B08_2 - 151201 CHOH ALL FINAL CD-Specs.pdf
PDF 20 MB Posted
- Attached to
- CHOH-151201, Reconstruct/Stabilize Historic Stone Federal contract opportunity
- Solicitation number
- 140P2020R0079
About this file
This document provides details on a federal solicitation opportunity and the related technical specifications file. The solicitation number is 140P2020R0079 for CHOH-151201, Reconstruct/Stabilize Historic Stone Wall & Towpath from McMahons Mill to Lock 42. The opportunity type is a solicitation issued by the Department of the Interior National Park Service National Office. The technical specifications file, B08_2 - 151201 CHOH ALL FINAL CD-Specs.pdf, contains requirements for reconstructing and stabilizing an historic stone wall and towpath along the Chesapeake and Ohio Canal between the specified points. Contractors should reference the technical specifications file for detailed requirements regarding the historic stone reconstruction and stabilization work.
View the file
Other files for this federal contract opportunity
Show all 45
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
C & O Canal National Historical Park
Williamsport, MD
Reconstruct/Stabilize Historic Stone Wall and Towpath
McMahon’s Mill to Lock 42
CHOH
PMIS NO. 151201
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
July 1, 2020
CHOH 151201 TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work
01 26 01 Contract Modification Procedures
01 27 00 Contract Line Items
01 31 00 Project Management & Coordination
01 32 16 Construction Schedule
01 32 33 Photographic Documentation
01 33 23 Submittal Procedures
01 35 23 Safety Requirements
01 35 91 Historic Preservation Treatment Procedures
01 40 00 Quality Requirements
01 42 00 Reference Standards
01 50 00 Temporary Facilities and Controls
01 57 19.12 Noise & Acoustics Management
01 57 23 Temporary Storm Water Pollution Prevention
01 67 00 Product Requirements
01 73 40 Execution
01 74 19 Construction Waste Management and Disposal
01 77 00 Closeout Procedures
DIVISION 02 – EXISTING CONDITIONS (not used)
DIVISION 03 - CONCRETE
03 30 00 Cast-in-Place Concrete
DIVISION 04 - MASONRY
04 42 00 Stone Masonry for Headwalls
04 43 00 Stone Masonry
DIVISION 05 - 30 (not used)
DIVISION 31 - EARTHWORK
31 10 00 Site Clearing
31 20 00 Earth Moving
31 25 00 Erosion and Sediment Control
DIVISION 32 EXTERIOR IMPROVEMENTS
32 92 00 Seeding and Topsoil
DIVISION 33 - UTILITIES
33 41 00 Storm Utility Drainage Piping
APPENDICES
APPENDIX A Geotechnical Report
APPENDIX B Geotechnical Report Addendum No. 1
CHOH - 151201 01 11 00 - 1
091015 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Contractor use of premises.
4. Public use of site.
5. Work Restrictions.
6. Special Construction Requirements.
7. Soils Investigation Report.
8. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Chesapeake and Ohio Canal Historical Park, Big Slackwater - McMahon’s
Mill to Lock 42, Williamsport, Maryland.
B. The Work consists of the following:
1. The Work includes the reconstruction and stabilization of the towpath supporting walls, realignment and resurfacing of the towpath, removal of vegetation, and compliance with all permit requirements.
C. Project will be constructed under a single prime contract.
1.3 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations during the construction period as indicated on the Drawings by the Contract limits.
B. Storage of Materials: Confine storage of materials to areas indicated on the Documents.
C. Preservation of Natural Features and Protection of a Cultural Resource:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
CHOH - 151201 01 11 00 - 2
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
6. Restore cultural resource adhering to guidance as per the Secretary of the Interior's
Standards for the treatment of Historic Properties.
D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Construction Camp: Establishment of a camp within the park will not be permitted.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park
Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
G. The primary access to the site will be at the south end of the Project at McMahon’s Mill;
however, access at the north end will also be allowed.
1.4 PUBLIC USE OF SITE
A. The towpath will be closed to the public during construction. Provide restrictive signage at the towpath at the both ends of the Project.
B. Contractor shall maintain visitor access to downstream towpath and provide detour route and signage in accordance with section “Work Restrictions” 1.6.K.
C. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public. Parking area and road closures will be permitted, when required, upon specific approval of Contracting Officer. The Contractor must make provision for traffic control – flagmen, signage, etc. – at public roads.
1.5 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Contactor shall submit requests a minimum of 48 hours in advance of the work to the Contracting Officer for approval.
