This is a pre-proposal Question and Answer log for National Park Service solicitation 140P2026R0091 addressing the HAVO 326181 project.

The project encompasses significant rehabilitation and construction work at Hawaii Volcanoes National Park, including replacement of Buildings 43 and 241, construction of a new Storage and Administrative Records (SAR) Building as an option, water treatment system improvements, and associated infrastructure upgrades. Key deliverables include CLIN 1 (Rehabilitate Water Treatment System—base contract), CLIN 2 (Replace Building 43), CLIN 3 (Replace Building 241), CLIN 4 (Historic Preservation at Redwood Tanks), CLIN 5 (Replace SAR Building—option), CLIN 6 (Repair and Improve Water Treatment System—option), and CLIN 7 (additional Chain Link Fence—option). The contractor must maintain a minimum 22,000 gallons-per-day potable water supply throughout the 610-calendar-day contract period and coordinate extensively with NPS operations, including protection of existing equipment, temporary water supplies, and sequential system shutdowns. Critical technical requirements include ground catchment rehabilitation, slow sand filter media replacement, CCTV integration with existing Verkada security systems (not Genetec), UPS backup power for 24-hour surveillance operation, fire protection service installation, and extensive hazardous materials management. The contractor must provide a qualified archeological monitor for all ground-disturbing activities and submit a Draft Archeological Monitoring Report within 90 days of construction completion, with final reporting permitted as an administrative closeout activity beyond contract close-out. The proposal submission deadline is local Hawaii Standard Time, and projects must be fully completed (not in-progress) for evaluation credit under Project Experience and Past Performance factors.

View the file

Other files

File Type Posted
B09_Att_(21)_REFERENCE_Redwood-Water-Tank-Drawing_0003.pdf PDF
Sol_140P2026R0091_Amd_0003.pdf PDF
B09_Att_(24)_REFERENCE_PrePropSiteVisitSignInSheet_0003.pdf PDF
B09_Att_(23)_REFERENCE_2024TankInspectionReports_0003.pdf PDF
B09_Att_(20)_REFERENCE_ElectricalAsBuiltDrawings_0003.pdf PDF
B09_Att_(18)_Spec-09-65-00_Resilient-Base_0003.pdf PDF
B09_Att_(17)_A-E-Technical-Addendum_0003.pdf PDF
B09_Att_(19)_Spec-09-67-23_Resinous-Flooring_0003.pdf PDF
B09_Att_(22)_REFERENCE_RedwoodTanks2018TripReport_0003.pdf PDF
Sol_140P2026R0091_Amd_0002.pdf PDF
B09_Att_(15)_HAVO_326181_-_Site_Walk_Requirements_30JUL2026_0001.pdf PDF
Sol_140P2026R0091_Amd_0001.pdf PDF
B08_Att_(13)_HAVO_326181_Final_CD_Basis_of_Design_Product_Files.pdf PDF
Sol_140P2026R0091.pdf PDF
B08_Att_(9)_Redwood_Water_Tanks_Trip_Rpt_and_Prelim_Treat_Recs__2018.pdf PDF
B08_Att_(12)_GenRefs.docx DOCX document
B08_Att_(4)_2025_01_02_-_Geotechnical_Report_HAVO_Rehabilitate_Water_Treatment_System.pdf PDF
B08_Att_(6)_HAER_HAVO_Water_Collection_System_HI-76__Final_report.pdf PDF
B08_Att_(3)_2024_08_26_-_Geotechnical_Data_Report_-_HAVO_Rainsheds_Shear_Wave_Velocity_Survey.pdf PDF
B08_Att_(8)_HAVO_326181_Construction_Phasing_Memo.pdf PDF
B08_Att_(14)_Hazardous_Material_Survey_HAVO_Rainshed_Enviroquest_May2025.pdf PDF
B08_Att_(2)_HAVO_326181_26_0908_Final_CD_Drawing_Set.pdf PDF
B08_Att_(1)_HAVO_326181_26-0908_Project_Specifications.pdf PDF
B08_Att_(7)_HAVO_326181_Construction_Phasing_Calcs.xlsx XLSX spreadsheet
B08_Att_(10)_Davis-Bacon_Act_WD__HI20260001.pdf PDF
B08_Att_(11)_Solit_PSP_Vol_II_SubKPlan.docx DOCX document
B08_Att_(5)_HAER_Drawings_HAVO_Rainshed.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HAVO 326181 - Pre-Proposal Question & Answer Log | Solicitation 140P2026R0091

RFI # Reference Document Reference Question Answer

Government-Furnished GNSS Equipment

27 00 00; 28 00 00

Please provide the manufacturer/model, product data, installation instructions, mounting requirements, power requirements, communications requirements, grounding/bonding requirements, surge protection requirements, and complete interface information for the Government-furnished GNSS station and associated equipment. (A12-A14; E2)

Keynote #2 and associated junction box on sheet E10 for power will be removed. The Contractor is not required to reinstall the existing GNSS station or associated equipment.

