The Department of the Interior's National Park Service, through its Denver Service Center Contracting Services Division, is soliciting competitive proposals under RFP 140P2026R0091 to rehabilitate the rainshed and water treatment system at Hawaii Volcanoes National Park, with proposals due November 27, 2026. The procurement is unrestricted (No Set-Aside Used), and large business offerors must submit a small business subcontracting plan. Place of performance is Volcano, Hawaii, within Hawaii Volcanoes National Park, the customer organization the Denver contracting office serves. The NAICS code is 237110 and the PSC is Y1NE.

Base CLIN 1 rehabilitates the water treatment system, CLIN 2 replaces Building 43, CLIN 3 replaces Building 241, and CLIN 4 covers historic preservation at redwood tanks. CLIN 5 (SAR Building replacement), CLIN 6 (water treatment repair and improvement), and CLIN 7 (chain link fence) are options. The contract is firm-fixed-price with a 610-calendar-day period following notice to proceed. The contractor must maintain a minimum 22,000 gallons-per-day potable water supply throughout performance. Liquidated damages are $1,558.00 per calendar day of delay. Performance and payment bonds are due within 10 calendar days of award.

Technical requirements include a qualified archeological monitor for all ground-disturbing activities and a Draft Archeological Monitoring Report due within 90 days of construction completion. CCTV must integrate with the existing Verkada system (not Genetec), with UPS backup for 24-hour surveillance operation. Scope also includes slow sand filter media replacement and hazardous materials management. Underground cement water piping must be assumed to contain asbestos unless tested. NPS retains responsibility for relocating its stored contents from Buildings 43 and 241, with planning for up to eight weeks. The contractor must place twelve temporary storage containers as early preconstruction work after notice to proceed. Demolition beneath those buildings cannot start until the Contracting Officer confirms the area is available. Projects must be fully completed, not in progress, to receive evaluation credit under Project Experience and Past Performance.

Evaluation uses best value tradeoff, with technical and management factors, past performance, and price. Volume I covers project experience, technical approach, management approach, and construction schedule. Volume II covers the SF-1442, a price schedule with Schedule of Values, bid guarantee, and representations and certifications. Buy American construction materials and Davis-Bacon wage rates apply.

Amendment 0004 extends the deadline from November 20 to November 27, 2026, and adds Attachments 25 and 26. Offerors must acknowledge receipt before the deadline, and failure to do so may result in rejection of the offer. Amendment 0003 added nine reference attachments, and the A-E Technical Addendum lists 53 itemized changes. The September 30, 2026 site visit and the October 15, 2026 question deadline have passed.

Notice text

5 versions

Update #5 · Latest ·

Amendment 4. HAVO 326181 Rehabilitate Rainshed & Water Treatment System located at Hawaii Volcanoes National Park, Volcano, Hawaii

Update #4 ·

Amendment 3. HAVO 326181 Rehabilitate Rainshed & Water Treatment System located at Hawaii Volcanoes National Park, Volcano, Hawaii

Update #3 ·

Amendment 2. HAVO 326181 Rehabilitate Rainshed & Water Treatment System located at Hawaii Volcanoes National Park, Volcano, Hawaii

Update #2 ·

Amendment 1. HAVO 326181 Rehabilitate Rainshed & Water Treatment System located at Hawaii Volcanoes National Park, Volcano, Hawaii

Update #1 ·

HAVO 326181 Rehabilitate Rainshed & Water Treatment System located at Hawaii Volcanoes National Park, Volcano, Hawaii

Files

File Type Posted
Sol_140P2026R0091_Amd_0004.pdf PDF
B09_Att_(26)_Supplemental-Technical-Addendum_02_0004.xlsx XLSX spreadsheet
B09_Att_(25)_Revised-RFI-102-Response_0004.xlsx XLSX spreadsheet
B09_Att_(19)_Spec-09-67-23_Resinous-Flooring_0003.pdf PDF
B09_Att_(22)_REFERENCE_RedwoodTanks2018TripReport_0003.pdf PDF
B09_Att_(21)_REFERENCE_Redwood-Water-Tank-Drawing_0003.pdf PDF
Sol_140P2026R0091_Amd_0003.pdf PDF
B09_Att_(24)_REFERENCE_PrePropSiteVisitSignInSheet_0003.pdf PDF
B09_Att_(17)_A-E-Technical-Addendum_0003.pdf PDF
B09_Att_(16)_Pre-Proposal_RFI_Responses_0003.pdf PDF
B09_Att_(18)_Spec-09-65-00_Resilient-Base_0003.pdf PDF
B09_Att_(20)_REFERENCE_ElectricalAsBuiltDrawings_0003.pdf PDF
B09_Att_(23)_REFERENCE_2024TankInspectionReports_0003.pdf PDF
Sol_140P2026R0091_Amd_0002.pdf PDF
B09_Att_(15)_HAVO_326181_-_Site_Walk_Requirements_30JUL2026_0001.pdf PDF
Sol_140P2026R0091_Amd_0001.pdf PDF
B08_Att_(5)_HAER_Drawings_HAVO_Rainshed.pdf PDF
B08_Att_(11)_Solit_PSP_Vol_II_SubKPlan.docx DOCX document
B08_Att_(13)_HAVO_326181_Final_CD_Basis_of_Design_Product_Files.pdf PDF
B08_Att_(2)_HAVO_326181_26_0908_Final_CD_Drawing_Set.pdf PDF
B08_Att_(3)_2024_08_26_-_Geotechnical_Data_Report_-_HAVO_Rainsheds_Shear_Wave_Velocity_Survey.pdf PDF
B08_Att_(14)_Hazardous_Material_Survey_HAVO_Rainshed_Enviroquest_May2025.pdf PDF
Sol_140P2026R0091.pdf PDF
B08_Att_(7)_HAVO_326181_Construction_Phasing_Calcs.xlsx XLSX spreadsheet
B08_Att_(9)_Redwood_Water_Tanks_Trip_Rpt_and_Prelim_Treat_Recs__2018.pdf PDF
B08_Att_(10)_Davis-Bacon_Act_WD__HI20260001.pdf PDF
B08_Att_(12)_GenRefs.docx DOCX document
B08_Att_(1)_HAVO_326181_26-0908_Project_Specifications.pdf PDF
B08_Att_(4)_2025_01_02_-_Geotechnical_Report_HAVO_Rehabilitate_Water_Treatment_System.pdf PDF
B08_Att_(6)_HAER_HAVO_Water_Collection_System_HI-76__Final_report.pdf PDF
B08_Att_(8)_HAVO_326181_Construction_Phasing_Memo.pdf PDF
Show all 31

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
Pre-Solicitation HAVO 326181 Construction Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
GRCA 318719 North Rim & Springs Rehabilitation Pro NAICS 237110 — No set-aside
GRCA 257282 - Replace Wastewater Plant at South Ri Grand Canyon, Arizona, United States · NAICS 221320 National Office No set-aside
Request for Proposal EFMO 224159/318539, Rehabilit NAICS 236220 — No set-aside
11842 perl renovate 7 public restrooms NAICS 236220 — No set-aside
Preventive Maintenance and Repair Services - Kahuku Training Area (KTA) Kahuku, Hawaii 96731, United States · NAICS 561210 Army Contracting Command Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors