This document is an amendment to a solicitation for the Rehabilitation of the Ohanapecosh Campground, Solicitation Number 140P2024R0077. The purpose of the amendment is to:

  1. Provide updated specification and drawing sheets as Attachments 1-6.
  2. Provide official government responses to questions received.
  3. Revise the period of performance from 730 calendar days after Notice to Proceed to 365 calendar days after Notice to Proceed.

The solicitation is issued by the Department of the Interior National Park Service National Office. The contractor is required to commence work within 10 calendar days after receiving the Notice to Proceed and complete the entire work within 365 days. The amendment addresses some minor discrepancies found in the specification and drawing attachments.

View the file

Other files

File Type Posted
B09_Amd_9_2024_Quarry_Survey_Summary__0009.docx DOCX document
Sol_140P2024R0077_Amd_0009.pdf PDF
Sol_140P2024R0077_Amd_0008.pdf PDF
B09_AMD_7_Attach_(4)_20240813-Enclosure4_CertComp_0007.pdf PDF
B09_AMD_7_Attach_(6)_20240813-NWPVerifLtr-NWS-2024-570_0007.pdf PDF
B09_AMD_7_Attach_(1)_019-GC10_Amendment_07_0007.pdf PDF
B09_AMD_7_Attach_(2)_20240813-Enclosure1-PmtDrawings_NWS-2024-570_0007.pdf PDF
B09_AMD_7_Attach_(5)_20240813-Enclosure302021-NWP18_0007.pdf PDF
B09_AMD_7_Attach_(3)_20240813-Enclosure2_2021-NWP03_0007.pdf PDF
Sol_140P2024R0077_Amd_0007.pdf PDF
B09_AMD_6_Attach_(2)_MORA_HazMat_051523_REV1_FTC_0006.pdf PDF
Sol_140P2024R0077_Amd_0006.pdf PDF
B09_AMD_6_Attach_(1)_MORA_Amphitheater_Drain_Exhibit_0006.pdf PDF
B09_AMD_6_Attach_(3)_MORA_20-GC10_0006.pdf PDF
Sol_140P2024R0077_Amd_0005.pdf PDF
B09_Amd_4_Attach_1_33_40_00_-_Storm_Drainage_0004.pdf PDF
B09_Amd_4_Attach_3c_IMG_0890_0004.jpg JPG image
B09_Amd_4_Attach_2_33_31_13_-_Site_Sanitary_Sewerage_Gravity_Piping_0004.pdf PDF
B09_Amd_4_Attach_3a_IMG_0888_0004.jpg JPG image
B09_Amd_4_Attach_3d_IMG_0891_0004.jpg JPG image
B09_Amd_4_Attach_3b_IMG_0889_0004.jpg JPG image
Sol_140P2024R0077_Amd_0004.pdf PDF
Sol_140P2024R0077_Amd_0003.pdf PDF
B09_AMEND_02_Attach_(5)_31_20_00_-_Earth_Moving_MORA_Ohana_AMEND02_0002.pdf PDF
B09_AMEND_02_Attach_(3)_01_32_16-ConstructionSchedule_MORA_Ohana_AMEND02_0002.pdf PDF
B09_AMEND_02_Attach_(2)_01_11_00-SummaryOfWork_MORA_Ohana_AMEND02_0002.pdf PDF
B09_AMEND_02_Attach_(6)_Revised_drawing_sheets_MORA_Ohana_AMEND02_0002.pdf PDF
B09_AMEND_02_Attach_(4)_01_50_00_TemporaryFacilitiesAndControls_MORA_Ohana_AMEND02_0002.pdf PDF
B09_AMEND_02_Attach_(1)_00_01_10-1_MORA_Ohana_AMEND02_0002.pdf PDF
B11_Preproposal_SignIn_(3)_0001.pdf PDF
B11_Preproposal_SignIn_(1)_0001.pdf PDF
B11_Preproposal_SignIn_(2)_0001.pdf PDF
B11__Site_Visit_Tri_Fold_MORA_Ohanapecosh_0001.docx DOCX document
Sol_140P2024R0077_Amd_0001.pdf PDF
B08_Attach_2_MORA_313019_331809_312439_Final_Drawings_Part1.pdf PDF
B08_Attach_2_MORA_313019_331809_312439_Final_Drawings_Part3.pdf PDF
B08_Attach_6_Solit_PSP_Vol_I_PastPerf_REQD(1).docx DOCX document
B08_Attach_1_MORA_313019_331809_312439_Final_Specifications_App_B.pdf PDF
B08_Attach_2_MORA_313019_331809_312439_Final_Drawings_Part4.pdf PDF
B08_Attach_2_MORA_313019_331809_312439_Final_Drawings_Part2.pdf PDF
Sol_140P2024R0077.pdf PDF
B08_Attach_1_MORA_313019_331809_312439_Final_Specifications.pdf PDF
B08_Attach_1_MORA_313019_331809_312439_Final_Specifications_App_A.pdf PDF
B08_Attach_5_Solit_PSP_Vol_I_Exp_REQD.docx DOCX document
B08_Attach_7_Construction_Contract_Administration.docx DOCX document
B08_Attach_3_WD_WA20240051_20240524.pdf PDF
B08_Attach_4_Deliverables_LmtOnSubconRpt_REQD.xlsx XLSX spreadsheet
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P2024R0077 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PDS

Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div

07/31/20240002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

07/11/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of amendment 2 is to:

1) Provide Attachments 1-6 with updated specification and drawing sheets;

2) Provide official government responses to questions received. Refer to the continuation sheet of the SF 30;

3) Update SECTION F- DELIVERIES OR PERFORMANCE: Period of performance revised from 730 calendar days after Notice to Proceed to 365 calendar days after Notice to Proceed.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Dayna Omiya

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

SOLICITATION SECTION F – DELIVERIES OR PERFORMANCE

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 365 days after Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

(End of clause)

Questions and Answers:

Q1. I wanted to mention some discrepancies found in the documents for this project.

Attachment 1 Specifications:

- Section 040141.91 & 102113.43 number mismatch vs. table of contents

Attachment 1 Specifications Appendix A:

- missing content for Appendix A-N, unsure if intentional

Attachment 2 Drawings Part 1:

- 00-GL2.11 slight title mismatch vs. index

Attachment 2 Drawings Part 2:

- 13-L201 slight title mismatch vs. index

Attachment 2 Drawings Part 3:

- Sheets LG4.1-LG4.7 & 19-G10 sheet number mismatch vs. index

- 18-LH4.6 & 18-AD01 slight title mismatch vs. index

A1. See attachments (1) through (6).