Small Munitions Trailers
Closed Solicitation Posted
- Solicitation number
- FA8532-18-R-0003
- Agency
- Air Force Materiel Command Air Force, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 333924 Industrial Truck, Tractor, Trailer, and Stacker Machinery Manufacturing
- PSC
- Not on record
Notice details come from SAM.gov. Updated .
About this opportunity
The Air Force Materiel Command seeks to award an indefinite delivery indefinite quantity contract to design, test, and produce two classifications of small munitions trailers over seven years. The contractor shall provide the MHU-110V2 and MHU-141V2 trailers in accordance with technical requirements, with first article units required for each. Proposals will be evaluated using tradeoff best value source selection considering technical acceptability, past performance, and price/cost factors. The response deadline is April 22, 2019, with anticipated award from August to September 2019.
The solicitation is designated as a 100% small business set-aside under NAICS 333924 and PSC codes 5340 and 5305. Up to 300 trailers of each classification may be ordered annually during option periods, for a potential total value over the seven-year contract life exceeding $300 million. Delivery locations include Air Force installations worldwide. The technical data is export controlled, and foreign companies are ineligible to participate in the full and open competition.
Notice text
28 versions
Update #28 · Latest ·
Posted Industry Questions and Responses.
Update #27 ·
Uploaded Industry Questions and Answers 16 Apr 2019
Update #26 ·
UPLOADED SOLICITATION AMENDMENT 0004
Update #25 ·
Posting Industry Questions and Answers 10 Apr 2019
Update #24 ·
Posted Industry Questions and Answers as well as Additional drawings.
Update #23 ·
Additional Drawing #200415593-01 has been uploaded and is available on FedBizOpps via the export controlled file is titled: Drawing_200415593_98752
Update #22 ·
01 April 2019 (UPDATED) Industry Questions and Answers
Added part number to question #1 and added question #2.
Update #21 ·
01 April 2019 Industry Questions and Answers
Update #20 ·
Uploaded Solicitation Amendment 0003. Response date has been extended to 22 Apr 2019.
Update #19 ·
26 MAR 2019 Industry Questions and Answers
Update #18 ·
UPLOADED 20 March 2019
FA8532-18-R-0003 Questions and Responses
Update #17 ·
Industry Questions and Answers have been uploaded. The document is: 18 MAR 2019 Industry Questions and Answers
Solicitation FA8532-18-R-0003 Amendment 0002 has been issued and uploaded.
The attachment to Solicitation Amendment 0002 is PD15WRWNZEA05 Amendment 5 which has been uploaded as an export controlled document.
PD15WRWNZEA05 Amendment 5 references drawings which have been uploaded as export controlled documents also.
Update #16 ·
Posted (Uploaded) Questions and Answers - 14 MAR 2019
Update #15 ·
Posted (Uploaded) Questions and Answers Part 2
Update #14 ·
Posted (Uploaded) Solicitation Amendment 0001
Posted (Uploaded) PD15WRWNZEA05 Amendment 4
Posted (Uploaded) Questions and Answers
Update #13 ·
Offical Solicitation and all attachments are hereby released. Offers will be received at the issuing office until: 3 Apr 2019 at 5:00 pm EST.
Update #12 ·
The Government is posting Questions and Answers from Industry. The questions and answers will be uploaded as an attachment named: 26 Feb 2019 Industry Questions
Update #11 ·
TDP has been uploaded and is Export Controlled. Vendor must be authorized to access Export Controlled Data.
Update #10 ·
Notice has been updated and two attachments uploaded today with responses to Industry Questions received by the Government.
Update #9 ·
SMALL MUNITIONS TRAILERS RESPONSE TO INDUSTRY
As of 07 Jan 2019 - Additional Questions
•1. Question: In reading the PD of this solicitation, I am struck by the numerous pages of system level design requirements laid out. The paragraph 1.1 spells out very clearly the scope required: "The scope of this Purchase Description (PD) is replacement of the obsolete braking system with disc brakes and corresponding updates to sealed wheel bearings, replacement of the obsolete lighting system with light emitting diode (LED) lights, replacement of the obsolete steering system components with sealed, maintenance free tie rod ends, and enhancement of the corrosion prevention coatings on the trailers. Major system design changes are not expected or desired."
Rather than telling us the design requirements of the system, it seems the PD should direct us to build-to-print the trailers except for the defined scope in paragraph 1.1. We are not bidding on design of theses trailers, only modification of a few sub-systems.
Answer: The Government is not procuring additional quantities of legacy MHU-110 and
MHU-141 munitions trailers, rather the Government will be issuing requests for proposals to design and build new small munitions trailers based upon the legacy MHU-110 and MHU-141 designs. Potential vendors are highly encouraged to read the Purchase Description and the Statement of Work in their entirety; neither shall be construed as standalone documentation. In particular, potential vendors are encouraged to carefully review paragraphs 3.1, 3.2, and 3.3 of the subject Purchase Description.
The Government suggests potential vendors not assume the legacy MHU-110 and MHU-141 drawing packages meet the design requirements laid forth in the Purchase Description. While the Government does not expect or desire major changes, other than those mandated within the Purchase Description, changes to the legacy design may be required to meet the performance and test criteria set forth in the Purchase Description.
The Government will use numerous analyses, reports, and reviews (as denoted in the Statement of Work) during the design and build process to ascertain whether or not the vendors new design meets the entirety of the Purchase Description. The required analyses, reports, and reviews are included in the project scope, in part, to reduce the risk of test failure due to faulty assumptions. As such, performance criteria for the new trailer design have been set forth by the Government in Section 3 of the Purchase Description and resultant test criteria have been set forth in Section 4 of the Purchase Description. The vendor selected for contract award will be responsible for ensuring the newly designed small munitions trailers meet ALL requirements contained within the Purchase Description, regardless of whether the existing legacy MHU-110 and MHU-141 munitions trailers meet the requirements of the Purchase Description.
•2. Question: Please advise current schedule regarding release of formal FA8532-18-R-0003 Small Munitions Trailer solicitation.
Answer: The solicitation is expected to be released by the end of January 2019.
•3. Question: Please provide access to the TDP.
Answer: The TDP is Export Controlled and will be accessible along with other Export Controlled Documentation via FedBizOpps once the Government releases the official solicitation and it is posted to FedBizOpps. In order for a vendor to access any Export Controlled documents, the vendor must be registered in FBO, CCR, JCP and be approved for export control document access.
Update #8 ·
SMALL MUNITIONS TRAILERS RESPONSE TO INDUSTRY
As of 21 Dec 2018 - Additional Questions
Question
Under section Past Performance, your 'relevancy' criteria requires both the tasks AND features to be met on each given contract submitted. Have you considered modifying the 'relevancy' standard to an "OR" standard rather than an "AND" standard and allowing contractors to demonstrate they have experience in meeting the tasks requirements on certain contracts although they may not have been specifically for trailers having a gross vehicle weight of 8,000 pounds? And vice versa allowing contractors to show that they have the experience in meeting the features requirements although maybe not necessarily the specific tasks tied to those contracts?
Answer
Please see the most recent versions of Draft Sections L and M uploaded 21 Dec 2018.
Update #7 ·
SMALL MUNITIONS TRAILERS RESPONSE TO INDUSTRY
As of 19 Dec 2018 - Additional Questions
•1. What is the rule for Past Performance is in terms of elapsed time?
Answer: The rules for Past Performance are stated in the SECTION L PROVISION - INSTRUCTIONS TO OFFERORS. Please refer to "D. Volume III, Past Performance", Item number, 2.
•2. How far back can you go for Past Performance and it be considered relevant?
Answer: Past Performance Format. The paragraph states the history length in years and the format required to present the data.
•3. The metallization process called out for ferrous substrates and subsequent powder coating requirement are production intensive and have a profound impact on the service life and life cycle costs of the trailer. A vendor expressed concern that the lowest cost evaluation criteria may cause offerors to ignore this requirement and the language used in 3.3.1.1.3 may be interpreted as only being required IF components are metallized, instead of all ferrous components as defined in 3.3.1.1 being required to be metallized.
