This document provides details for a National Park Service solicitation seeking proposals to replace an existing wastewater treatment plant in Stehekin, Washington. Offerors are requested to submit proposals by August 30, 2023 to design and install a new recirculating textile filter treatment system, rehabilitate the existing building, and demolish and remove the package skid and tanks from the current site. The project is intended to be awarded as a firm-fixed-price contract. Evaluation factors include technical approach, logistics and schedule, project experience, safety on a remote project, and past performance. The government may award without discussions and expects work to commence within 10 days of notice to proceed and be completed within 595 calendar days, with liquidated damages of $2,621 per day for any delays.

View the file

Other files for this federal contract opportunity

Other files attached to NOCA 156728 Stehekin WWTP, newest first.
File Type Posted
Sol_140P2023R0131_Amd_0004.pdf PDF
B09_Amd_03_Attach_01_140P2023R0131_QA3_0003.xlsx XLSX spreadsheet
B09_Amd_03_Attach_05_NOCA_STEHEKIN_Drawings_for_Rev_2_Structural_Updates_08-25-23_0003.pdf PDF
B09_Amd_03_Attach_04_32_62_17_Driven_Steel_Sheet_Piling_Rev_1_0003.pdf PDF
B09_Amd_03_SF30_NOCA_156728_140P2023R0131_0003.pdf PDF
B09_Amd_03_Attach_02_Solit_Clauses_Construction_REVISED_20230828_0003.docx DOCX document
B09_Amd_03_Attach_03_01_27_00_Definition_of_Contract_Line_Items_Rev_1_0003.pdf PDF
Sol_140P2023R0131_Amd_0003.pdf PDF
B09_Amd_02_Attach_08_26_28_00_Overcurrent_and_Short_Circuit_Protective_Devices_Rev_1_0002.pdf PDF
B09_Amd_02_Attach_02_Specification_01_73_20_correction_0002.pdf PDF
B09_Amd_02_Attach_09_NOCA_STEHEKIN_Drawings_for_Rev_1_Electrical_Updates_08-10-2023_0002.pdf PDF
Sol_140P2023R0131_Amd_0002.pdf PDF
B09_Amd_02_Attach_04_Specification_40_61_96_correction_0002.pdf PDF
B09_Amd_02_Attach_01_140P2023R0131_QA2_0002.xlsx XLSX spreadsheet
B09_Amd_02_Attach_06_Specification__46_53_25_correction_0002.pdf PDF
B09_Amd_02_Attach_03_Specification_03_31_30_correction_0002.pdf PDF
B09_Amd_02_SF30_NOCA_156728_140P2023R0131_0002.pdf PDF
B09_Amd_02_Attach_11_Site_Visit_Sign-in_0002.pdf PDF
B09_Amd_02_Attach_05_Specification__40_66_40_correction_0002.pdf PDF
B09_Amd_02_Attach_07_26_09_13_Electrical_Metering_Devices_Rev_1_0002.pdf PDF
B09_Amd_01_SF30_NOCA_156728_140P2023R0131_0001.pdf PDF
Sol_140P2023R0131_Amd_0001.pdf PDF
B09_Amd_01_140P2023R0131_QA1s_0001.xlsx XLSX spreadsheet
B08_Attach_2c_NOCA_156728_100__CD_Drawings_Part3.pdf PDF
B08_Attach_2b_NOCA_156728_100__CD_Drawings_Part2.pdf PDF
B08_Attach_3_22_07_26_-_Final_Geo-tech_Report.pdf PDF
B08_Attach_6_Construction_Contract_Administration.docx DOCX document
B08_Attach_9_Solit_PSP_Vol_II_GenRefs.doc DOC document
B08_Attach_2d_NOCA_156728_100__CD_Drawings_Part4.pdf PDF
B08_Attach_5_Const_WD_DBA_WA20230065.pdf PDF
B08_Attach_2a_NOCA_156728_100__CD_Drawings_Part1.pdf PDF
B08_Attach_1_NOCA_156728_100___CD_Specifications.pdf PDF
B08_Attach_8_Solit_PSP_Vol_I_PastPerf_REQD.docx DOCX document
B08_Attach_7_Deliverables_LmtOnSubconRpt_REQ.xlsx XLSX spreadsheet
B08_Attach_4_22_10_06_-_Geotech_Report_for_Disposal_Field_Test_Pits_-r1.pdf PDF
Sol_140P2023R0131.pdf PDF
B08_SF_1442_140P2023R0131.pdf PDF
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AFTER PREPROPOSAL CONFERENCE

· Direct all questions to both Dayna Asuncion, Contracting Officer, and Patrick Naulty, Contracting Specialist. Please submit all questions no later than August 23, 2023.

