This document outlines the sea acceptance test procedures for Kongsberg Maritime's SBP 27 and SBP 29 sub-bottom profilers. The test procedures verify system functionality at sea and serve as a record of completion. Key items to be tested include the operator station, transceiver units, fiber optic cables, junction boxes, and connection cables. Tests include power-on self-tests, attitude and navigation data reception, bottom slope compensation, and verification of penetration at various beam angles. Upon completion, authorized personnel must sign the testimonial to accept the results.
This federal contract opportunity seeks a firm fixed price contract to complete a mid-life refit of NOAA Ship Ronald H. Brown. The refit will include upgrades to ship systems such as propulsion, science equipment, HVAC, piping, and structural repairs. The solicitation will utilize FAR Part 12 and 15 with full and open competition. Inquiries are due by June 28, 2021 and proposals are due by August 6, 2021 to the Department of Commerce National Oceanic and Atmospheric Administration contracting and contract specialist points of contact listed. The refit services required and response dates are the key relevant details provided.
View the file
Other files
Show 40 more
Latest 50 of 63 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMPANY SHARED
KONGSBERG PROPRIETARY. This document and its accompanying elements contain
KONGSBERG information which is proprietary and confidential. Any disclosure, copying, distribution or use is prohibited if not otherwise explicitly agreed with KONGSBERG in writing. Any authorized reproduction, in whole or in part, must include this legend. ©2019 KONGSBERG - All rights reserved.
Sea Acceptance Test
SBP 27 and SBP 29
Sub-Bottom Profiler
Doc No: 429348
Revision: B
Status: This document is under configuration control at Kongsberg Maritime.
Kongsberg Maritime AS COMPANY SHARED
KONGSBERG PROPRIETARY – see Statement of Proprietary Information
429348 / B / 2019-05-10 / Page 2 of 12
Document history
Revision Description of Change
A First Issue for SBP 27 only
B Revision. Now applicable for both SBP 27 and SBP 29
References
No Doc No Description
1 429347 Harbour Acceptance Test SBP 27 and SBP 29
2 429346 Factory Acceptance Test SBP 27 and SBP 29
Disclaimer
Kongsberg Maritime AS endeavours to ensure that all information in this document is correct and fairly stated but does not accept liability for any errors or omissions.
429348 / B / 2019-05-10 / Page 3 of 12
Table of contents
1 Introduction
2 References
3 Test equipment
4 List of items
5 Configuration
5.1 Changed hardware modules
5.2 Changed software modules
6 Interconnection/arrangements
7 Test procedure
8 Check list
9 Testimonial
429348 / B / 2019-05-10 / Page 4 of 12
Definitions / Abbreviations
FAT Factory Acceptance Test
HAT Harbour Acceptance Test
SAT Sea Acceptance Test
SW Software
HW Hardware
TX Transmitter
RX Receiver
RXU RX unit for deep EM 124/304
GW Gateway between RXU and RX beamformer
DW EM Dep water EM systems; i.e. EM 124 or EM 304
HWS Hydrographic Work Station
SBP Sub-bottom profiler
TRU Transceiver unit
OPU Operator unit
RXBF RX beamformer
BIST Built-in system test
SRV A NMEA-like datagram including information about bottom
Slopes, Range to the seafloor, and Velocity of sound
N/A Not Applicable/Available
429348 / B / 2019-05-10 / Page 5 of 12
1 Introduction The purpose of this procedure is to verify that the system installed is fully functional at sea, and to serve as a record of the successful completion of the Sea Acceptance Test.
2 References The Factory Acceptance Test and the Harbour Acceptance Test.
3 Test equipment No test equipment is required for the Sea Acceptance Test.
429348 / B / 2019-05-10 / Page 6 of 12
4 List of items
List of items to be tested. Which units are included will be system delivery dependent.
Item Registration
Number
Equipment Serial number
1 Operator station / HWS
2 SBP 27: SBP 29:
□ 426922 □ 446099 Transceiver Unit 64 ch
□ 426924 □ 446101 Transceiver Unit 32 ch
□ 426926 □ 446103 Transceiver Unit 16 ch
For SBP 29 only
3 446953 Fiber Cable Kit SBP29
For SBP 27 only
3 428150 TX/RX Junction Box SBP, 64 ch
428153 TX/RX Junction Box SBP, 32 ch
428156 TX/RX Junction Box SBP, 16 ch
4 EM 122: 380-213296 Connection cables
Preamp. to TX/RX Junction Box
NA
EM 302: 331813 NA
5 380-215352
Connection cables
TRU to TX/RX Junction Box
NA
6 428033
Control signal cable
TRU to TX/RX Junction Box
NA
429348 / B / 2019-05-10 / Page 7 of 12
5 Configuration If any software or hardware modules have been replaced after the HAT, they shall be listed here.
5.1 Changed hardware modules
Item Item name Part number Rev. Serial number
5.2 Changed software modules
Item Item name Version: Date
429348 / B / 2019-05-10 / Page 8 of 12
6 Interconnection/arrangements The system shall be fully installed and tested.
If SBP 27, the EM 122/302 preamplifier must be switched on. Sensors providing the required inputs shall be available. This includes attitude (to the transceiver unit), navigation (to the operator unit), and the EM must be running and configured to send the SRV datagram to the SBP operator unit.