Answer: The Government has carefully considered items that should/should not be evaluated as part of the source selection process. The Government will not be evaluating the capability to perform MWAS as part of the source selection process. However, it should be noted that each offeror is required to fully comply with all requirements of the RFP and resulting contract.
Ignoring this requirement or failing to understand the requirement might enable an offeror to submit a lowest cost bid, and since the relevant sections are not part of Sections L and M, may be missed during the evaluation of offers. To remedy this potential omission, it is recommended that an additional Subfactor be added to Sections L and M requiring offerors to describe how they will accomplish the protective coating of components as defined in sections 3.3.1.1 (all), including listing of structures to be metallized.
Answer: Offerors are encouraged to carefully review PD15WRWNZEA05 paragraph 3.3.1.1, Protective Coatings. This paragraph provides explicit guidance on what coating system(s) shall be applied to components that are used in construction of the assembled trailer.
Further under section 3.3.1, we are unable to determine if metallizing is required.
Answer: PD15WRWNZEA05 paragraph 3.3.1.1 denotes substrate coatings, i.e., commercial, chemical conversion, metallization (MWAS), and topcoat (powder coat) as applicable to particular trailer components/sub-components. Paragraph 3.3.1.1.2 denotes how to prepare aluminum. Paragraph 3.3.1.1.3 denotes how to prepare ferrous for metallization (MWAS. Paragraph 3.3.1.1.4 denotes how to apply metallization (MWAS). Paragraph 3.3.1.1.5 denotes top coat (powder coat). Note that the entire body of Section 3.3.1, Protective Coatings and Finish, must be used in summation to fulfill technical requirements of PD15WRWNZEA05.
How sections 3.3.1.1.3 and 3.3.1.1.4 read is that IF metallizing is performed, it shall be performed in accordance to sections 3.3.1.1.3 and 3.3.1.1.4. However, we do not see anywhere in section 3.3.1 where metallizing is required. If the intent of sections 3.3.1.1.3 and 3.31.1.4 are to require metallizing of all ferrous substrates, we recommend the first sentence of 3.3.1.1.3 be changed to read.
Answer: Each offeror is required to fully comply with all requirements of PD15WRWNZEA05, unless an offeror chooses to bid with exception. Therefore, the Government anticipates, the full cost of metallization (MWAS) and powder coat to be included in the total proposed price of each offeror. However, the Government cannot dictate pricing structures of various offerors.
•4. Can existing trailer units, one of each variant, be made available for inspection, measurement and documentation?
Answer: Refer to Statement of Work (SOW) paragraph 3.7 Government Furnished Equipment (GFE) for details.
•5. Is a debrief possible from current users to describe current shortcomings, advantages, likes and dislikes for the current hardware?
Answer: The current Purchase Description (PD) and Statement of Work (SOW) incorporate any and all areas identified by the users requiring improvements. We see no need to re-address the users at this time.
•6. Can a technical data package, including detailed manufacturing drawings, be made available for inspection and analysis?
Answer: The Government owned drawings from the MHU-141 and MHU-110 will be included in the solicitation. In addition see Table I and II of PD15WRWNZEA05.
•7. It looks like another contractor is the OEM for the trailers. Is there a reason the OEM will not make the new trailers?
Answer: The Government owns the existing drawing packages for the legacy MHU-110 and MHU-141 trailers; in that sense, the Government is the OEM because the Government owns the technical baseline. There have been many vendors over the years who have assembled legacy MHU-110 and MHU-141 trailers. This effort is to design and integrate product improvements into the existing, legacy design using new Government provided Purchase Description, Statement of Work, and the legacy MHU-110 and MHU-141 drawing packages. New trailers designs will be the outcome of this acquisition; it is in the best interest of the Government to competitively award a contract for this acquisition.
•8. How far along is the design for the new trailers? Will the contractor be required to design new elements of the trailer or prove the design through analysis? Will a completely new TDP be required (TOs, engineering drawings, cataloguing, FEA analysis results, etc)?
