Amendment_0002_Complete.pdf

PDF 389 KB Posted

Attached to
NOAA Ship Ronald H. Brown: Mid-Life Refit Federal contract opportunity
Solicitation number
1305M221RNMAN01155
Issued by
Department of Commerce National Oceanic and Atmospheric Administration

About this file

This amendment modifies a solicitation for the mid-life refit of the NOAA Ship Ronald H. Brown. The refit includes upgrades to systems such as repowering, bow thrusters, Z-drives, potable water, chilled water, sewage, science refrigeration, uncontaminated seawater, air handling, HVAC, tank level indicators, navigational equipment, radar, lighting, and vent renewals. Piping and steel replacements are also included based on an ABS report. The amendment extends the response deadline to August 20, 2021, adds a second ship check opportunity, and reduces required payment and performance bond amounts to 20% of the total price. It addresses vendor questions on bonding calculations, file access issues, drydock certification needs, and component specifications. The refit will be awarded as a firm-fixed-price contract under FAR Parts 12 and 15 to provide all labor, materials and equipment for the modification at the selected contractor's drydock facility.

View the file

Other files for this federal contract opportunity

Other files attached to NOAA Ship Ronald H. Brown: Mid-Life Refit, newest first.
File Type Posted
SF30_Amendment_0008_RBML_Complete.pdf PDF
SF30_Amendment_0007_RBML_Complete.pdf PDF
SF30_Amendment_0006_RBML_Complete.pdf PDF
20065.01-02-501-01_Bow Thruster Equipment Removal and Installation Plan_Rev(-) signed.pdf PDF
WP-27 Transducer Modifications V1.pdf PDF
428711_EM 124 - SAT procedure.pdf PDF
SF30_Amendment_0004_RBML_Complete.pdf PDF
18038.02-10A-514-01 AC Spaces General Electrical Modifications_Rev-_20201023.pdf PDF
429347_HAT PROCEDURE SBP 27 and SBP 29.pdf PDF
428709_em124_hat_procedure.pdf PDF
RB-528- 6932929.pdf PDF
WP-11 Ships Stores Refrigeration Equipment Replacement V1.pdf PDF
WP 07B - AC Controls Upgrades V1.pdf PDF
SF30_Amendment_0003_RBML_Complete.pdf PDF
Tech Man RB-437-00.pdf PDF
Keen-K4RHX100M2-43-4.625-Inch-Implr-Pump-Data.pdf PDF
18038.02-12-514-01 Chilled Water Diagram_Rev- signed.pdf PDF
6932929.pdf PDF
20065.01-01-201-01 Machinery Arrangements_Rev(P1).pdf PDF
20065.01-01-536-01 FW Cooling Diagram_Rev(P1).pdf PDF
Consolidated References_07142021.pdf PDF
18038.02-01-440-02_Machinery Control System Points List_Rev A_signed.pdf PDF
18038.02-10C-512-01_AHU5 Zone Redesign - Arrangements_Rev- signed.pdf PDF
20065.01-01-300-01_Electrical One-Line Diagram_Rev(P1).pdf PDF
RB_461A_RB-461A-07_RevA_Sht001-024_ABS_MULTIBEAM FAIRING CONSTRUCTION.pdf PDF
18038.02-10C-512-02_AHU5 Zone Redesign - AC System Modifications_Rev- signed.pdf PDF
20065.01-01-517-01 Waste Heat Diagram Rev (P1).pdf PDF
20065.01-01-320-01_Propulsion Switchboard Layout_Rev(P1).pdf PDF
20065.01-01-320-02_Ship Service Switchboard Layout_Rev(P1).pdf PDF
20065.01-01-513-01_Generator Room Ventilation Upgrades_Rev(P1).pdf PDF
18038.02-11A-512-01 HVAC Makeup Air Upgrades_Rev- signed.pdf PDF
20065.01-01-300-06_Electrical One-Line Removals Diagram_Rev(P1).pdf PDF
20065.01-01-551-01 Compressed Air Diagram_Rev(P1).pdf PDF
20065.01-01-543-01 Waste Oil Diagram_ Rev(P1).pdf PDF
20065.01-01-260-01 Fuel Oil System Diagrams_ Rev(P1).pdf PDF
20065.01-01-513-02_Natural Ventilation Trunk Modifications_Rev(P1).pdf PDF
18038.02-10B-514-01_AC Control System Mods Diagram_Rev- signed.pdf PDF
05-521-01_Rev 0.pdf PDF
WP-25 Steel Replacement REV 1.pdf PDF
RB_101-6932803_RevE_SHT001-0013.pdf PDF
20065.01-01-532-01 SW Cooling Diagram_Rev(P1).pdf PDF
J.4 USDL Poster.pdf PDF
J.8 Standard Form 1416 - Payment Bond.pdf PDF
J.1 SF-33_Solicitation_Offer_Award.pdf PDF
J.2 Section B - Schedule of supplies or services.xlsx XLSX spreadsheet
RFP - 1305M221RNMAN01155_RHB Mid-Life.pdf PDF
J.3 Specification (Work Packages and References).zip ZIP file
J.5 Past Performance Information Form.rtf RTF text file
J.6 Past Performance Questionnaire.docx DOCX document
J.7 Standard Form 1418 - Performance Bond.pdf PDF
Show all 50

