This specification document outlines requirements for electrical metering devices for a wastewater treatment plant replacement project. Key details include the need to provide digital metering equipment that can display current, voltage, power readings and demand data with specified accuracies. The meters must also include data logging capabilities and communication ports for Ethernet and MODBUS protocols. Additional requirements cover power management software, separately mounted enclosures, and installation, configuration, programming and training. The related federal contract opportunity is for solicitation number 140P2023R0131 to replace the obsolete Stehekin wastewater treatment plant for the Department of the Interior National Park Service National Office.

View the file

Other files

File Type Posted
Sol_140P2023R0131_Amd_0004.pdf PDF
B09_Amd_03_Attach_02_Solit_Clauses_Construction_REVISED_20230828_0003.docx DOCX document
Sol_140P2023R0131_Amd_0003.pdf PDF
B09_Amd_03_Attach_04_32_62_17_Driven_Steel_Sheet_Piling_Rev_1_0003.pdf PDF
B09_Amd_03_Attach_01_140P2023R0131_QA3_0003.xlsx XLSX spreadsheet
B09_Amd_03_Attach_05_NOCA_STEHEKIN_Drawings_for_Rev_2_Structural_Updates_08-25-23_0003.pdf PDF
B09_Amd_03_Attach_03_01_27_00_Definition_of_Contract_Line_Items_Rev_1_0003.pdf PDF
B09_Amd_03_SF30_NOCA_156728_140P2023R0131_0003.pdf PDF
Sol_140P2023R0131_Amd_0002.pdf PDF
B09_Amd_02_Attach_04_Specification_40_61_96_correction_0002.pdf PDF
B09_Amd_02_Attach_10_Site_Visit_Tri_Fold_NOCA_156728_0002.docx DOCX document
B09_Amd_02_Attach_11_Site_Visit_Sign-in_0002.pdf PDF
B09_Amd_02_Attach_01_140P2023R0131_QA2_0002.xlsx XLSX spreadsheet
B09_Amd_02_SF30_NOCA_156728_140P2023R0131_0002.pdf PDF
B09_Amd_02_Attach_05_Specification__40_66_40_correction_0002.pdf PDF
B09_Amd_02_Attach_08_26_28_00_Overcurrent_and_Short_Circuit_Protective_Devices_Rev_1_0002.pdf PDF
B09_Amd_02_Attach_03_Specification_03_31_30_correction_0002.pdf PDF
B09_Amd_02_Attach_06_Specification__46_53_25_correction_0002.pdf PDF
B09_Amd_02_Attach_02_Specification_01_73_20_correction_0002.pdf PDF
B09_Amd_02_Attach_09_NOCA_STEHEKIN_Drawings_for_Rev_1_Electrical_Updates_08-10-2023_0002.pdf PDF
Sol_140P2023R0131_Amd_0001.pdf PDF
B09_Amd_01_SF30_NOCA_156728_140P2023R0131_0001.pdf PDF
B09_Amd_01_140P2023R0131_QA1s_0001.xlsx XLSX spreadsheet
B08_Attach_3_22_07_26_-_Final_Geo-tech_Report.pdf PDF
B08_Attach_9_Solit_PSP_Vol_II_GenRefs.doc DOC document
B08_Attach_2c_NOCA_156728_100__CD_Drawings_Part3.pdf PDF
B08_Attach_8_Solit_PSP_Vol_I_PastPerf_REQD.docx DOCX document
B08_Attach_2b_NOCA_156728_100__CD_Drawings_Part2.pdf PDF
B08_Attach_2a_NOCA_156728_100__CD_Drawings_Part1.pdf PDF
B08_SF_1442_140P2023R0131.pdf PDF
B08_Attach_7_Deliverables_LmtOnSubconRpt_REQ.xlsx XLSX spreadsheet
B08_Attach_6_Construction_Contract_Administration.docx DOCX document
Sol_140P2023R0131.pdf PDF
B08_Attach_4_22_10_06_-_Geotech_Report_for_Disposal_Field_Test_Pits_-r1.pdf PDF
B08_Attach_1_NOCA_156728_100___CD_Specifications.pdf PDF
B08_Attach_5_Const_WD_DBA_WA20230065.pdf PDF
B08_Attach_2d_NOCA_156728_100__CD_Drawings_Part4.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

10350902 National Park Service Replace Obsolete Stehekin Wastewater Treatment Plant - 100% Complete Contract Documents

ELECTRICAL METERING DEVICES

26 09 13 - 1

SECTION 26 09 13

ELECTRICAL METERING DEVICES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Digital metering equipment.

