This document is a survey summary of quarry sites that provide fill materials for facilities projects in Mount Rainier National Park. The purpose is to identify quarries that can provide weed-free fill materials to prevent the introduction of invasive species. The document lists several approved quarry sources, including WA Rock Quarries Inc., Ashe Quarry, Cal-Portland DuPont, Randles Sand & Gravel Inc., and Heidelberg Materials, along with their contact information, materials available, weed mitigation measures in place, frequency of use, and any weed species of concern. The document also provides general guidelines for using weed-free fill, such as requesting fresh fill, limiting time in stockpiles, cleaning truck beds and exteriors, and tarping fill before transport. The document is related to a federal contract opportunity for the rehabilitation of the Ohanapecosh Campground in the park.

View the file

Other files

File Type Posted
Sol_140P2024R0077_Amd_0009.pdf PDF
Sol_140P2024R0077_Amd_0008.pdf PDF
B09_AMD_7_Attach_(4)_20240813-Enclosure4_CertComp_0007.pdf PDF
B09_AMD_7_Attach_(6)_20240813-NWPVerifLtr-NWS-2024-570_0007.pdf PDF
B09_AMD_7_Attach_(1)_019-GC10_Amendment_07_0007.pdf PDF
B09_AMD_7_Attach_(2)_20240813-Enclosure1-PmtDrawings_NWS-2024-570_0007.pdf PDF
B09_AMD_7_Attach_(5)_20240813-Enclosure302021-NWP18_0007.pdf PDF
B09_AMD_7_Attach_(3)_20240813-Enclosure2_2021-NWP03_0007.pdf PDF
Sol_140P2024R0077_Amd_0007.pdf PDF
B09_AMD_6_Attach_(2)_MORA_HazMat_051523_REV1_FTC_0006.pdf PDF
Sol_140P2024R0077_Amd_0006.pdf PDF
B09_AMD_6_Attach_(1)_MORA_Amphitheater_Drain_Exhibit_0006.pdf PDF
B09_AMD_6_Attach_(3)_MORA_20-GC10_0006.pdf PDF
Sol_140P2024R0077_Amd_0005.pdf PDF
B09_Amd_4_Attach_1_33_40_00_-_Storm_Drainage_0004.pdf PDF
B09_Amd_4_Attach_3c_IMG_0890_0004.jpg JPG image
B09_Amd_4_Attach_2_33_31_13_-_Site_Sanitary_Sewerage_Gravity_Piping_0004.pdf PDF
B09_Amd_4_Attach_3a_IMG_0888_0004.jpg JPG image
B09_Amd_4_Attach_3d_IMG_0891_0004.jpg JPG image
B09_Amd_4_Attach_3b_IMG_0889_0004.jpg JPG image
Sol_140P2024R0077_Amd_0004.pdf PDF
Sol_140P2024R0077_Amd_0003.pdf PDF
B09_AMEND_02_Attach_(5)_31_20_00_-_Earth_Moving_MORA_Ohana_AMEND02_0002.pdf PDF
Sol_140P2024R0077_Amd_0002.pdf PDF
B09_AMEND_02_Attach_(3)_01_32_16-ConstructionSchedule_MORA_Ohana_AMEND02_0002.pdf PDF
B09_AMEND_02_Attach_(2)_01_11_00-SummaryOfWork_MORA_Ohana_AMEND02_0002.pdf PDF
B09_AMEND_02_Attach_(6)_Revised_drawing_sheets_MORA_Ohana_AMEND02_0002.pdf PDF
B09_AMEND_02_Attach_(4)_01_50_00_TemporaryFacilitiesAndControls_MORA_Ohana_AMEND02_0002.pdf PDF
B09_AMEND_02_Attach_(1)_00_01_10-1_MORA_Ohana_AMEND02_0002.pdf PDF
B11_Preproposal_SignIn_(3)_0001.pdf PDF
B11_Preproposal_SignIn_(1)_0001.pdf PDF
B11_Preproposal_SignIn_(2)_0001.pdf PDF
B11__Site_Visit_Tri_Fold_MORA_Ohanapecosh_0001.docx DOCX document
Sol_140P2024R0077_Amd_0001.pdf PDF
B08_Attach_2_MORA_313019_331809_312439_Final_Drawings_Part1.pdf PDF
B08_Attach_2_MORA_313019_331809_312439_Final_Drawings_Part3.pdf PDF
B08_Attach_6_Solit_PSP_Vol_I_PastPerf_REQD(1).docx DOCX document
B08_Attach_1_MORA_313019_331809_312439_Final_Specifications_App_B.pdf PDF
B08_Attach_2_MORA_313019_331809_312439_Final_Drawings_Part4.pdf PDF
B08_Attach_2_MORA_313019_331809_312439_Final_Drawings_Part2.pdf PDF
Sol_140P2024R0077.pdf PDF
B08_Attach_1_MORA_313019_331809_312439_Final_Specifications.pdf PDF
B08_Attach_1_MORA_313019_331809_312439_Final_Specifications_App_A.pdf PDF
B08_Attach_5_Solit_PSP_Vol_I_Exp_REQD.docx DOCX document
B08_Attach_7_Construction_Contract_Administration.docx DOCX document
B08_Attach_3_WD_WA20240051_20240524.pdf PDF
B08_Attach_4_Deliverables_LmtOnSubconRpt_REQD.xlsx XLSX spreadsheet
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Quarry survey reports and recommendations 2024 Purpose: Fill materials imported into Mount Rainier NP for facilities projects can bring in new species or populations of invasive weeds. Eliminating or reducing the import of invasive species is an important part of NPS and park management policies and an ongoing operational effort in the park. Using weed-free fill or fill from quarries with frequent use and active weed mitigations will help meet that goal. Park revegetation specialists survey area quarries every 2-3 years to determine 1) the weed mitigations in place at the quarry; 2) the frequency of activity and fill extraction at each site, with more frequently used quarries and freshly extracted and processed fill preferred to reduce weed import; and 3) weed species present at any site that would be of particular concern (new or rare in park). Invasive weed surveys and treatments will still be required at any site where fill is imported for 2-3 years following any installation.

