429347_HAT PROCEDURE SBP 27 and SBP 29.pdf
PDF 344 KB Posted
- Attached to
- NOAA Ship Ronald H. Brown: Mid-Life Refit Federal contract opportunity
- Solicitation number
- 1305M221RNMAN01155
About this file
This document outlines a solicitation for a mid-life refit of the NOAA Ship Ronald H. Brown. The National Oceanic and Atmospheric Administration seeks a firm fixed price contract to upgrade many of the ship's systems, including repowering, bow thrusters, Z-drive, potable water, chilled water, sewage, science refrigeration, uncontaminated seawater, air handling units, heating/ventilation/air conditioning, tank level indicators, navigational equipment, radar renewals, overhead and security perimeter lighting, and exterior ballast and fuel tank vent renewals. Much of the ship's piping and identified steel will also be replaced. Interested parties must submit all inquiries by June 28, 2021 and proposals by August 6, 2021 to the identified contracting and contract specialist emails. The refit modification is to be competed using Federal Acquisition Regulation Parts 12 and 15.
View the file
Other files for this federal contract opportunity
Show all 50
NOAA Ship Ronald H. Brown: Mid-Life Refit has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMPANY SHARED
KONGSBERG PROPRIETARY. This document and its accompanying elements contain
KONGSBERG information which is proprietary and confidential. Any disclosure, copying, distribution or use is prohibited if not otherwise explicitly agreed with KONGSBERG in writing. Any authorized reproduction, in whole or in part, must include this legend. ©2019 KONGSBERG - All rights reserved.
Harbour Acceptance Test
SBP 27 and SBP 29
Sub-Bottom Profiler
Doc No: 429347
Revision: D
Status: This document is under configuration control at Kongsberg Maritime.
Kongsberg Maritime AS COMPANY SHARED
KONGSBERG PROPRIETARY – see Statement of Proprietary Information
429347 / D / 2019-05-10 / Page 2 of 12
Document history
Revision Description of Change
A First version for SBP 27
B Adding table for installation parameters. Minor corrections.
C Minor changes
D Updated to apply to both SBP 27 and SBP 29
References
No Doc No Description
1 429346 Factory Acceptance Test, SBP 27 and SBP 29
Disclaimer
Kongsberg Maritime AS endeavours to ensure that all information in this document is correct and fairly stated, but does not accept liability for any errors or omissions.
429347 / D / 2019-05-10 / Page 3 of 12
Table of contents
1 Introduction
2 References
3 List of items
4 Configuration
5 Changed SW- or HW-modules
6 Interconnection/arrangement
7 Test procedure
8 Check list
9 Testimonial
429347 / D / 2019-05-10 / Page 4 of 12
Definitions / Abbreviations
FAT Factory Acceptance Test
HAT Harbour Acceptance Test
SAT Sea Acceptance Test
SW Software
HW Hardware
TX Transmitter
RX Receiver
RXU RX unit for deep EM 124/304
GW Gateway between RXU and RX beamformer
DW EM Dep water EM systems; i.e. EM 124 or EM 304
HWS Hydrographic Work Station
SBP Sub-bottom profiler
TRU Transceiver unit
OPU Operator unit
RXBF RX beamformer
BIST Built-in system test
SRV A NMEA-like datagram including information about bottom
Slopes, Range to the seafloor, and Velocity of sound
N/A Not Applicable/Available
429347 / D / 2019-05-10 / Page 5 of 12
1 Introduction The purpose of this procedure is to verify that the system installed is fully functional, and to serve as a record of the successful completion of the Harbour Acceptance Test (HAT).
The test shall verify that the system is ready for sea trials.
2 References
The Factory Acceptance Test (FAT) record.
3 List of items
List of items to be tested. Which units are included will be system delivery dependent.
Item Registration
Number
Equipment Serial number
1 Operator station / HWS
2 SBP 27: SBP 29:
□ 426922 □ 446099 Transceiver Unit 64 ch
□ 426924 □ 446101 Transceiver Unit 32 ch
□ 426926 □ 446103 Transceiver Unit 16 ch
For SBP 29 only
3 446953 Fiber Cable Kit SBP29
For SBP 27 only
3 428150 TX/RX Junction Box SBP, 64 ch
428153 TX/RX Junction Box SBP, 32 ch
428156 TX/RX Junction Box SBP, 16 ch
4 EM 122: 380-213296 Connection cables
Preamp. to TX/RX Junction Box
NA
EM 302: 331813 NA
5 380-215352
Connection cables
TRU to TX/RX Junction Box
NA
6 428033
Control signal cable
TRU to TX/RX Junction Box
NA
429347 / D / 2019-05-10 / Page 6 of 12
4 Configuration
For module serial numbers, please refer to the FAT record.
5 Changed SW- or HW-modules
The software modules and circuit boards included in the system and their serial numbers were noted in the FAT record. If any of these items have been replaced after the FAT, they shall be listed here
Item
Item name
For HW-modules Serial number (HW) or
Version / date (SW) Part number Rev.
429347 / D / 2019-05-10 / Page 7 of 12
6 Interconnection/arrangement
The system shall be fully installed and tested before the HAT. No simulators or test arrangements shall be used.
• For SBP 27, the EM 122/302 preamplifier must be switched on
• For SBP 29 the EM 124/304 must be running
• Sensors providing the required inputs shall be available. This includes o attitude to the SBP transceiver unit, o navigation to the SBP operator unit, and o slope, range, and velocity information (the SRV datagram) from the EM operator unit1 to the SBP operator unit2
• Trig out from the EM must be connected to the SBP transceiver unit
• If K-Sync is part of the delivery, the wiring between K-Sync and the SBP transceiver unit must be completed, and K-Sync must be configured for synchronizing the SBP
1 If a shallow water EM echo sounder, e.g. EM 2040 or EM 712, is available on the ship, we recommend configuring this echo sounder to transmit SRV datagrams to the SBP. In shallow water this EM will provide more accurate information than the EM 122/124 or the EM 302/304.
2 Note that the model number of an EM providing SRV datagrams must be listed in the SRV shallow/deep water priority strings found under the NMEA readers. The string might look like this in the shallow water case: “EM2040>EM712>EM122” meaning SRV from the EM 2040 has priority over SRV from the EM 712, which in turn have priority over the SRV from an EM 122 in shallow water.
429347 / D / 2019-05-10 / Page 8 of 12
The system shall have been installed according to the Installation Manual. In the following table, fill in the installation parameters as entered on the Operator station. All coordinates are relative to the ships reference point. The X/Y/Z-axes are pointing forward/starboard/downward.
EM receiver type No of Tx channels3 No of Rx channels4
X [m] Y [m] Z [m] Roll [º] Pitch [º] Heading [º]
Water level NA NA NA NA NA
Tx array
Rx array
GPS NA NA NA NA
MRU5 NA
7 Test procedure
Switch on power to the Operator Station and to the Processing Unit. Perform all tests as described in the check list and fill in the results for each individual test.
3 For a 3/6/12 degree transmitter the number of Tx channels is 64/32/16, respectively.
4 For a 1/2/4 degree EM 122/124 receiver the MAXIMUM number of SBP Rx channels is 64/32/16, respectively. The actual number of SBP Rx channels available is limited by the number of SIHD8 boards installed in the TRU. See the SBP installation manual for details.
For a 1/2/4 degree EM 302/304 receiver the MAXIMUM number of RX channels is 32/16/8, respectively.
The actual number of SBP Rx channels available is limited by the number of SIHD8 boards installed in the TRU. See the SBP installation manual for details.
5 Note that there is no calibration procedure for roll and pitch for the SBP. The values found after the EM
SAT may be entered for roll offset and pitch offset.
429347 / D / 2019-05-10 / Page 9 of 12
8 Check list
Check list
Pos Test operation Result Specification
PreHAT HAT /Instructions
1 Start the operator software.
Version number/date of OPU sw
Version number of Online Monitor
Make sure that both the
Online Monitor and the
Beamformer is running.
See the “About” box.
2 Run internal
Built in system tests
(BIST tests)
Result of a BIST is displayed as text on the
OPU
a. Software version / date
Ver.: Date:
CPU
VxWorks
Filter version
RXBF
GW
HVPU-1 N/A
HVPU-2 N/A
HVPU-3 N/A
HVPU-4 N/A
SISP10
SIHD8-1 N/A
SIHD8-2 N/A
SIHD8-3 N/A
SIHD8-4 N/A
SIHD8-5 N/A
SIHD8-6 N/A
SIHD8-7 N/A
SIHD8-8 N/A
429347 / D / 2019-05-10 / Page 10 of 12
Check list
Pos Test operation Result Specification
PreHAT HAT /Instructions
b. CPU Card Test Verify response “OK”
c. SIHD8 Card Test Verify response
“All units OK”
d. HV Power Verify response “OK”
e. Average noise level All values should be above
35 [dB re 1 uPA@1m]
f. MRU Check that attitude is updated.
3 Test of sensor input to the Operator
Unit.
Verify that the NMEA readers receive and display the all required sensor information, e.g.
navigation input.
4 Start pinging in normal mode with synchronization Fixed rate
Verify that the
SBP is pinging
Start raw data logging for testing of playback.
5 Verify that roll, heave, and pitch values are displayed on the OPU when the SBP is pinging
Check for updated values in the beam reader and/or the status area
6 Check that SRV datagram are successfully received
An EM providing SRV datagrams must be pinging.
Check in the lower part of the Runtime parameters menu for received BIR/NIR et cetera.
7 Stop pinging, set synchronization to
EM trigger, start pinging
Verify that the
SBP is pinging when the
EM is pinging
8 Data playback Stop raw data logger, and verify data playback
6 When NMEA readers is highlighted (Select System/Readers and writers/NMEA readers) the sensor information received and interpreted by all NMEA readers is displayed in the lower part of the Property area.
429347 / D / 2019-05-10 / Page 11 of 12
Check list
Pos Test operation Result Specification
PreHAT HAT /Instructions
If applicable, synchronization by K-Sync (or similar) shall be verified
9 Stop pinging, set synchronization to
External trigger, start pinging
Verify that the SBP is pinging when K-Sync gives trig out to the SBP
10 Ready to transmit (RTT) Check that K-Sync receives
RTT
11 Trigger output Check that K-Sync receives trigger output from the
SBP
Performed by (date/sign) Witnessed by (date/sign)
PreHAT:
PreHAT:
HAT:
HAT:
429347 / D / 2019-05-10 / Page 12 of 12
9 Testimonial
The HARBOUR ACCEPTANCE TEST for the SBP …, for …………………………., has been performed according to the test procedure.
The test is: Accepted / Not accepted (Delete as appropriate)
Remarks:
Please use capital letters:
Test performed by Position Company
Kongsberg Maritime
Test accepted by Position Company
Date
Signature