CHOH - 151201 01 11 00 - 3
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.6 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m. to 7 p.m., Monday through Friday, daylight permitting, except when otherwise indicated.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by
Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
D. Portions of the existing towpath are very narrow; therefore, construction will have to be performed from two ends and from barges located in the river.
E. Constricted space at McMahon's Mill will require close coordination of deliveries, vehicles, storage, etc.; limited storage space. Turning radius limitations at staging area. See Sheet G5 for additional staging area information.
F. Any water vessels used for construction (i.e., barge) shall be decontaminated prior to use in the
Potomac River so they are free of any vegetation, animals, mud, and any other organic material that is not native to the river.
G. If previously unknown archeological resources are discovered during construction, all work in the immediate vicinity (600 feet) of the discovery shall be halted until the resources are identified and documented and an appropriate mitigation strategy developed, if necessary, in accordance with pertinent laws and regulations, including the stipulations of the 2008
Programmatic Agreement Among the National Park Service (U.S. Department of the Interior), the Advisory Council on Historic Preservation, and the National Conference of State Historic
Preservation Officers.
H. To minimize potential impacts on northern long-eared bat habitat, removal of trees greater than
4-inches in diameter at breast height (OBH) will be prohibited from June 1 to July 31.
CHOH - 151201 01 11 00 - 4
I. Due to proximity of the site to the river, an environmentally friendly hydraulic oil/fluids shall be used in heavy machinery. Contractor shall submit the proposed product for NPS review/approval prior to beginning construction.
J. Contractor is to provide temporary bridge reinforcement and protection for existing stream and culvert crossings throughout all phases of construction. Contractor shall prepare and submit a temporary bridge reinforcement and protection plan for NPS review/approval prior to beginning construction. Load ratings are unknown. Take extra care not to damage the existing bridges, existing stone headwalls or culverts. Repair the damaged areas/features at no additional time or cost to the government.
K. Contractor shall prepare and submit a detour plan for NPS review/approval prior to beginning construction. Contractor will be responsible for installing and maintaining required detour route including signage, temporary barriers, and temporary trails.
L. Contractor shall prepare and submit a staging plan for NPS review/approval prior to beginning construction. Contractor will be responsible for installing and maintaining required including signage, contractor access, temporary barriers and gates, temporary site improvements, security fencing related to staging areas and contractor access.
M. If required to obtain proper placement of material, the Contractor has the option of using either mooring piles, anchors, spud barges, or other suitable methods approved by the Contracting
Officer. Contractor shall prepare and submit Mooring Facility Plan for review/approval prior to beginning construction.
N. Construction employees will be instructed on the sensitivity of the general environment, and their activity will be monitored by NPS.
O. Best management practices shall be followed to avoid exposure of the terrestrial and aquatic environment to risks, such as fuel spills. Contractor shall prepare and submit a Spill Prevention
Plan meeting all State of Maryland requirements for NPS review/approval prior to beginning construction.
1.7 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.
1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.
B. It is expected that high water will interrupt work several times throughout the contract term.
Contractor must provide a written contingency plan for such events prior to the start of the
Work. The Contractor’s plan shall include employee and visitor safety, protection of Work, protection of the environment, and protection of equipment.
C. Preservation of Protected Species:
1. Coordinate with the NPS regarding protected species:
CHOH - 151201 01 11 00 - 5
a. To minimize potential impacts on northern long-eared bat habitat, removal of trees greater than 4-inches DBH is prohibited from June 1 to July 31. Contractor shall coordinate with NPS and USFWS to minimize impacts to bats when possible.
2. Waterways Special Conditions
a. To protect aquatic species, MD-DNR prohibits in-stream work during certain times of the year as determined by the classification of the stream. This section of the
Potomac River is classified as a Use I Waters. MD-DNR prohibits in-stream work within Use I Waters during the period March 1 through June 15, inclusive, during any year unless MD-DNR issues a waiver. The NPS is currently filing a request for an instream waiver from MD-DNR. NPS does not warrant or guarantee that a waiver will be granted.
b. Contractor shall be expected to minimize instream impacts and abide by any and all state and federal permit conditions regarding instream work and the protection of water quality. The contractor will coordinate with NPS and MD-DNR to minimize in-stream impacts to waterways when possible and any other special conditions.
1.8 SOILS INVESTIGATION REPORT
A. A soils investigation report entitled “Geotechnical Engineering Report”, dated May 12, 2017, along with an addendum dated April 24, 2020, has been prepared for the NPS by Schnabel
Engineering.
B. A copy of the report and addendum are included with this package as Appendices.
C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
CHOH - 151201 01 26 01 - 1
031414 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
CHOH - 151201 01 26 01 - 2
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
CHOH - 151201 01 26 01 - 3
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate
CHOH - 151201 01 26 01 - 4
Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS.
