This document contains questions and answers related to solicitation number 140P2020R0079 for the CHOH-151201 Reconstruct/Stabilize Historic Stone Wall & Towpath project from McMahons Mill to Lock 42. The solicitation involves reconstructing and stabilizing historic stone walls and a towpath along the Potomac River between the specified locations. The questions and answers provide additional details on tree sizes to be removed, permits that have been obtained by the government, the instream work waiver request submitted to the state, clarifications on backfill requirements below the waterline, and an extension of both the proposal question deadline and bid due date to August 6th and August 24th, 2020 respectively. Legible wage determination rates are also included as an update.

The document clarifies requirements and specifications to address contractor questions on the scope of work. Bidders should prepare their proposals assuming an instream waiver will be obtained, though changes would be addressed if the waiver is denied. Additional details in plan sheets and specifications have also been provided in the question responses.

View the file

Other files

File Type Posted
A07_02_20200821_SECTION 01 27 00 DEFINITION OF CONTRACT LINE ITEMS_0007.pdf PDF
A07_04_20200821_Structural DrawingsRev3_0007.pdf PDF
A07_05_20200821_Section B_Contract Price Schedule_0007.pdf PDF
A07_01 Questions and Answers Round 4 Final_0007.pdf PDF
Sol_140P2020R0079_Amd_0007.pdf PDF
A07_03_20200821_SECTION 044300 - STONE MASONRY_0007.pdf PDF
Sol_140P2020R0079_Amd_0006.pdf PDF
Sol_140P2020R0079_Amd_0005.pdf PDF
2020_0811 151201 - C2.01a DEMO & ES Ext_A04_03_0004.pdf PDF
20200812 MDE_USACE Authorization_A04_02_0004.pdf PDF
QA Round 3 QA_FINAL_A04_01_0004.pdf PDF
Sol_140P2020R0079_Amd_0004.pdf PDF
140P2020R0079 Amend 04_0004.pdf PDF
Sol_140P2020R0079_Amd_0003.pdf PDF
A03_01 - 011100 - SUMMARY OF WORK_REV_0003.pdf PDF
A03_04 - B08 - Solit_Equals_0003.doc DOC document
A03_03 - B08 BidBond_SF24-16d_0003.pdf PDF
A03_02 - 151201 CHOH ALL FINAL CD-Drawings - REV2_0003.pdf PDF
A02_01 CHOH 151201 CD-ContractPriceSchedule FINAL_0002.pdf PDF
A02_04_Section H Special Clause COVID_0002.pdf PDF
A02_02 CHOH 151201 CD-ContractPriceSchedule FINAL_0002.xlsx XLSX spreadsheet
A02_03 Contract Line Items FINAL_0002.pdf PDF
A02_05_52.211-18 Variation Est Qty Clause_0002.pdf PDF
A02_06_CHOH 151201 Q and A Round 1 7-30-20_0002.pdf PDF
A02_07 151201 CHOH ALL FINAL CD-Drawings - REV1_0002.pdf PDF
Sol_140P2020R0079_Amd_0002.pdf PDF
Atch 01 CHOH 151201 Site Visit Attendees July 14 2020 1130 AM_0001.pdf PDF
Atch 03 PreProposal Presentation 071420_0001.pdf PDF
Atch 04 PriceSchedVol2 Amend01_0001.xlsx XLSX spreadsheet
Sol_140P2020R0079_Amd_0001.pdf PDF
Atch 02 CHOH 151241_PreBid_Agenda 7-14-20_0001.pdf PDF
B08_4 -1048516_Big_Slackwater_T_EF.pdf PDF
B08_SF1442 140P2020R0079.pdf PDF
B08_3 - 151201 CHOH ALL FINAL CD-Drawings Part II.pdf PDF
B08_1 - 151201 CHOH ALL FINAL CD-Drawings Part I sig.pdf PDF
B08_2 - 151201 CHOH ALL FINAL CD-Specs.pdf PDF
B08_5 - CHOH_151201-Reduced - 081632 Final Report-Enviroscan.pdf PDF
B08_12 - Atch12GenRefsVol2.doc DOC document
B08_7.1 - Wage Determination MD20200022 Heavy 6-5-20.pdf PDF
B08_6 - PriceSchedVol2.xlsx XLSX spreadsheet
B08_11 - Atch11SubKPlanFormVol2.doc DOC document
B08_10 - Atch10PastPerfVol1.docx DOCX document
B08_13 - Atch13HazMatVol2.doc DOC document
B08_7.2 - Wage Determination MD20200005 Dredging 1-3-20.pdf PDF
B08_9 - Atch09ExpVol1.docx DOCX document
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Colum n6 ROUND #2 CHOH 151201 Question

Answer

In the plan sheet series C2.xx there are various plans sheets that identify trees for removal but do not identify the size of the tree. Please provide sizes of these trees..

Additional tree size data has been added as a redline to the "Revision 2" plans on the Sheet C2.XX series. These are provided along with this response. Of note is that the diameter of trees scheduled for demo and those anticipated to remain were both included in the redlined "Revision 2".

