About this file

This document provides details for a federal solicitation seeking proposals for small munitions trailers. The solicitation involves a firm fixed price IDIQ contract over seven years total, including a basic two year contract and five additional option periods of one year each. The Air Force Materiel Command is seeking to procure two classifications of small munitions trailers, the MHU-110V2 and MHU-141V2, in accordance with the terms and conditions of the resulting contract. Offerors must propose for all line items which include first article units and option year quantities of the trailers in any combination not to exceed the stated maximums. Proposals are due in August 2019, with award anticipated in September 2019. The solicitation will utilize tradeoff source selection and is set aside for small businesses.

View the file

Other files for this federal contract opportunity

Other files attached to Small Munitions Trailers, newest first.
File Type Posted
Industry_Questions_and_Answers_19_Apr_2019.docx DOCX document
Industry_Questions_and_Answers_16_Apr_2019_(002).docx DOCX document
FA853218R0003_______0004.pdf PDF
Industry_Questions_and_Answers_10_Apr_2019.docx DOCX document
FA853218R0003_______0003.pdf PDF
Industry_Questions_and_Answers_26_Mar_2019.DOCX DOCX document
Question_and_Answer_Industry_22_Mar_2019.docx DOCX document
20_March_2019_Industry_Question.pdf PDF
FA853218R0003_______0002.pdf PDF
Questions_and_Responses_8_Mar_2019.docx DOCX document
ppi_tool.accdb MDB file
CDRL_ELIN_A004.pdf PDF
CDRL_ELIN_A009.pdf PDF
Attachment_8.xlsx XLSX spreadsheet
Attachment_6.docx DOCX document
CDRL_ELIN_A00E.pdf PDF
CDRL_ELIN_A00D.pdf PDF
CDRL_ELIN_A005.pdf PDF
CDRL_ELIN_D003.pdf PDF
Attachment_1.docx DOCX document
CDRL_ELIN_A008.pdf PDF
Attachment_3.docx DOCX document
CDRL_ELIN_A00C.pdf PDF
CDRL_ELIN_A00N.pdf PDF
Attachment_5.docx DOCX document
CDRL_ELIN_A00Q.pdf PDF
CDRL_ELIN_D001.pdf PDF
CDRL_ELIN_A00U.pdf PDF
SOW.pdf PDF
CDRL_ELIN_B003.pdf PDF
CDRL_ELIN_C004.pdf PDF
CDRL_ELIN_A002.pdf PDF
Attachment_4.docx DOCX document
CDRL_ELIN_C002.pdf PDF
CDRL_ELIN_A00L.pdf PDF
M-900.pdf PDF
Packaging_AFMC_158.pdf PDF
CDRL_ELIN_A001.pdf PDF
CDRL_ELIN_A00B.pdf PDF
CDRL_ELIN_A00T.pdf PDF
L-900.pdf PDF
CDRL_ELIN_A006.pdf PDF
Attachment_2.docx DOCX document
CDRL_ELIN_A00M.pdf PDF
Attachment_9.xlsx XLSX spreadsheet
26_Feb_2019_Industry_Questions.docx DOCX document
14_Feb_2019__Industry_Questions_and_Responses.docx DOCX document
Draft_Section_L_Small_Munition_Trailers.doc DOC document
DRAFT_COPY_OF_Section_M_Small_Munition_Trailers.doc DOC document
Draft_Section_L_Small_Munition_Trailers.doc DOC document
Show all 50

Small Munitions Trailers has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Industry Questions – 14 March 2019

1. Question: I have sent the following form DD2345 to the JCP for ability to open the locked items within this Solicitation. We obviously need to see this material for this solicitation. Can you help please?

Answer: Verify your company is authorized to access Export Controlled Information in SAM, JCP, and FBO (all three website locations are listed in the paragraph below). If your company has registered at all 3 locations, has active accounts, and continues to have difficulties accessing export controlled data, please ensure your company’s information (CAGE, DUNS, CAGE, etc.) is input into each location exactly the same. If your information is active and the same at all 3 locations, contact the POC/Focal point for the respective system/website. Restating instructions for access to export controlled data below:

In order for a vendor to access the TDP and other Export Controlled data, the vendor must also be authorized to access Export Control Data via all 3 locations listed below:

- Vendor registered at SAM) http://www.sam.gov/Default.aspx

- Vendor registered at JCP and approved to view export control https://public.logisticsinformationservice.dla.mil/PublicHome/jcp/default.aspx The JCP system is the approval authority for export control. The solicitation and the export control documents, even though they are linked together on FBO, are separate downloads for the vendor. The FBO system controls access to the export control attachments by checking with the SAM and JCP systems automatically. If not approved by JCP, access is denied to the export control attachments in FBO.

- Vendor registered at FBO https://www.fbo.gov/

2. Question: There is a discrepancy regarding submission requirements for individual volumes. L-900 II.A states that “Each volume should be submitted in a separate binder as set forth below…”. L-900 II.A.2 implies that all volumes go in a single notebook or binder, as it states, “Each volume within the proposal notebook shall be separately tabbed and identified.” Please clarify if each volume should be submitted in a separate binder or if all volumes should be placed in one binder and individually tabbed.

Answer: Each volume should be submitted in a separate binder. Section LII.A. General states: “Each volume should be submitted in a separate binder as set forth below.”

3. Question: In order to assist in developing the Engineering Requirements and to level the playing field between the proposing contractors, will the government provide copies of the current Technical Orders and Technical Manuals for both the MHU 110 and MHU 141?

Answer: The legacy technical orders (TOs) do not assist with any technical development for the Engineering Requirements. The complete TDP, consisting of legacy MHU-110/141 drawings, PD15WRWNZEA05, and the SOW, contains all of the engineering requirements for this project, including technical and performance requirements. Therefore legacy MHU-110/141 TOs are not part of the MHU-110V2/141V2 TDP and will not be released with this RFP.

4. Questions: Referencing Section L. Attachment, Para. 1.(c) of the Volume IV-Price instructions on page 10 of 31, can the government please confirm their desire that Offerors complete Section B – CLIN Pricing from the solicitation and insert the completed section into Volume I – Completed RFP? If not, please provide exact instructions on how Section B of the RFP should be handled.

Answer: The Completed RFP is submitted as Volume I. The completed RFP includes the signed and completed copies of the entire solicitation (including Section B and all clauses filled-in) and any solicitation amendments. Section L.B.1 (page 3 of 31) states “Volume I, Completed RFP shall consist of the completed and signed RFP, to include any amendments issued, with a cover letter delineating any exceptions taken to the RFP terms and conditions with accompanying rationale.”

Volume IV – Price Volume IV should include completed Attachment 7 Small Munitions Pricing Model. Section IV should not include completed Schedule B from the RFP.