· Questions directed to any other Government team member will be redirected to Ms. Mascarenas or Mr. Naulty. No answers will be provided by any other team member. All questions and answers will be provided to all prospective offerors by amendment to the solicitation

· Request for Proposal (Solicitation Document) shall only be changed by formal amendment issued by the Contracting Officer at the website – www.SAM.gov Award of a Contract:

Best Value Tradeoff Alternate proposals shall not be accepted or evaluated The government intends to evaluate proposals and award a contract without discussions with offerors, therefore the offeror’s initial proposal should contain the offeror’s best terms from a cost or price and technical standpoint. The government reserves the right to conduct discussions if the CO later determines them to be necessary.

Project Location:

North Cascades National Park During Site Visit Direct all Questions to Patrick Naulty

Responses do not change the solicitation document

Changes to the solicitation document shall be made by formal written amendment only

Pre-proposal Conference/Site Visit meeting notes, questions, and answers will be issued by a formal written amendment to the solicitation for information only

Preproposal Conference/ Site Visit- Thursday, August 10, 2023

Request for Proposals No. 140P2023R0131 CO: Dayna Asuncion dayna_asuncion@nps.gov CS: Patrick Naulty patrick_naulty@nps.gov

NOCA 156728 Stehekin WWTP

Clauses 52.211-10 Commencement, Prosecution, and Completion of Work - Commence work within 10 days after NTP. Complete not later than 595 days after NTP.

52.211-12 Liquidated Damages – Construction - If contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $2,621 for each calendar day of delay until the work is completed or accepted.

Special Requirement 2 – Key Personnel: Project Manager, Job-Site Superintendent, Quality Control Manager, Safety Manager. Prospective contractor shall not be allowed to change key personnel during the first 90 days of performance.

DIAR 1452.228-70 Liability Insurance-Department of the Interior: The contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the CO by an insurance company which is acceptable to the CO. The amounts of insurance shall be not less than:

Construction $100,000 each person $500,000 each occurrence $1,000,000 property damage

52.225-11 Buy American – CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (NOV 2021)– Refer to Clause for specific requirements

Submission and Evaluation Section L Instructions for the Submission of Offers

· Proposals Due August 30, 2023, 1:00 PM PT

· Volume I – Non-Price Proposal

· Volume II Business and Price Proposal

· Alternate proposals SHALL NOT be considered

· Government may award without discussion

· Send electronic proposals to: CS_DSC_Proposal_Submission@nps.gov Dayna_asuncion@nps.gov Patrick_naulty@nps.gov

· Submissions shall contain the solicitation number, park-PMIS, and number of total emails (example in solicitation) Evaluation Factors: The evaluation factors are correlated to the proposal preparation instructions. Factors 1- 5 are equally important. Overall: All evaluation factors, other than price, when combined, are approximately equally important to price.

FACTOR 1- TECHNICAL APPROACH AND KEY PERONNEL

FACTOR 2- LOGISTICS AND SCHEDULE

FACTOR 3- PROJECT EXPERIENCE

FACTOR 4- SAFETY ON A REMOTE PROJECT

FACTOR 5- PAST PERFORMANCE

Overview of project This project will replace existing Stehekin Wastewater Treatment Plant (WWTP) with a modern facility. Project scope includes demolition and removal of existing package skid and tanks, rehabilitation and upgrade of the building, and installation of new recirculating textile filter treatment system capable of meeting new discharge permit standards set by the State of Washington Department of Health (DOH). The new treatment system will be cost effective, simple to operate and capable of meeting new DOH groundwater discharge permit requirements. This project will also eliminate the biosolids handling process in favor of a primary tank to reduce overall operations and maintenance requirements.