Section 01 31 00 1.9.B details the permits that the Government has procured and specifies that the contractor shall adhere to the terms and provisions of these permits. Please provide copies of these permits so the contact and bid responsibly.

Permit applications are ongoing with USACE & MDE. Any substantial changes in scope that result in conditions/constraints provided with the permit authorizations will be addressed per

52.243‐4 CHANGES.

Section 01 11 00 ‐ 1.7.C.2 states, "This section of the Potomac River is classified as a Use I Waters. MD‐DNR prohibits in‐ stream work within Use I Waters during the period March 1 through June 15, inclusive, during any year unless MD‐DNR issues a waiver. The NPS is currently filing a request for an instream waiver from MD‐DNR. NPS does not warrant or guarantee that a waiver will be granted."

This vague and will cause a large dissimilarity in costs among bidders if all do not use the same ideology, we suggest that this language be modified to the following:

DELETE: "NPS does not warrant or guarantee that a waiver will be granted.

ADD: "Bidders shall prepare their bid assuming that the MD‐ DNR will issues a waiver. If the MD‐DNR rejects the request, any additional costs will be addressed per 52.243‐4 CHANGES."

Concur, subject paragraph was edited to "a.To protect aqua c species, MDE prohibits in‐stream work during certain times of the year as determined by the classification of the stream. This section of the Potomac River is classified as a Use I Waters. MDE prohibits in‐stream work within Use I Waters during the period March 1 through June 15, inclusive, during any year unless MDE issues a waiver. The NPS has submitted an instream waiver and submitted to MD‐DNR and MDE. Coordination with these entities indicates that the waiver will very likely be granted. For bidding purposes, the contractor should assume that MDE will be issuing a waiver. If the waiver is not issued, then any impacts to the contract will be addressed under 52.243‐4 CHANGES." Revised section 011100 has been provided with this response.

For the Wall Extension at Station 21+69 ‐ 21+90: is it the government’s intention to place a portion the 57 stone below the water table?

As shown on Sheet S1.2, free draining stone is required to be placed under the water line within the 1H:1V line of influence projected up from the toe of the stone wall. However, due to constraints with placement of #57 stone below the water line, Detail 1 / Sheet S1.2 was revised to require that "IN REACHES

REQUIRED TO HAVE FREE DRAINING BACKFILL PLACED BENEATH

WATER, BACKFILL WITH WALL STONE MATERIAL (SALVAGED OR

NEW) BELOW THE WATER LINE. PACK VOIDS TIGHT WITH HEART

STONES IN SIMILAR MANNER TO WALL CONSTRUCTION." Redline revisions were added to sheet S1.2, and provided along with this response

For the Wall Extension at Station 12+55 ‐ 12+75 is it the government’s intention to place a portion the 57 stone below the water table?

As shown on Sheet S1.2, free draining stone is required to be placed under the water line within the 1H:1V line of influence projected up from the toe of the stone wall. However, due to constraints with placement of #57 stone below the water line, Detail 1 / Sheet S1.2 was revised to require that "IN REACHES

REQUIRED TO HAVE FREE DRAINING BACKFILL PLACED BENEATH

WATER, BACKFILL WITH WALL STONE MATERIAL (SALVAGED OR

NEW) BELOW THE WATER LINE. PACK VOIDS TIGHT WITH HEART

STONES IN SIMILAR MANNER TO WALL CONSTRUCTION." Redline revisions were added to sheet S1.2, and provided along with this response

Required offer documents lists SF 24 Bid Bond and is stated to be included as Attachment 8 (Bid Bond 08.2016 2). No attachment 8 has been included with the solicitation, can one be provided?

Attachment 8 Bid Bond has been included as referenced in Section J

Solicitation page 159 of 176 references an attached form 'Proposed Equals' to be submitted with the bid but no attachment was included with the bid documents. Is this document required, and if so can it be provided?

B08_Atch14 Equals has been added to Section J of the soliciation

Based on the forthcoming bid date extension referenced in your email from 7/23/20 from August 4 to August 13, we request a similar extension for the Proposal Question deadline to seven days prior to bid ‐ August 6. Please confirm.

The bid date has been extended to August 24, 2020, 1400MT (Amendment 02)

The wage rate determinations available with the bid documents for this project are unreadable. Can an updated copy of the required wages rates be provided?

Confirmed version(s) uploaded to BetaSAM as legible. Updated rates for Wage Determination MD20200022 Heavy and MD20200005 Construction: Heavy Dredging are available at https://beta.sam.gov/search?index=wd

Solicitation page 1, sections 8 & 13 specify an original and one copy are due electronically to the email address provided. Since this is an electronic‐only bid is the copy necessary or can section 13 be revised to state one signed electronic copy only?

Refer to SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO

OFFERORS.

The time offers are due is listed as 1600 (4:00PM) local time. Is this local time for the project site or local time for the office location offers are sent to (1600 MT‐4:00PM or 1800ET

6:00PM)?

52.215‐1(c)(3)(i) states Solicitation "If no time is specified in the solicitation the time for receipt is 4:30 p.m., local time". Refer to

SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO

OFFERORS.

File details come from the government source that posted it. Updated .