Answer: Please refer to the answer for Question 1, above, as well as the Statement of Work and Purchase Description PD15WRWNZEA05 for the technical and logistical requirements of this acquisition effort.
•9. Will there be a BOM/drawings available for the RFP or is that part of the design element of this task?
Answer: Please refer to the Statement of Work and Purchase Description PD15WRWNZEA05 for the technical and logistical requirements of this acquisition effort.
•10. Will Robins AFB personnel want to witness the design and build locally or is it expected that all trailers will be delivered to Hill AFB?
Answer: Please refer to the Statement of Work and Purchase Description PD15WRWNZEA05 for the technical and logistical requirements of this acquisition effort. Shipment of first article trailers is contained within the Statement of Work and Purchase Description PD15WRWNZEA05; shipment of production trailers will be as specified in the resulting contract.
Update #6 ·
Uploaded revised Draft copy of Section M to FedBizOpps. The draft attachment uploaded today is the most recent document.
Update #5 ·
SMALL MUNITIONS TRAILERS RESPONSE TO INDUSTRY
As of 19 Nov 2018 - Additional Questions
•1. Do you have information pertaining to the size and what this trailer will be hauling?
Answer: This Information is included in the Draft Purchase Description (PD) attached to Presolicitation notice under Solicitation number FA8532-MHU-110-141:
https://www.fbo.gov/index?s=opportunity&mode=form&id=57c6a2f8258caad41266a80a2031c7ef&tab=core&_cview=1
Update #4 ·
UPDATE:
The draft Sections L & M are for information and comments if any and are subject to change in the final solicitation document that will be published to FedBizOpps. These documents are drafts only and final copies will be attached to the final solicitation document that will be published to FedBizOpps.
Update #3 ·
******THIS NOTICE WILL SERVE AS THE PRIMARY LINK FOR ALL INQUIRIES IN REGARDS TO THE SMALL MUNITIONS TRAILERS ACQUISITION. A PREVIOUS PRESOLICITATION NOTICE WAS POSTED TO FEDBIZOPPS UNDER SOLICITATION # FA8532-MHU-110-141. THE LINK TO THE PREVIOUS PRESOLICITATION NOTICE IS: https://www.fbo.gov/index.php?mode=form&id=aade22201fb149cdb7193d87313e5c71&tab=ntype
The Government's request for proposal will be posted referencing this Solicitation number (FA8532-18-R-0003) The link to this notice is: https://www.fbo.gov/index?s=procurement&mode=form&id=9891f38508a70d4173c21926c3c4e0bc&tab=ntype
Listed below are the current questions/answers already received in regards to this notice and the PreSolicitation notice found on this notice and at: https://www.fbo.gov/index?s=procurement&mode=form&id=9891f38508a70d4173c21926c3c4e0bc&tab=ntype
SMALL MUNITIONS TRAILERS RESPONSE TO INDUSTRY
As of 16 Nov 2018
•1. Please advise the expected release date for the MHU-110-141 solicitation.
Answer: On or about Mid December 2018 to January 2019 timeframe.
•2. Please provide reference National Weapons Center Handbook 63-126. I have unsuccessfully attempted through below reference link from AFI 63-125 and a google search.
Answer: The NWC can be accessed on the World Wide Web at https://wwwmil.nwc.kirtland.af.mil/nwc/e-Guide/WebHelp/index.htm.
Update #2 ·
******THIS NOTICE WILL SERVE AS THE PRIMARY LINK FOR ALL INQUIRIES IN REGARDS TO THE SMALL MUNITIONS TRAILERS ACQUISITION. A PREVIOUS PRESOLICITATION NOTICE WAS POSTED TO FEDBIZOPPS UNDER SOLICITATION # FA8532-MHU-110-141. THE LINK TO THE PREVIOUS PRESOLICITATION NOTICE IS: https://www.fbo.gov/index.php?mode=form&id=aade22201fb149cdb7193d87313e5c71&tab=ntype
The Government's request for proposal will be posted referencing this Solicitation number (FA8532-18-R-0003) The link to this notice is: https://www.fbo.gov/index?s=procurement&mode=form&id=9891f38508a70d4173c21926c3c4e0bc&tab=ntype
Update #1 ·
This synopsis is for a Firm Fixed Price, Indefinite Delivery Indefinite Quantity (IDIQ) Contract for the Small Munitions Trailers Acquisition. The duration of the contract will be 7 years total to include a Basic contract period of two (2) years and five (5) additional annual 12 month
option periods. The period of performance will be for a total of seven years and include a basic contract period of 24 months for ramp up and First Articles (FA) and five option periods of 12 months each.