All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)
CHOH - 151201 01 26 01 - 5
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized, then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10% Profit……………………8%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, then the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
CHOH - 151201 01 26 01 - 6
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
CHOH - 151201 01 27 00 - 1
082714 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends, and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 1: Mobilization & Demobilization.
1. This item consists of mobilization and demobilization.
2. Measurement for payment will be made on lump sum items (L.S.).
3. Payment will be made at the contract lump sum price (L.S.).
B. Contract Line Item No. 2: Contractor Staging & Access/ General Conditions.
1. This item consists of preparation of laydown and materials storage areas, trailers, and all access equipment including barges and cranes.
2. No separate measurement will be made on lump sum items (L.S.).
3. Payment will be made at the contract lump sum price (L.S.).
C. Contract Line Item No. 3: Erosion Control/Oil Seepage Control & Water Testing.
1. This item consists of activities required to protect water quality.
2. No separate measurement will be made on lump sum items (L.S.).
3. Payment will be made at the contract lump sum price (L.S.).
D. Contract Line Item No. 4: Tree Removal (12” and Smaller).
1. This item consists of all site clearing and tree removal along the towpath for trees 12” in diameter and smaller including stump removal, roots, obstructions, debris and backfilling as indicated in drawing notes and specifications.
2. Measurement for payment will be per tree removed.
3. Payment will be made at the contract price per tree removed.
CHOH - 151201 01 27 00 - 2
E. Contract Line Item No. 5: Tree Removal (13” or Larger).
1. This item consists of all site clearing and tree removal along the towpath for trees 13” in diameter and larger including stump removal, roots, obstructions, debris and backfilling as indicated in drawing notes and specifications.
2. Measurement for payment will be per tree removed.
3. Payment will be made at the contract price per tree removed.
F. Contract Line Item No. 6: Site Clearing and Grubbing.
1. This item consists of all site clearing and grubbing as indicated in drawing notes and specifications.
2. Includes existing tree limbing and pruning as indicated on the drawings and directed by
CO.
3. No separate measurement will be made on lump sum items (L.S.).
4. Payment will be made at the contract lump sum price (L.S.)
G. Contract Line Item No. 7: Towpath Excavation and Backfill.
1. This item consists of excavation, removal and disposal or re-use of suitable fill as required to construct towpath and shoulders. Includes suitable fill placement, grading and compaction.
2. Measurement for payment will be per cubic yard of soil cut and hauled.
3. Payment will be made at the contract price per cubic yard.
H. Contract Line Item No. 8: Wall Excavation and Backfill.
1. This item consists of excavation, removal and disposal or re-use of suitable fill as required behind existing, extended or reconstructed walls. Includes suitable fill placement, grading and compaction. Stone backfill behind walls is listed under CLIN
Item No. 13.
2. Measurement for payment will be per cubic yard of soil cut and hauled.
3. Payment will be made at the contract price per cubic yard.
I. Contract Line Item No. 9: Towpath.
1. This item consists of construction of the towpath surface and base courses including all geotextile placement.
2. Measurement for payment will be per cubic yard of for each course installed.
3. Payment will be made at the contract price per cubic yard.
J. Contract Line Item No. 10: Topsoil and Seeding.
1. This item consists of installation of topsoil and seeding.
2. Includes topsoil placement, finish grading and compaction
3. Measurement for payment will be per square yard of area topsoiled and seeded.
4. Payment will be made at the contract price per square yard.
K. Contract Line Item No. 11: Culvert Replacement.
1. This item consists of removal of existing 18” corrugated metal pipes, installation of 18”
HDPE pipes including excavation, backfill, pipe bedding and compaction. The cost also includes modifications to existing stone headwalls and construction of new stone headwalls.
CHOH - 151201 01 27 00 - 3
2. Measurement for payment will be per linear foot of pipe installed.
3. Payment will be made at the contract price per linear foot.
L. Contract Line Item No. 12: #57 Stone Backfill Behind Walls.
1. This item consists of installation of #57 stone backfill behind existing, extended or reconstructed walls as indicated on the structural plans including all geotextile placement.
Includes stone placement, grading and compaction.
2. Measurement for payment will be per cubic yard of #57 stone installed.
3. Payment will be made at the contract price per cubic yard.
M. Contract Line Item No. 13: Repair Existing Dry-laid Stone Walls.
1. This item consists of re-chinking existing dry-laid stone wall along the river.
2. Measurement for payment will be per cubic foot of wall treated.
3. Payment will be made at the contract price per cubic feet.
N. Contract Line Item No. 14: Reconstruct Existing Stone Walls.
1. This item consists of reconstructing existing dry-laid and mortared stone walls along the river.
2. Measurement for payment will be per cubic foot of wall reconstructed
3. Payment will be made at the contract price per cubic feet.
O. Contract Line Item No. 15: Extend Existing Dry-laid Stone Walls.
1. This item consists of constructing a dry-laid vertical extension on top of existing dry-laid stone wall along the river.
2. Measurement for payment will be per cubic foot of wall extension.
3. Payment will be made at the contract price per cubic feet.
P. Contract Line Item No. 16: Extend Existing Mortared Stone Walls.
1. This item consists of construction of a mortared vertical extension on top of existing mortared stone wall along the river.
2. Measurement for payment will be per cubic foot of wall extension.
3. Payment will be made at the contract price per cubic foot.
Q. Contract Line Item No. 17: Repair Existing Mortared Stone Walls.
1. This item consists of repointing or setting stone with mortar to match existing mortared stone walls along the river.
2. Measurement for payment will be per square foot of wall repointed or stone set with mortar.
3. Payment will be made at the contract price per square foot.
3.2 BID OPTIONS
A. Contract Line Item No. 18: Bid Option A – Station 0+00 to 4+00 - Reconstruct/Stabilize
Historic Stone Wall & Towpath
CHOH - 151201 01 27 00 - 4
1. This item consists of all labor and materials required to reconstruct/stabilize Historic
Stone Wall and Towpath from Station 0+00 to Station 4+00 per the drawings and specifications.
2. Measurement for payment will be lump sum or percentage complete of line item per schedule of values.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item No. 19: Bid Option B – Station 28+00 to 38+50 - Reconstruct/Stabilize
Historic Stone Wall & Towpath
1. This item consists of all labor and materials required to reconstruct/stabilize Historic
Stone Wall and Towpath from Station 28+00 to Station 38+50 per the drawings and specifications.
2. Measurement for payment will be lump sum or percentage complete of line item per schedule of values.
3. Payment will be made at the contract lump sum price.
C. Contract Line Item No. 20: Bid Option C – Station 38+50 to 51+75 - Reconstruct/Stabilize
Historic Towpath
1. This item consists of all labor and materials required to reconstruct/stabilize Historic
Towpath from Station 38+50 to Station 51+75 per the drawings and specifications.
2. Measurement for payment will be lump sum or percentage complete of line item per schedule of values.
3. Payment will be made at the contract lump sum price.
D. Contract Line Item No. 21: Bid Option D – Widen Towpath Trail to 8’
1. This item consists of all labor and materials required to widen the towpath trail to 8’ at locations shown on the plans per the drawings and specifications.
2. Measurement for payment will be lump sum or percentage complete of line item per schedule of values.
3. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
CHOH - 151201 01 31 00 - 1
091015 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on
Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination.
3. Submittals
4. Requests for Information (RFIs).
5. NPS/DSC SharePoint Project Website.
6. Project meetings.
7. Environmental Coordination.
8. Permits
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction: An Agency that has been granted legal authority over a location, action, or resource. This authority includes the ability to issue a permit or other legal permission document.
B. Construction Permits – Contractor Provided: Permits obtained by the Contractor based on the means and methods to conduct the work. Construction Permits are typically issued by the Agency to the Contractor and not to the National Park Service (NPS). Examples of typical
Contractor Provided Permits are: NPDES Construction Permit (ground disturbance), dewatering permit, permit for work in a roadway (with traffic management plan), temporary utility tap permit, etc.
C. Government Furnished Permits: Obtained by National Park Service (NPS), usually through the Architect/Engineer (A/E) or a consultant, during the design process (Predesign (PD) through Construction Documents (CD)) and are usually concerned with impacts to resources protected by federal law. However, GF permits can include other permits that are obtained for the convenience of the Government during design. GF permits are "furnished" to the Contractor in the Request for Proposal (RFP) and as part of the final contract documents.
The Contractor must comply with GF permit provisions. Examples of typical GF permits: Clean
Water Act (CWA) 404 dredge and fill permit, CWA Water Quality Certification (often state administered), Highway Right-of-Way Permit, etc.
CHOH - 151201 01 31 00 - 2
1.3 CONSTRUCTION COORDINATION
A. Special Coordination: Before staging, the Contractor shall coordinate construction logistics with NPS, submit a work plan, and gain approval prior to beginning the work.
1. Access will require the construction of a dock at McMahon’s Mill for use by construction barges, in addition to work from the land.