NOAA Ship Ronald H. Brown: Mid-Life Refit has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

1305M221RNMAN01155

9B. DATED (SEE ITEM 11)

04/29/2021

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

2. AMENDMENT/MODIFICATION NUMBER

A0002

3. EFFECTIVE DATE

06/11/2021

4. REQUISITION/PURCHASE REQUISITION NUMBER

NMAN2100-20-01155

5. PROJECT NUMBER (If applicable)

CODE AJ930073 7. ADMINISTERED BY (If other than Item 6) CODE 6. ISSUED BY

NOAA/ERAD

200 GRANBY STREET, NORFOLK, VA 23510

Andrew Northcutt, andrew.northcutt@noaa.gov, 757-441-6457

See Block 6

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

is not extended. The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required) N/A

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

NOAA SHIP RONALD H. BROWN MID-LIFE REFIT

Please see continuation page for details pertaining to this amendment.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE OF PAGES

X

6/11/2021

Andrew Hildebrandt

Jessica.Loftus Rectangle

Continuation Page – Amendment 0002

RONALD BROWN MID-LIFE REFIT

RFP# 1305M221RNMAN01155

The purpose of this Amendment is as follows:

1. Provide RFP Revision 1. Changes made in Revision 1 include:

a. Extend to Solicitation Closing date/time to Friday, August 20, 2021 at 12:00 PM

Eastern (Pages 2, 3, and 66)

b. Add a second ship check scheduled for August 3-6, 2021 in San Diego, CA (Page 65)

c. Reduce the Payment Bond and Performance Bond requirements from 100% to 20%

(Page 16)

d. Add language to L.4 FAR 52.212-1 INSTRUCTIONS TO OFFERORS-

COMMERCIAL ITEMS (JUN 2020) pertaining to email quarantine precautions as described in Amendment 0001 (Page 66)

2. Provide the following information: If any vendor has difficultly accessing the Reference files in the Google Drive linked in the Beta.SAM solicitation posting, please contact Andrew

Northcutt at 757-441-6457 or andrew.northcutt@noaa.gov and alternative means to transmit the files will be provided.

3. Address questions received from vendors in response to the RFP:

Question 1

This inquiry is in regard to RFP clause H.26 FAR 52.228-16 PERFORMANCE AND

PAYMENT BONDS-OTHER THAN CONSTRUCTION (NOV 2006):

(a) Definitions. As used in this clause-

"Original contract price" means the award price of the contract or, for requirements contracts, the price payable for the estimated quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.

(b) The Contractor shall furnish a performance bond (Standard Form 1418) for the protection of the Government in an amount equal to 100 percent of the original contract price and a payment bond (Standard Form 1416) in an amount equal to 100 percent of the original contract price.

Question 1a: Would the ADDITIONAL ITEMS – GROWTH be considered Options and be excluded from the Original Contract Price?

mailto:andrew.northcutt@noaa.gov

Response 1a: No, the bond value is based on the total quoted price (Base Items, Growth and

Options Items).

Question 1b: Are the Performance & Payment Bonds considered as one 100% Original

Contract Price? Original Contract Price Twice?

Response 1b: Performance Bonds and Payment Bonds are two separate bonds.

Question 1c: Due to the magnitude of the Mid-Life Refit 100% Bonding will have an adverse impact on the bid pricing for this project. Will NOAA consider either eliminating the

Bond requirement or perhaps lower the Bond percentage of the Original Contract Price to

20% or below?

Response 1c: Yes, the Payment Bond and Performance Bond value requirement has been lowered to 20% of the total quoted price for both.

Question 2

Question 2: There is one file that is password protected “NEED PW-fe800_installation-manual”.

Response 2: A password was not encountered on this file. Please contact Andrew Northcutt at andrew.northcutt@noaa.gov or 757-441-6457 if there are issue accessing particular files.

Alternative means to transmit files will be provided.

Question 3

Question 3: In the Referenced Drawing Download, we have files that don’t have drawings in them. Specifically: NAVSEA 6932948 Rev B

Response 3: The subject Reference file has been verified to contain the drawing files.

Question 4

Question 4: Is there a method to prompt bidders when NOAA makes an update to their bid folders? For example, DropBox would let the estimators know when there was an update.