The successful offeror (contractor) shall provide support development and procurement of two MHU classifications: NSN 1740-01-644-2083RN (PART NUMBER MHU-110V2) and NSN 1740-01-644-2085RN (PART NUMBER MHU-141V2) in accordance with the terms and conditions of the contract resulting from the Request for Proposal (RFP). The successful offeror shall design, test and produce the MHU-110M munitions trailer and MHU-141 munitions trailer in accordance with technical data package, the associated Statement of Work, and the DD1423 data requirements.
First Article units will be required for each NSN. A Product Description (PD) and Statement of Work (SOW) will be provided as part of the RFP package along with various mandatory data deliverables such as First Article Test Plan and Test Reports. Foreign Companies will not be permitted to participate in the competition.
FAR Part 15 procedures will be utilized. Offerors shall prepare their proposals in accordance with mandatory, explicit, and detailed instruction contained in the RFP. This acquisition will utilize the tradeoff source selection process wherein a tradeoff between non-cost factors and cost/price is permitted in order for the Government to make a best value award decision. For those offerors whose proposals are found to be technically acceptable, tradeoffs will be made between past and present performance and cost/price. Past and present performance is considered to be approximately equal to cost/price. The Government will evaluate proposals and make award in accordance with the "Evaluation Basis of Award" provision in the RFP.
Interested offerors may notify the POCs listed below for any additional questions. NO TELEPHONE QUESTIONS. Offerors are encouraged to register to receive notification for solicitation and all amendments/revisions and to check FEDBIZOPPS site prior to submission of their proposal.
It is anticipated that the RFP will be released on or around 30 November 2018 and anticipated award in the August - September 2019 timeframe.
FAR Part 15 procedures will be utilized in the procurement process wherein the Government will utilize the best value source selection process in the determination of an award.
The Technical Data is Export Controlled Data. In order to access Export Controlled Data, Vendors must be registered in FBO, CCR, JCP and be approved for export control document access.
Potential offerors shall propose to every line item in the Schedule of the written Solicitation/Request for Proposal (RFP).
Information in this announcement relative to line items is tentative and is subject to change in the final solicitation document that is published on FedBizOpps (FBO).
Solicitation Number: FA8532-18-R-0003
Contracting Office:
SUPPORT EQUIPMENT -
AFLCMC/WNKAA
235 BYRON ST STE 19A
ROBINS AFB, GA 31098-1670
Primary Points of Contact.:
Erica Carter,
Contract Specialist erica.carter.3@us.af.mil Phone: (478)222-1859
Janeka Jones, Contract Special janeka.jones.1@us.af.mil Phone: 478-222-1859
Secondary Point of Contact:
Lenora J. Elliott,
Contract Officer lenora.elliott@us.af.mil Phone: (478)222-1942
PSE: 1740
NAICS: 333924
Set Aside: 100% Small Business Set-Aside
All responsible sources may submit a bid, proposal, or quotation which shall be considered by the agency.
