This document is a technical memorandum from Arcadis U.S., Inc. detailing October 2016 slope inclinometer readings for the Upper Brownsville Levee Reach Lower Rio Grande Flood Control Project. The report presents data from four new inclinometers (Arc-1, Arc-2, Arc-3, and Arc-4) installed in June 2016, with baseline and subsequent readings taken through October 2016. Additionally, three existing inclinometers (I-32, I-33, and I-34) were noted to have measurement challenges, with the probe unable to pass through certain pipe depths.

The inclinometer readings were collected using a Digitilt AT system, which includes an inclinometer probe, control cable, Bluetooth reel, and an Android-based tablet computer. The measurements track potential ground displacement in two axes: A-axis (perpendicular to the levee) and B-axis (parallel to the levee). Despite multiple measurement periods, the report indicates that none of the inclinometers showed significant movement, with all incremental and cumulative displacement plots remaining consistent with the baseline readings. The measurements were planned to continue monthly until June 2017, with the goal of monitoring potential levee and ground stability.

View the file

Other files

File Type Posted
SF-30 Amendment 005_.pdf PDF
191BWC25R0010_Brownsville Specs_ 20250702_.pdf PDF
Technical Specifications Brownsville 20250630.pdf PDF
SF-30 Amendment 004.pdf PDF
Section L Source Selection Criteria _4.pdf PDF
SF-30 Amendment 003.pdf PDF
191BWC25R0010_Brownsville_Drawings_20250617.pdf PDF
Section L Source Selection Criteria _6_21_25.pdf PDF
191BWC25R0010 Brownsville Rev Dwgs 20250605.pdf PDF
191BWC25R0010 Brownsville Specs 20250605.pdf PDF
SF-30 Amendment 002.pdf PDF
SF-30 Amendment 001.pdf PDF
USIBWC Amendment 4 -D5_27_25.pdf PDF
USIBWC Amendment 3- D5-24-25.pdf PDF
USIBWC Amendment 2- D5-19-23.pdf PDF
Section L Source Selection Criteria _3.pdf PDF
Section L Source Selection Criteria (2).pdf PDF
R Upper Brownsville Levee and Floodplain Failure DDR Redacted_REDUCED.pdf PDF
REDUCED Geotech Donna Pump to Brownsville Raba Kistner.pdf PDF
Report of Subsurface Exploration Truck Lane Improvements Gateway Inl Bridge.pdf PDF
Report of Subsurface Exploration Intl Bridge PSI.pdf PDF
191BWC24R0010 Brownsville Drawings 20240419 FS.pdf PDF
Section L Source Selection Criteria.pdf PDF
Upper Brownsville Levee E-191BWC25R0010_.pdf PDF
00_31_19-1_4_B_IBM13C0001 Record Drawings Excerpts- REDUCED.pdf PDF
00_31_19-1_4_B_IBM13C0001 Record Drawings Excerpts.pdf PDF
00_31_32-1_3_C_3_20070928 Geotech Donna Pump to Brownsville SandB.pdf PDF
00_31_43-1_5_A_20230906 USACE 404 SWG-2023-00309 NWP.pdf PDF
WD_TX_20250003-01-03-2025.pdf PDF
00_31_32-1_3_B_20150713 ERDC Report of Investigation.pdf PDF
00_31_32-1_3_A_1_j_20170621 Inclinometer Readings.pdf PDF
00_31_32-1_3_A_1_e_20170105 Inclinometer Readings.pdf PDF
00_31_32-1_3_A_1_a_20160829 Inclinometer Readings.pdf PDF
00_31_32-1_3_A_1_b_20160926 Inclinometer Readings.pdf PDF
Upper Brownsville Levee and Floodplain F-191BWC25R0010_.pdf PDF
Attachment_Docs_List.pdf PDF
191BWC15R0010 Past Performance Questionnaire.pdf PDF
00_31_32-1_3_A_1_m_20200716 Inclinometer Readings.pdf PDF
00_31_32-1_3_A_1_l_20200403 Inclinometer Readings.pdf PDF
00_31_32-1_3_A_1_i_20170519 Inclinometer Readings.pdf PDF
00_31_32-1_3_A_1_d_20161118 Inclinometer Readings.pdf PDF
00_31_32-1_3_A_1_k_20170718 Inclinometer Readings.pdf PDF
00_31_32-1_3_A_1_h_20170412 Inclinometer Readings.pdf PDF
00_31_32-1_3_A_1_g_20170320 Inclinometer Readings.pdf PDF
00_31_32-1_3_C_4_20070928 Geotech Donna Pump to Brownsville Boreholes SandB.pdf PDF
191BWC25R0010 Brownsville Specs 20250115.pdf PDF
IBWC_Form_245C_Performance_of_Work_Contractor.pdf PDF
Client_Authorization_Letter.docx DOCX document
00_31_32-1_3_A_1_f_20170215 Inclinometer Readings.pdf PDF
00_31_19-1_4_A_2_201205 Upper Brownsville Levee Design Report TT REDACTED.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Arcadis U.S., Inc.