2. In order to work safely on or near water, Contactor shall comply with 29CFR1926.106.
A competent person shall be in charge of loading and unloading barges to prevent craft instability and capsizing. Whenever heavy equipment is to be used along the tow path special care shall be exercised to identify any areas capable of collapse. All work must be done under the supervision of a full‐time safety officer.
B. General Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
C. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
D. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
CHOH - 151201 01 31 00 - 3
1.4 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference. If all these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. Temporary Storm Water Pollution Prevention Plan (SWPP).
11. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit.
b. The Agency(ies) with Jurisdiction issuing the permit.
c. Information required from the Government to complete the permit application.
12. Logistics Work Plan.
13. Flood Plan: Include establishment of temporary monitoring device at the site to track water levels, outline frequency and source of monitoring forecasted river levels, action plans and site-specific flood procedures, responsibilities, and other pertinent procedures/information for planning, responding, and recovering from a flood. All items listed must be provided to the Contracting Officer before the Pre-Construction
Conference is held.
14. Historic Preservation Treatment Plan.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
CHOH - 151201 01 31 00 - 4
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:
1. Enter the general information at the top of the form.
2. Under the “Action” section at the bottom of the form, select “Question” then select
“CMR” in the drop-down of the “Send to” box.
3. Enter the details of the question and attach related documents.
4. Select “Submit Form” at the bottom of the page.
D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO's action on RFIs may result in the need for a change to the Contract Time or the
Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
1.6 PROJECT WEB SITE
A. Use the NPS/DSC SharePoint Project website for communication throughout the contract period. The NPS/DSC SharePoint Project website will be used for the following functions:
1. Project directory.
2. Project correspondence.
3. Meeting agendas and minutes.
CHOH - 151201 01 31 00 - 5
4. Contract modifications forms and logs.
5. RFI form and processing.
6. Task and issue management.
7. Photo documentation.
8. Baseline schedule, schedule updates and calendar management.
9. Submittal form and processing.
10. Payment coordination documentation.
11. Drawing and specification document hosting, viewing, and updating.
12. Online document collaboration.
13. Reminder and tracking functions.
14. Archiving functions.
15. Notification of submittal and RFI statuses and current responsible party.
16. Permits and addendums
B. Some documents however are not suitable to be shared using the NPS/DSC SharePoint Project website. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using the NPS/DSC SharePoint Project website and shall be coordinated with the SharePoint Project team as appropriate.
C. Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the NPS/DSC SharePoint Project website. For login procedures and other SharePoint information, refer to the Workflows website at http://www.nps.gov/dscw/precon_spproj.htm.
D. All users will be required to have the following software packages:
1. Internet Explorer version 7 or later.
2. Adobe Acrobat Professional (Pro) version 9 or later
1.7 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Jobsite Safety.
4. Resolution of comments on required Division 01 documents.
5. Coordination of Subcontractors.
6. Labor law application.
7. Modifications.
8. Payments to Contractor.
9. Payroll reports.
10. Contract time.
11. Liquidated damages.
12. Contractor Performance Evaluation.
13. Display of Hotline posters.
14. Notice to proceed.
15. Correspondence procedures.
CHOH - 151201 01 31 00 - 6
16. NPS/DSC SharePoint Project website.
17. Acceptance/rejection of work.
18. Progress meetings.
19. Submittal procedures.
20. NPS Final Accessibility Inspection.
21. Environmental requirements.
22. Permit requirements.
23. As-constructed drawings/operation and maintenance (O&M) manuals.
24. Saturday, Sunday, holiday and night work.
25. Reference materials.
26. Value engineering.
B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the
Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.
All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Submittal status.
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications.
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections,
h. Construction Schedule update (provide updated CPM).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
k. Permit requirements.
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related RFIs.
d. Related Change Orders.
CHOH - 151201 01 31 00 - 7
e. Purchases.
f. Deliveries.
g. Submittals.
h. Review of mockups.
i. Possible conflicts.
j. Compatibility requirements.
k. Time schedules.
l. Weather limitations.
m. Manufacturer's written instructions.
n. Warranty requirements.
o. Compatibility of materials.
p. Acceptability of substrates.
q. Temporary facilities and controls.
r. Space and access limitations.
s. Regulations of agency(ies) with jurisdiction.
t. Testing and inspecting requirements.
u. Installation procedures.
v. Coordination with other work.
w. Required performance results.
x. Protection of adjacent work.
y. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if the conference cannot be successfully concluded.
Initiate whatever actions are necessary to resolve impediments to performance of the
Work and reconvene the conference at earliest feasible date.
1.8 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate a party responsible for overseeing the
Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .