013200 Construction Documentation.pdf

PDF 64 KB Posted

Attached to
Z1DA--528A5-20-502 BOILER REPLACEMENT PROJECT Federal contract opportunity
Solicitation number
36C24224R0032
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2

About this file

This document is a section on Construction Documentation requirements for a federal contract opportunity. The key details are:

The contractor is required to use the VISN 2 VA Autodesk Build Construction management platform, also called Autodesk Construction Cloud (ACC), for all project-related submissions and collaboration at no cost to the contractor. Contractor staff must request access to the ACC platform and complete required training through the ProductivityNOW eLearning site within 12 calendar days of contract award. All official project correspondence and documentation, such as RFIs, submittals, schedules, and reports, must be submitted through the ACC platform. Additional staff can be added at any time with a request to the Contracting Officer Representative (COR). Failure to utilize the ACC platform as the official communication and collaboration system will not result in additional time or cost to the contract.

The related federal contract opportunity is for a Boiler Replacement Project (Solicitation # 36C24224R0032) with the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2. This is a 100% Service-Disabled Veteran Owned Small Business (SDVOSB) set-aside with a proposal due date of June 28, 2024. The evaluation factors include details on three previous similar contracts within the past ten years.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--528A5-20-502 BOILER REPLACEMENT PROJECT, newest first.
File Type Posted
36C24224R0032 0009.docx DOCX document
Canandaigua VAMC Boiler Plant - Final RBM Survey.pdf PDF
852.219-75 VA Notice of Limitations on Subcontracting.docx DOCX document
36C24224R0032 0008.docx DOCX document
36C24224R0032 0007.docx DOCX document
Attachment B.pdf PDF
Attachment A_VHA Boiler and Associated Plant Safety Device Testing Manual 8th Edition.pdf PDF
36C24224R0032 0006.docx DOCX document
36C24224R0032 0005.docx DOCX document
touchpoint-plus-user-guide-man0996_v1_0216.pdf PDF
Touchpoint Plus_Quick Start guide.pdf PDF
2024-06-13 Question 1 Attachments.pdf PDF
36C24224R0032 0004.docx DOCX document
Sensepoint XCD_IOM.pdf PDF
Copy of Pre-Bid RFI Questions_Encorus Response 2024-06-13.pdf PDF
Site Visit Sign In Sheet.pdf PDF
36C24224R0032 0003.docx DOCX document
528A5-20-502_SOW R1_Boiler Plant Replacement.pdf PDF
528A5-20-502 Boiler Replacement_Plans_Part 2.pdf PDF
36C24224R0032 0002.docx DOCX document
528A5-20-502 Boiler Replacement_Plans_Part 3.pdf PDF
528A5-20-502 Boiler Replacement_Plans_Part 1.pdf PDF
528A5-20-502 Boiler Replacement_Specifications REV1.pdf PDF
S02 - Past Performance Questionnaire - Exhibit B.docx DOCX document
36C24224R0032 0001.docx DOCX document
20-502 Bid Specifications.pdf PDF
P07 Wage Determination.pdf PDF
528A5-20-502 DESIGN BOLIER REPLACEMENT SET.pdf PDF
S02 - Contractor Projects Form.docx DOCX document
36C24224R0032.docx DOCX document
S02 - Past Performance Questionnaire.docx DOCX document
852.219-78 VA Notice of Limitations on Subcontracting.docx DOCX document
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

09-01-23

01 32 00 - 1

SECTION 01 32 00

CONSTRUCTION DOCUMENTATION

PART 1- GENERAL

1.1 DESCRIPTION:

A. Construction contractors and A/E design firms, selected by award to perform work at VISN 2 VA facilities, are required to utilize VISN 2

Autodesk Build Construction management platform, also called Autodesk

Construction Cloud (ACC). Access to the platform and training portal will be provided by VISN 2 through project Contracting Officer

Representative (COR) at no cost for the duration of the project.

Autodesk Build is the management and collaborative environment that

VISN 2 uses for all its Non-Recurring Maintenance (NRM), Minor Program projects, Feasibility Studies, Commissioning and Retro-Commissioning contracts. There is no user, license, or subscription fee to the contractor for using this cloud-based platform.

1.2 REQUIREMENTS:

A. Contractor shall accomplish and complete the following tasks upon award of contract:

1. Request access to ACC platform and ProductivityNOW eLearning Site to project VA COR NLT 14 days from contract award.

2. Only staff that shall utilize the platform to be granted access.

Examples: Project manager, sub-contractors POC, Site manager, Safety officer, etc.

3. The access request shall be in writing and include a list of staff.

The list shall include the following information:

• Full Name

• Company Name

• Email Address

• Role/Position on the project (i.e., Project manager, site super)

4. Upon granting access, staff shall complete required ACC training through ProductivityNOW platform within 12 Calendar days.

5. Upon successful completion of training, contractor shall submit certificates of completion to COR NLT 2 Business days.

B. Access to ProductivityNOW eLearning will expire after 12 Calendar days after online access is granted. Contractor shall complete ACC training within that period.

09-01-23

01 32 00 - 2

C. Additional Staff and Subcontractors can be added at any time with a request submission to the project COR as described above.

D. The contractor shall only use the ACC platform for all contract required submissions, official project correspondence to be acknowledged, reviewed, and actioned by the responsible party. No additional time shall be added to the contract, nor an increase in contract amount be provided for the contractor’s failure to utilize the

ACC platform as the project’s official communication and collaboration system. Any correspondence out of platform shall not be the governing authority contradicting direction and will be at the contractor’s expense. Official project correspondence and collaboration includes but not limited to: RFIs, submittals, schedules, shutdown requests, actionable tasks, reports, testing, safety inspections, photos, and site surveys.

E. Contractor must inform the COR of any staff changes NLT 2 business days from the change. Staff changes pertains to staff who was granted access to the ACC platform. Contractor shall request termination of access, replacement of personnel and/or any other action that might impact the contractor ability to maintain required utilization of the platform.

F. Contractor submission requirements cannot be accepted for work to begin without meeting all ACC Platform requirements outlined herein, including completing required ACC platform training.

- - - E N D - - -