B. Related Sections include but are not necessarily limited to:

1. Section 26 05 00 - Electrical - Basic Requirements.

2. Section 26 08 13 - Acceptance Testing.

3. Section 26 24 16 – Panelboards

4. Section 26 28 00 – Overcurrent and Short Circuit Protective Devices

1.2 QUALITY ASSURANCE

A. Referenced Standards:

1. National Electrical Manufacturers Association (NEMA):

a. 250, Enclosures for Electrical Equipment (1000 Volts Maximum).

2. National Electrical Manufacturers Association/American National Standards Institute

(NEMA/ANSI):

a. C12.20, For Electricity Meter - 0.2 and 0.5 Accuracy Classes.

3. Underwriters Laboratories, Inc. (UL):

a. 508, Standard for Safety Industrial Control Equipment.

1.3 SUBMITTALS

A. Shop Drawings:

1. Product technical data including:

a. Provide submittal data for all products specified in PART 2 of this Specification:

b. See Section 26 05 00 for additional requirements.

2. Fabrication and/or layout drawings.

a. Electrical wiring/connection diagrams.

B. Contract Closeout Information:

1. Operation and Maintenance Data:

a. See Specification Section 01 78 23 for requirements for the mechanics, administration, and the content of Operation and Maintenance Manual submittals.

b. Content of Operation and Maintenance Manual:

1) Data sheet of the meters electrical parameters, configuration and characteristics including a complete model number and associated equipment connected too.

2) Operating instructions of the meter(s) supplied.

3) Operating instructions of the Power Management software.

4) Maintenance instructions.

5) As-constructed electrical wiring/connection diagrams.

6) Acceptance testing data.

C. Refer to Section 01 81 33 – Cyber Security Requirements for required cyber security related submittals.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Subject to compliance with the Contract Documents, the following manufacturers are acceptable:

ELECTRICAL METERING DEVICES

26 09 13 - 2

1. Allen-Bradley.

2. Eaton.

3. Electro Industries.

4. GE by ABB.

5. Power Measurement.

6. Square D Company.

7. Siemens.

2.2 DIGITAL METERING DEVICES

A. Refer to Section 01 81 33 - Cyber Security Requirements for cyber security related product requirements.

B. General:

1. Direct reading metered or calculated values.

2. Microprocessor based.

3. Integral LED or LCD display.

4. Current and potential transformers as required.

5. Integral fusing.

6. Operating temperature: 0 degrees F to 150 degrees F.

7. Standards:

a. NEMA/ANSI C12.20.

b. UL 508.

C. High Range Meter:

1. Display the following minimum electrical parameters (accuracy):

a. RMS current per phase (+0.2% full scale).

b. RMS voltage line-to-line and line-to-neutral (+0.2% full scale).

c. Real power (W): 3 PH total (+0.4% full scale).

d. Apparent power (VA): 3 PH total (+0.4% full scale).

e. Reactive power (VAR): 3 PH total (+0.4% full scale).

f. Power factor (+1.0%).

g. Frequency (+0.04%).

h. Percent current individual harmonic and total harmonic distortion (50th).

i. Percent voltage individual harmonic and total harmonic distortion (50th).

j. Watt-hours (0.5%).

k. VAR-hours (1.0%).

l. VA-hours (0.5%).

m. Ampere demand (+0.2% full scale).

n. Watt demand (+0.4% full scale).

o. VAR demand (+0.4% full scale).

p. VA demand (+0.4% full scale).

2. Data logging:

a. 128 KB.

b. Selectable for parameters listed above for display.

c. Software for configuration, retrieval, and trending.