10352 Plaza Americana Drive

Baton Rouge

Louisiana 70816

Tel 225 292 1004

Fax 225 218 9677

Page:

1/3

MEMO

To:

Padinare Unnikrishna Contracting Officer Representative

IBWC

Copies:

Armando Flores (Arcadis)

From:

Kirk Lowery, P.E.

Date: Arcadis Project No.:

October 31, 2016 LA003315.0000

Subject:

October 2016 Summary Report of Inclinometer Readings Remediation Design of Levee Floodplain Failure within the Upper Brownsville Levee Reach Lower Rio Grande Flood Control Project – IBM15D0001 – IBM15T0015

1. Introduction

Arcadis U.S., Inc. (Arcadis), is pleased to submit this summary technical memorandum including data charts of the slope inclinometer readings at the IBWC site. The baseline readings for the new inclinometers, Arc- 1, Arc-2, Arc-3 and Arc-4, were taken in June 2016 and the fourth set of readings were measured on October 27, 2016. These inclinometers will be measured every month until June of 2017.

Readings for the existing inclinometers, I-32, I-33 and I-34, were not made when Arcadis visited the site October 27, 2016. During the June readings, the inclinometer probe had difficulty passing certain depths and when Arcadis passed those depths retrieving the inclinometer probe was problematic. Arcadis plans to periodically read these inclinometers, but not to attempt to pass the probe through the constricted area of the pipe and possibly lose/abandon the probe. Since the readings could not be measured for the existing inclinometers, in October 2016, Arcadis measured the depth range in which the inclinometer probe could not pass through the constricted area of the pipe and are as follows:

I-32 (Top of the Levee): Depth Range: 32 feet

I-33 (Toe of the Levee): Depth Range: 38 feet to 39 feet

I-34 (Below Toe of Levee): Depth Range: 30 feet to 31 feet

2/3

MEMO

The readings for each inclinometer are reflected in the graphical displays provided in Attachment A.

Attachment A includes both incremental and cumulative displacement plots. Attachment B shows the inclinometer locations on a Google Map.

The incremental displacement plot compares the mean deviation data to the baseline survey file. This plot reveals the exact depth where displacements are actually occurring. The cumulative displacement is the sum of the displacements from the base of the borehole. This plot shows the change in the position of the casing from the first set of readings.

The A-axis charts in the displacement plots show displacements in the plane perpendicular to the levee while the B-axis charts show displacements in the plane parallel with the levee. A positive reading in the A-axis chart indicates displacement to the west heading toward the Rio Grande River, and a positive reading in the B-axis chart indicates displacement to the north heading toward the Gateway Bridge.

2. Digitilt AT Inclinometer Digitilt AT system was used to survey the inclinometers. The system components include an inclinometer probe, control cable, a Bluetooth reel and the Digitilt Reader app for certified Android-based tablet computer.

The equipment is shown in Figure 1.

Figure 1: Digitilt AT System Components.

3. First Quarter 2016 Inclinometers Assessment

The depth of the casing restriction for the USACE installed inclinometers, I-32, I-33 and I-34 appears to be the same depth as the previous readings.

Data collected on October 27, 2016 followed the same trend as the baseline reading measured in June 2016. The monthly displacement plots recorded between July through October are presented in Attachment A. Data comparisons for each inclinometer are described below:

3/3

MEMO

Inclinometer Arc-1: The base readings for inclinometer Arc-1 were collected on June 22, 2016. The Arc-1 cumulative and incremental displacement does not show any sign of movement on the plane perpendicular to the levee nor on the plane parallel to the levee.

Inclinometer Arc-2: The base readings for inclinometer Arc-2 were collected on June 17, 2016. The Arc-2 cumulative and incremental displacement does not show any sign of movement on the plane perpendicular to the levee nor on the plane parallel to the levee.

Inclinometer Arc-3: The base readings for inclinometer Arc-3 were collected on June 17, 2016. The Arc-3 cumulative and incremental displacement does not show any sign of movement on the plane perpendicular to the levee nor on the plane parallel to the levee.

Inclinometer Arc-4: The base readings for inclinometer Arc-4 were collected on June 22, 2016. The Arc-4 cumulative and incremental displacement does not show any sign of movement on the plane perpendicular to the levee nor on the plane parallel to the levee.