Tentative Line Item Descriptions Below for Basic Year:
Item: 0001
NSN: 1740-01-644-2083RN
Noun: MHU 110V2 Small MunitionTrailer (First Article Units)
Delivery: 24 months ARO
Qty: 3
Unit of Issue: Each
Item: 0002
NSN 1740-01-644-2085RN
Noun: MHU 141V2 Small MunitionTrailer (First Article Units)
Delivery: 24 months
Qty: 3
Unit of Issue: Each
CLIN 0003
Noun: Data
Unit of Issue: Not Separately Priced (NSP)
0003AA ELIN A001 Monthly Status Report 1 LO NSP
0003AB ELIN A002 Management Plan 1 LO NSP
0003AC ELIN A003 Integrated Master Schedule l LO NSP
0003AD ELIN A004 Technical Report-Study Services 1 LO NSP
0003AE ELIN A005 Conference Agenda 1 LO NSP
0003AF ELIN A006 Conference Minutes 1 LO NSP
0003AG ELIN A007 System Safety Program Plan 1 LO NSP
0003AH ELIN A008 System Safety Hazard Analysis 1 LO NSP
0003AJ ELIN A009 Corrosion Prevention and Control 1 LO NSP
0003AK ELIN A00A Tech Report-Study Services 1 LO NSP
0003AL ELIN A00B Finite Element Analysis Report 1 LO NSP
0003AM ELIN A00C Finite Element Analysis Report 1 LO NSP
0003AN ELIN A00D Tech Report-Study Services 1 LO NSP
0003AP ELIN A00E Tech Report-Study Services 1 LO NSP
0003AQ ELIN A00F Durability & Damage Tolerance 1 LO NSP
0003AR ELIN A00H Provison Guidance Conf Agenda 1 LO NSP
0003AS ELIN A00J Provision Guidance Conf Min 1 LO NSP
0003AT ELIN A00K First Article Test Plan 1 LO NSP
0003AU ELIN A00L First Article Test Procedure 1 LO NSP
0003AV ELIN A00M Contractor Progress Report 1 LO NSP
0003AW ELIN A00N Prod accept test procedure & report 1 LO NSP
0003AX ELIN A00P Test Inspection Report 1 LO NSP
0003AY ELIN A00Q Product Base Line Report 1 LO NSP
0003AZ ELIN A00R Engineering Change Proposal 1 LO NSP
0003BA ELIN A00S Notice of Revision 1 LO NSP
0003BB ELIN A00T Request for Variance (RFV) 1 LO NSP
0003BC ELIN A00U Conference Agenda 1 LO NSP
0003BD ELIN A00V Conference Minutes 1 LO NSP
0003BE ELIN A00W Conference Minutes 1 LO NSP
0003BF ELIN A00X Conference Agenda 1 LO NSP
CLIN 0004 ELIN B001 Data, Tech Manual Contract Requirement 1 LO Price
CLIN 0005 ELIN C001 Data, Product Drawings/models & Assoc lists 1 LO Price
CLIN 0006 Data
0006AA ELIN D001 Logistics Product Data 1 LO Price
0006AB ELIN D002 Eng Data for Provisioning 1 LO Price
Tentative Line Item Descriptions Below for Option Years:
Option I
1001 MHU 110V2 Small Munitions Trailers Min Max
1 125 ea*
1002 MHU 141V2 Small Trailers 1 125 ea*
NOTE: To be ordered in any combination NOT TO EXCEED a total of 125 between the two trailers.
Option II
2001 MHU 110V2 Small MunitionTrailer Min Max
1 300 ea*
2002 MHU 141V2 Small Munition Trailer 1 300 ea*
NOTE: To be ordered in any combination NOT TO EXCEED a total of 300 between the two trailers.
Option III
3001 MHU 110V2 Small MunitionTrailer Min Max
1 300 ea*
3002 MHU 141V2 Small Munition Trailer 1 300 ea*
NOTE: T To be ordered in any combination NOT TO EXCEED a total of 300 ea between the two trailers.
Option IV
4001 MHU 110V2 Small MunitionTrailer Min Max
1 300 ea*
4002 MHU 141V2 Small Munition Trailer 1 300 ea*
NOTE: To be ordered in any combination NOT TO EXCEED a total of 300 between the two trailers.
Option V
5001 MHU 110V2 Small MunitionTrailer Min Max
1 300 ea*
5002 MHU 141V2 Small Munition Trailer 1 300 ea*
NOTE: To be ordered in any combination NOT TO EXCEED a total of 300 between the two trailers.
Attachments
Show all 50
This notice has more attachments on GovTribe.