3. NEMA/ANSI C12.20, Class 0.2 revenue accuracy.

4. Communication ports and protocols: Ethernet TCP/IP and MODBUS.

5. Supply voltage: 120 VAC.

2.3 ACCESSORIES

A. Power Management and Control Software:

1. Provide PC-based configuration software tool and a minimum of one communication interface cable for each type of cable required to connect a PC-based computer to the devices specified herein for configuration and programming.

2. Configuration software shall be designed specifically for the control system and supported by the manufacturer. Software shall support system configuration, printing of configuration

ELECTRICAL METERING DEVICES

26 09 13 - 3 records, and monitoring and control functions in a Windows environment. Support for remote system connection shall be incorporated into the software package.

3. Basic features shall include, but shall not be limited to, support for configuring inputs, zones, circuit breaker actions, and load shedding. Software shall be able to monitor the status of the system and provide visual indication of input status, circuit breaker status, and operational parameters. Software shall be able to establish connections to the system through a controller RS232 port, RS485 port, and Ethernet front port. Support for remote system connection shall be incorporated into the software package.

4. Electronic configuration files, in a media format (e.g. CD, USB stick, etc.), updated to an as-installed and commissioned state.

B. Separately Mounted Enclosure:

1. NEMA 12 rated for indoor locations.

2. NEMA 4 rated for outdoor locations.

3. Hinged front opening door with padlockable latch.

4. Input/output terminal blocks and wiring.

5. Separate control voltage source disconnect switch and wiring.

6. 600 Volt rated power voltage terminal blocks and wiring.

7. Current transformer shorting terminal blocks and wiring.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Install as indicated and in accordance with manufacturer's recommendations and instructions.

1. Provide all equipment and programming as necessary to provide a complete and functioning system.

B. Communication Configuration:

1. As indicated on the Drawings.

C. Screen Configuration:

1. Meter shall have a data screen with the following minimum data as applicable for the capabilities of that type of meter:

a. Voltage line-to-line for each phase and an average.

b. Voltage line-to-neutral for each phase and an average.

c. Current for each phase, neutral and average and peak demands.

d. Kilowatts (kW) for each phase, total, demand and peak demand.

e. Kilovolt-amperes (kVA) for each phase, total, demand and peak demand.

f. Kilovolt-amperes reactive (kVAR) for each phase, total, demand and peak demand.

g. Power factor for each phase and total.

h. Frequency.

i. Voltage total harmonic distortion for each phase.

j. Current total harmonic distortion for each phase.

k. Energy (kWhr) for each phase and total.

l. A seven day kW, kVA and kVAR trend average.

m. Peak demands shall be resettable by the operator.

2. Meter shall have the following 15 minute trending graphs.

a. Duration: Adjustable, with a seven day default.

b. Phase A current: Minimum, maximum and average.

c. Phase B current: Minimum, maximum and average.

d. Phase C current: Minimum, maximum and average.

e. Neutral current: Minimum, maximum and average.

f. Phase A Watts: Minimum, maximum and average.

g. Phase B Watts: Minimum, maximum and average.

h. Phase C Watts: Minimum, maximum and average.

i. Watts total.

j. Phase A Voltamps: Minimum, maximum and average.

ELECTRICAL METERING DEVICES

26 09 13 - 4

k. Phase B Voltamps: Minimum, maximum and average.

l. Phase C Voltamps: Minimum, maximum and average.

m. Voltamps total.

n. Phase A power factor: Minimum, maximum and average.

o. Phase B power factor: Minimum, maximum and average.

p. Phase C power factor: Minimum, maximum and average.

q. Power factor total.

3.2 FIELD QUALITY CONTROL

A. Acceptance Testing: See Section 26 08 13.

3.3 TRAINING

A. A qualified factory-trained manufacturer's representative shall provide the Owner with 8 hours of on-site training in the operation and maintenance of the metering system and its components.

3.4 CLOSEOUT ACTIVITIES

A. Refer to Section 01 81 33 – Cyber-Security Requirements for cyber security related closeout requirements.

END OF SECTION