Response 4: Any changes or updates will be identified in an Amendment. Specific file names/locations will be provided in the Amendment if applicable.

Question 5 mailto:andrew.northcutt@noaa.gov

Question 5: Will NOAA specify Place of Performance? Will there be interport differentials applied to location other than the planned Place of Performance?

Response 5: The Place of Performance will be at the contractor’s drydock facility.

Foreseeable costs and/or interport differentials are not applicable to this solicitation.

Question 6

Question 6: Is a NAVSEA Certified Dry-Dock required to Dock NOAA Ship Ronald H.

Brown? Reference - WP-26 – Reference 24. Standard – Safety Certification Program for

Dry-Docking Facilities and Shipbuilding Ways for U.S. Navy Ships, US Department of

Defense (DoD), MIL-STD 1625C(SH)

Response 6: No, a NAVSEA Certified drydock is not required. The requirements for the drydock are included in WP 026, paragraph 000.2.2.

Question 7

Question 7: Please provide clarification for WP-06 POTABLE WATER SYSTEM

MODIFICATIONS in reference to the two new 4,800 GPD RO Units. Do you have a spec as to what is expected to come with the machines, i.e. media tank, remin filter, auto fresh flush, chlorination system, etc.?

Response 7: The requirements for the two new 4800 GPD RO units are all shown in the proposed package (Ref 12 in WP) from Lifestream.

Question 8

Question 8: Please provide Detail 17-D called out in Item 100.4 Bilge Well Renewals, page

4 of Specifications. Reference 16 doesn’t have a Detail 17-D.

Response 8: A revised Work Package 025 Rev. 1 and additional References are provided.

Question 9

Question 9: Please provide clarification for WP-03 Z-Drive Overhaul in reference to the steering motor planetary reduction gear units, four (4) each per thruster, eight (8) total. The unit nameplate date is as follows: Mfr: Brevini Model: ED 2065/Z-18/M-7.5. The Tag information for each unit is requested. Do you have a spec as to what is expecting to come with the machines, i.e. media tank, remin filter, auto fresh flush, chlorination system, etc.?

Response 9: The Brevini steering motor planetary reduction gear units are proprietary units provided by Brevini to Wartsila. Contact Wartsila Defence directly for quote on these units.

The scope to be provided are just the planetary gear box assemblies.

Question 10

Question 10: What are the resilient mount requirements for the project?

Response 10: Review the resilient mount requirements in Section 2.16.6 of the General

Spec WP-00. That lays out the basic requirements for resilient mounts. The generators shall be supplied with the necessary resilient mounts (WP-01.300.2.2). When the contractor purchases the generator supply and exhaust fans, they should purchase them with the necessary resilient mounts (WP-01.500.5.2). The rest of the mounts will be selected by the contractor.

Question 11

Question 11: Will a copy of the 3d model be released to the bidder or winning shipyard?

Response 11: Due to schedule constraints in the design phase, a 3D model was not developed for WP-01 or WP-02. A 3D model will not be provided for WP-01 and WP-02.

Question 12

Question 12: Do both water makers get removed?

Response 12: Both evaporators in the forward starboard corner will be removed along with the R/O unit. A new evaporator will be installed in place of the two evaporators as part of

WP-01 (WP-01.500.7). A new R/O will be installed in place of the existing R/O unit as part of WP-06 (WP-06.500.2).

Question 13

Question 13: How much of the shore power connection is the contractor responsible for?

Response 13: The shore power circuit breakers and interlocks in the 480VAC ship service switchboard are within Contractor’s scope of supply through Siemens (WP-01.300.4). The

Contractor will be responsible for providing and installing the shore power connection enclosure (WP-01.300.27) and running and terminating the cable between the switchboard and the shore power connection enclosure. Also see Drawing 01-300-01, Electrical One-

Line Diagram.

6 ISSUED BY CODE:
AJ930073:
5 PROJECT NUMBER If applicableRow1:
8 NAME AND ADDRESS OF CONTRACTOR Number street county State and ZIP Code:
undefined:
10A MODIFICATION OF CONTRACTORDER NUMBER:
undefined_2:
10A MODIFICATION OF CONTRACTORDER NUMBER_2:
10B DATED SEE ITEM 13:
11 THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS:
The above numbered solicitation is amended as set forth in Item 14 The hour and date specified for receipt of Offers: Off
is extended: On
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
13 THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTSORDERS:
undefined_3:
B THE ABOVE NUMBERED CONTRACTORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES such as changes in paying office:
undefined_4:
undefined_5:
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
undefined_6:
1:
is not: Off
is required to sign this document and return: Off
14 DESCRIPTION OF AMENDMENTMODIFICATION Organized by UCF section headings including solicitationcontract subject matter where feasible:
15B CONTRACTOROFFEROR:
15C DATE SIGNED: