BIBE_259631-317515_Lodge_Final_CD_Drawings_E2_01_Revision_1_08_18_2025_0004.pdf
PDF 323 KB Posted
- Solicitation number
- 140P2025R0039
About this file
This document is an electrical lower floor plan drawing for the Big Bend National Park lodge component project, dated 08-18-2025. The detailed electrical schematic shows the layout of various rooms including mechanical equipment, storage, receiving, electrical room, and corridor spaces, with specific annotations for electrical infrastructure. Key technical notes include requirements for surface junction boxes, transformer installations, power connections for equipment like gas and water meters, generator systems, and a representative photovoltaic inverter panel. The drawing specifies electrical coordination requirements with mechanical and plumbing plans, equipment locations, conduit routing, and exterior device installations. The document is signed by engineers Steve Diffenderfer and Robert Mills, with Diffenderfer taking responsibility for specific scope changes, and is part of the final construction documents for the lodge component.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
S7.16
S7.16
S7.16
S7.16
J
M
M
M
M
M
M
J
J
J
J
F
STORAGE
MECHANICAL
EQUIPMENT
RECEIVING
ELECTRICAL
ROOM
LOADING
STAIR 2
PLUMBING
EQUIPMENT
CORRIDOR
ELEVATOR 2
GG
WP
N-M-A
N-P-A
CU-LL-03
E-MTS
G WP
G
FSD-LL-01
FSD-LL-02
CU-LL-03
CU-LL-02-A
CU-LL-02-B
ELEV 1
OVERHEAD DOOR OPERATOR1
AHU-LL-01
BSB-LL-01
FCU-LL-01
NEW
GENERATOR
E-P-OPA: 17.
AHU-FAN
G
CU-LL-01
TP-1
CU-LL-02-C
ACCU-LL-01
GM-1
GM-2
WM-2
WM-1
SP-101
RHWP-1
GWH-2
GWH-1
15.
17.
17.
13.
13.
19.
G
21.
23.
21.
23.
23.
21.
21.
60AS
NF
ACCU-LL-01
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9 10 11 AA
D.3
EXVK-AHU-01
RPBA-1
RAIN WATER
HARVESTING
44.
E5.02
400A/3P PV
DISCONNECT
R1
E-P-OPA:
37,39,41.
100AS
NF
TITLE OF SHEETSUB SHEET NO.DESIGNED:
TECH. REVIEW:
DATE:
DRAWING NO.
PMIS/PKG NO.
SHEET
OF
BIG BEND NATIONAL PARK
47608-18-20251
LBW
PWH
RAM
12-10-2024
LOWER FLOOR PLAN -
ELECTRICAL
E2.01 171153
259631-317515
FINAL CONSTRUCTION DOCUMENTS - LODGE COMPONENT
1/8" = 1'-0"
1 LOWER FLOOR PLAN - ELECTRICAL
1. PROVIDE SURFACE JUNCTION BOX FOR CONTROLS
LOCATED 48" AFF AND PROVIDE (1) 3/4"C FROM JUNCTION
BOX TO OVERHEAD DOOR OPERATOR. COORDINATE EXACT
LOCATION OF JUNCTION BOX IN WALL WITH CONTRACTING
OFFICER PRIOR TO ROUGH-IN. COORDINATED WITH
OVERHEAD DOOR SUPPLIER AND PROVIDE ALL ELECTRICAL
FOR A COMPLETE AND OPERATIONAL SYSTEM.
2. PROVIDE 120V-24V BUCK-BOOST TRANSFORMER FOR GAS
AND WATER METERS. COORDINATE MOUNTING LOCATION
WITH EQUIPMENT IN THE ROOM. COORDINATE EXACT
WIRING REQUIREMENTS AND POWER REQUIREMENTS WITH
GAS METER MANUFACTURER PRIOR TO PROCUREMENT OR
INSTALLATION OF ANY EQUIPMENT.
NOTES:GENERAL NOTES:
A. REFER TO EQUIPMENT CONNECTION SCHEDULES FOR EQUIPMENT CONNECTION
REQUIREMENTS.
B. PROVIDE 10AWG CONDUCTORS FOR RECEPTACLE CIRCUITS EXCEEDING TOTAL
LENGTH OF 100 FEET BETWEEN DEVICE AND PANEL.
C. COORDINATE ELECTRICAL INSTALLATION WITH CASEWORK INSTALLER PRIOR TO
ROUGH-IN.
D. COORDINATE ELECTRICAL INSTALLATION WITH MECHANICAL AND PLUMBING
PLANS FOR EQUIPMENT LOCATIONS PRIOR TO ROUGH-IN.
E. LOCATE STARTERS/DISCONNECTS WITHIN SIGHT OF AND ADJACENT TO
EQUIPMENT SERVED UNLESS OTHERWISE NOTED.
F. COORDINATE ROUTING OF EXPOSED CONDUIT AND REVIEW WITH THE
CONTRACTING OFFICER PRIOR TO INSTALLATION.
G. PROVIDE EXTERIOR DEVICES WITH LOCKABLE WEATHERPROOF WHILE-IN-USE
COVERS.
H. COORDINATE COVER PLATE REQUIREMENTS WITH CONTRACTING OFFICER PRIOR
TO INSTALLATION.
I. COORDINATE THE INSTALLATION OF PATHWAY INFRASTRUCTURE WITH
TECHNOLOGY DRAWINGS PRIOR TO ROUGH-IN.
J. ALL POWER CIRCUITED FROM PANEL N-P-A.
3. CONNECTIONS TO GENERATOR ALTERNATOR HEATER, BATTERY
CHARGER, AND JACKET HEATER.
4. PROVIDE PANIC HARDWARE ON DOORS PER NEC 110.26.
5. PROVIDE GENERATOR EMERGENCY STOP BUTTON.
6. REPRESENTATIVE PV INVERTER PANEL. THE PHOTOVOLTAIC SYSTEM
AND INFRASTRUCTURE WILL BE DELIGATED-DESIGN BY THE
CONTRACTER. EXACT EQUIPMENT SIZES AND CONNECTION POINTS WILL
BE DETERMINED BY THE CONTRACTOR.
7. PROVIDE POWER TO REMOTE AIR-COOLING REFRIGERATION RACK,
REFER TO KITCHEN SCHEDULE ITEM 'R1' ON SHEET E0.10. COORDINATE
EXACT POWER REQUIREMENTS WITH KITCHEN CONSULTANT PRIOR TO
PROCUREMENT OR INSTALLATION OF ELECTRICAL INFRASTRUCTURE.1
SCALE OF
SCALE K
0 1688
FEET
SIGNING ENGINEER STEVE DIFFENDERFER TAKES
RESPONSIBILITY FOR ALL SCOPE OF WORK RELATED TO
DELTA 1 CLOUDED CHANGES ON THIS DRAWING DATED
8/18/2025. ALL OTHER WORK IS UNDER THE RESPONSIBILITY OF
ROBERT MILLS.