The system shall have been installed according to the Installation Manual. In the following table, fill in the installation parameters as entered on the Operator station. All coordinates are relative to the ships reference point. The X/Y/Z-axes are pointing forward/starboard/downward.
EM receiver type No of Tx channels1 No of Rx channels2
X [m] Y [m] Z [m] Roll [º] Pitch [º] Heading
[º] Water level
NA NA NA NA NA
Tx array
Rx array
GPS NA NA NA NA
MRU3 NA
7 Test procedure Switch on power to the system and perform all tests as described in the Check List and fill in the results for each individual test.
1 For a 3/6/12 degree transmitter the number of Tx channels is 64/32/16, respectively.
2 For a 1/2/4-degree EM 122/124 receiver the MAXIMUM number of SBP Rx channels is 64/32/16, respectively. The actual number of SBP Rx channels available is limited by the number of SIHD8 boards installed in the TRU. For a 1/2/4-degree EM 302/304 receiver the MAXIMUM number of RX channels is
32/16/8, respectively. The actual number of SBP Rx channels available is limited by the number of
SIHD8 boards installed in the TRU. See the SBP installation manual for details.
3 Note that there is no calibration procedure for roll and pitch for the SBP. The values found after the EM
SAT may be entered for roll offset and pitch offset.
429348 / B / 2019-05-10 / Page 9 of 12
8 Check list
Check list
Pos Test operation Result Specification
PreSAT SAT /Instructions
1 Power on the operator station. Start the operator software.
Power on the transceiver unit
Version number/date of OPU sw
Version number of Online Monitor
Make sure that both the
Online Monitor and the
Beamformer is running.
See the “About” box.
2 Run internal
Built in system tests
(BIST tests)
Result of a BIST is displayed as text on the
OPU
a. Software version / date
Ver.: Date:
CPU
VxWorks
Filter version
RXBF
GW N/A
HVPU-1 N/A
HVPU-2 N/A
HVPU-3 N/A
HVPU-4 N/A
SISP10
SIHD8-1 N/A
SIHD8-2 N/A
SIHD8-3 N/A
SIHD8-4 N/A
SIHD8-5 N/A
SIHD8-6 N/A
SIHD8-7 N/A
SIHD8-8 N/A
429348 / B / 2019-05-10 / Page 10 of 12
Check list
Pos Test operation Result Specification
PreSAT SAT /Instructions
b. CPU Card Test Verify response “OK”
c. SIHD8 Card Test All boards must report voltage and temperature and respond “OK”
d. HV Power Verify response “OK”
e. Average noise level All values should be above
35 [dB re 1 uPA@1m]
f. MRU Check that attitude is updated.
3 Start operation of the EM providing
SRV and the SBP
Both systems operational
4 Verify attitude data being presented after each ping
5 Verify navigation data being presented while pinging
Look in the status area
6 Check that the SRV datagram is successfully received
Look in the lower part of the menu for runtime parameters.
7 Verify bottom slopes along/across being presented (see run-time parameters) and compensated for in transmit/ receive tilt
Automatic bottom slope correction must be enabled.
Look in status area
8 Verify penetration on a flat area Penetration and image is dependent on bottom type.
The water depths should be greater than 250 m.
9 Verify reduced penetration in this area when the transmit beam is manually tilted.
Set automatic slope correction to off and enter slope angles manually to tilt the beams. Use e.g. 15°
429348 / B / 2019-05-10 / Page 11 of 12
Performed by (date/sign) Witnessed by (date/sign)
PreSAT:
PreSAT:
SAT:
SAT:
429348 / B / 2019-05-10 / Page 12 of 12
9 Testimonial The SEA ACCEPTANCE TEST for the SBP …, for …………………………., has been performed according to the test procedure.
The test is: Accepted / Not accepted (Delete as appropriate)
Remarks:
Please use capital letters:
Test performed by
Position Company
Kongsberg Maritime
Test accepted by Position
Company
Date
Signature