ATTACHMENTS:

A – Inclinometer Plots B – Inclinometer Location Map

ATTACHMENT A

INCLINOMETER PLOTS

IBWC Arc-1 A - Axis

6/22/2016 11:22:30 AM 7/25/2016 3:17:20 PM

8/25/2016 1:34:40 PM 9/22/2016 1:35:22 PM

10/27/2016 2:18:50 PM

D ep th in

F ee t

Incremental Displacement (in) -3 -1.5 0 1.5 3

IBWC Arc-1 B - Axis

6/22/2016 11:22:30 AM 7/25/2016 3:17:20 PM

8/25/2016 1:34:40 PM 9/22/2016 1:35:22 PM

10/27/2016 2:18:50 PM

D ep th in

F ee t

Incremental Displacement (in) -3 -1.5 0 1.5 3

IBWC Arc-1 A - Axis

6/22/2016 11:22:30 AM 7/25/2016 3:17:20 PM

8/25/2016 1:34:40 PM 9/22/2016 1:35:22 PM

10/27/2016 2:18:50 PM

D ep th in

F ee t

Cumulative Displacement (in) -4 -3 -2 -1 0 1 2 3 4

IBWC Arc-1 B - Axis

6/22/2016 11:22:30 AM 7/25/2016 3:17:20 PM

8/25/2016 1:34:40 PM 9/22/2016 1:35:22 PM

10/27/2016 2:18:50 PM

D ep th in

F ee t

Cumulative Displacement (in) -4 -3 -2 -1 0 1 2 3 4

IBWC Arc-2 A - Axis

6/17/2016 6:27:13 PM 7/25/2016 3:57:11 PM

8/25/2016 2:02:22 PM 9/22/2016 2:05:40 PM

10/27/2016 2:44:45 PM

D ep th in

F ee t

Incremental Displacement (in) -3 -1.5 0 1.5 3

IBWC Arc-2 B - Axis

6/17/2016 6:27:13 PM 7/25/2016 3:57:11 PM

8/25/2016 2:02:22 PM 9/22/2016 2:05:40 PM

10/27/2016 2:44:45 PM

D ep th in

F ee t

IBWC Arc-2 A - Axis

6/17/2016 6:27:13 PM 7/25/2016 3:57:11 PM

8/25/2016 2:02:22 PM 9/22/2016 2:05:40 PM

10/27/2016 2:44:45 PM

D ep th in

F ee t

Cumulative Displacement (in) -4 -3 -2 -1 0 1 2 3 4

IBWC Arc-2 B - Axis

6/17/2016 6:27:13 PM 7/25/2016 3:57:11 PM

8/25/2016 2:02:22 PM 9/22/2016 2:05:40 PM

10/27/2016 2:44:45 PM

D ep th in

F ee t

IBWC Arc-3 A - Axis

6/17/2016 7:05:22 PM 7/25/2016 4:28:56 PM

8/25/2016 2:41:46 PM 9/22/2016 2:36:13 PM

10/27/2016 3:17:17 PM

D ep th in

F ee t

Incremental Displacement (in) -3 -1.5 0 1.5 3

IBWC Arc-3 B - Axis

6/17/2016 7:05:22 PM 7/25/2016 4:28:56 PM

8/25/2016 2:41:46 PM 9/22/2016 2:36:13 PM

10/27/2016 3:17:17 PM

D ep th in

F ee t

IBWC Arc-3 A - Axis

6/17/2016 7:05:22 PM 7/25/2016 4:28:56 PM

8/25/2016 2:41:46 PM 9/22/2016 2:36:13 PM

10/27/2016 3:17:17 PM

D ep th in

F ee t

Cumulative Displacement (in) -4 -3 -2 -1 0 1 2 3 4

IBWC Arc-3 B - Axis

6/17/2016 7:05:22 PM 7/25/2016 4:28:56 PM

8/25/2016 2:41:46 PM 9/22/2016 2:36:13 PM

10/27/2016 3:17:17 PM

D ep th in

F ee t

IBWC Arc-4 A - Axis

6/22/2016 10:48:04 AM 7/25/2016 5:08:42 PM

8/25/2016 3:15:23 PM 9/22/2016 3:09:20 PM

10/27/2016 3:58:37 PM

D ep th in

F ee t

Incremental Displacement (in) -3 -1.5 0 1.5 3

IBWC Arc-4 B - Axis

6/22/2016 10:48:04 AM 7/25/2016 5:08:42 PM

8/25/2016 3:15:23 PM 9/22/2016 3:09:20 PM

10/27/2016 3:58:37 PM

D ep th in

F ee t

IBWC Arc-4 A - Axis

6/22/2016 10:48:04 AM 7/25/2016 5:08:42 PM

8/25/2016 3:15:23 PM 9/22/2016 3:09:20 PM

10/27/2016 3:58:37 PM

D ep th in

F ee t

Cumulative Displacement (in) -4 -3 -2 -1 0 1 2 3 4

IBWC Arc-4 B - Axis

6/22/2016 10:48:04 AM 7/25/2016 5:08:42 PM

8/25/2016 3:15:23 PM 9/22/2016 3:09:20 PM

10/27/2016 3:58:37 PM

D ep th in

F ee t

ATTACHMENT B

INCLINOMETER LOCATION MAP

TM_Inclinometer Readings_IBWC Project_October 2016.pdf
Attachment A_10-31-16.pdf
Arc-1_Inc
Arc-1_Cum
Arc-2_Inc
Arc-2_Cum
Arc-3_Inc
Arc-3_Cum
Arc-4_Inc
Arc-4_Cum

File details come from the government source that posted it. Updated .