to residences, deliveries and noise generating activities must be scheduled during regular business hours.