2024 Quarry inspection summaries are below. Those listed as “Yes” under Suitable Source can be used fill in the park without further inspections. Please note that two sources are suitable for most rock fill, but not for soil.

Individual site reports and summaries will be updated here: M:\NCR\MORAShare\NCRVegetation\Quarry Surveys.

All recommended fill import mitigations should still be in place:

· Request fresh fill for projects

· Limit time in stockpile and only use sub-surface rock that is hauled to the project within 2-weeks of being process from hill side.

· Clean truck beds importing fill prior to fill pick up and clean truck exteriors prior to entry into park

· Tarp all fill before leaving pit and traveling access roads (to keep out wind-borne weed seed along access road).

· Notify vegetation staff of locations of fill installation for follow up weed management activities Contact:

Kim Popek, Supervisory Biological Technician and Restoration lead, kimberly_popek@nps.gov Beth Fallon, Plant Ecologist, beth_fallon@nps.gov

Suitable source
Quarry
Contact
Materials available
Site specific recommendations
Weed mitigations in place
Frequency of use/fill extraction
Weed species of concern
Yes
WA Rock Quarries Inc.

King Creek Pit (Orting) and Kapowsin Quarry (Orting) Sam Martinson (253)-262-1661 or 253-255-8631 (cell) Sand, 5/8 inch minus, soil, 1 ¼, crushed rock, etc.

Standard mitigations: work with quarry on recently mined and processed fill
Seasonal manual control treatments of target invasive plants including Scotch broom and tansy.
highly active year-round

knotweed, tansy, and European coltsfoot

Yes
Ashe Quarry, Randle
Jim Ashe, (360) 520-4375
5/8 inch minus and 1 ¼ gravel
Standard mitigations: work with quarry on recently mined and processed fill
Currently certified weed free with Lewis County. Seasonal herbicide treatment of a wide variety of invasive plants. Frequent mowing occurs through fields around the lower commercial lots.
Mining 5 times per year; 1 week to 1 month hold time
No new or high priority species
Yes
Cal-Portland DuPont, DuPont
Sean Smith, (206) 406-0397 or (206) 764-3108
¼ inch minus, specialty fill
Standard mitigations: work with quarry on recently mined and processed fill
Manual removal and mowing, 2x/year; hydroseeding decommissioned mine sites; Truck wash
Continuous production in the summer; complete turn over at least 1/month
butterfly bush, Scotch broom, and European coltsfoot
Yes, except soil
Randles Sand & Gravel Inc., Puyallup

Lynch Creek Quarry (aka Randles Quarry), Eatonville

Rick Mondoux, office: (253) 531-6835 or mobile: (253) 686-0521
Sand, ¼ inch minus, 5/8 inch minus, 1 ¼ inch minus, pea gravel
Standard mitigations: work with quarry on recently mined and processed fill
Seasonal herbicide treatment of target invasive plants; fill largely devoid of vegetation
Highly active year round mine; 2-3 days between processing and pick up
butterfly bush, poison hemlock, Japanese knotweed, and European coltsfoot
Yes, except soil
Heidelberg Materials (previously Corliss Resources), Enumclaw and Puyallup locations
Mary Schmitz (Enumclaw): (206)773-7134

Breydy Triano (Puyallup): (253)987-9912

5/8 inch minus, 1 3/4”, and washed sand
Standard mitigations: require recently mined and processed materials because of weed species of concern on site
Bi-annual herbicide treatments of two species (minimal control); truck wash upon exit. Biocontrol on gorse populations.
Active mine; relatively quick turnover
Poison hemlock infestation in soil pile; butterfly bush, orange hawkweed, teasel, European coltsfoot, knapweed, and common tansy
No
Justice Quarry, Glenoma
Albert Justice, (360) 520-1671
5/8 inch minus, washed sand
Not recommended; re-evaluate for operational changes
None
Infrequent mining and 6 months in stockpile
Canada thistle; velvet grass, scotch broom