GNSS Mounting Locations / Routing

27 00 00; 28 00 00 Please identify exact mounting locations for exterior GNSS equipment and associated equipment within the SAR Building and required routing between exterior and interior equipment. (A12-A14; E2)

Keynote #2 and associated junction box on sheet E10 for power will be removed. The Contractor is not required to reinstall the existing GNSS station or associated equipment.

Building 241 Transfer Pump Station Protection

01 50 00; 02 41 00

Please define the required temporary protection and support for the Transfer Pump Station and existing buildings that remain during Building 241 demolition and reconstruction, including allowable shutdown durations and whether temporary structural protection, relocation, or temporary utility work is required. (A7-A11; C50-C52)

The Contractor shall maintain continuous power to the main distribution pump room at all times. The Transfer Pump Station shall maintain on-demand power to support emergency water-hauling operations. Temporary power shall also be maintained for the cardboard baler, which is typically operated approximately once per week for 1–2 hours.

Existing equipment to remain, including the cardboard baler, pressure-tank controls, and air compressor controls, shall be protected from weather and damage throughout demolition and reconstruction. Temporary weather protection, structural protection, utility routing, and support systems necessary to meet these requirements shall be the Contractor’s means and methods.

Refer to Division 01 for applicable shutdown and coordination requirements. Any proposed interruption affecting water-system operations shall be coordinated with and approved by NPS in advance.

Existing Electrical Service Capacity / Shutdown Sequence:

26 00 00 Please confirm existing electrical source equipment/capacity and required outage/shutdown sequencing for Building 43 demolition and reconnection, including NPS facilities that must remain continuously energized. (E2-8)

The existing electrical capacity is a 200 amp service disconnect that feeds an existing panel 'RA3' that is a main lug only panel with a nameplate rating of 225 amps, both at 240/120V, 1 phase, 3 wire system.

The existing Rainshed gate is served through Building 43 and shall remain continuously energized during demolition and reconstruction. The Contractor shall coordinate any required outages and shutdown sequencing with NPS and the Contracting Officer prior to interruption of service.

Temporary power shall be provided as necessary to maintain continuous operation of the Rainshed gate.

NPS Temporary Storage Containers;

01 50 00 Please confirm the required quantity, size, exact locations, duration, access requirements, and utility requirements, if any, for the NPS temporary storage containers required by Section 01 50 00. (G11-G12; site logistics drawings)

Refer to Section 01 50 00 and Sheets G11 and G12. Provide twelve (12) 40-foot temporary storage containers for NPS use within the area shown on Sheet G11. Final placement within the designated area shall be coordinated with the Contracting Officer. Maintain access to the containers for NPS staff throughout their use.

The containers shall remain in place until NPS has relocated their contents into completed Buildings 43 and 241, after which the Contractor shall remove the containers.

Provide 6-inches of compacted and leveled base course beneath the twelve temporary 40-foot containers shown on Sheet G11. Geotextile is not required. Upon removal of the temporary containers, restore the area so final grade generally matches the adjacent existing grade. Base course may be removed, redistributed, or otherwise regraded as necessary to achieve the final condition.

The twelve temporary containers shown on Sheet G11 do not require utility connections. The powered storage containers shown at the Magma House location on Sheet G12 are separate from these twelve containers and shall be provided and connected to power as indicated on Sheets G12 and E13.

NPS Permanent 40-ft Storage Containers:

01 50 00; 26 00 00

Please confirm the quantity and final locations of the permanent 40-ft x 8-ft x 8.5-ft one-trip/new storage containers, required foundation/support, feeder source and routing, A/C criteria, and whether the specified 125A panel and 60A exterior disconnect are required at each container. (G11-G12; E2; site logistics drawings)

Refer to contract documents -- provide new 40-foot x 8-foot x 8.5-foot one-trip/new storage containers for NPS use. During construction, place the containers at the Magma House location shown on Sheet G12, adjacent to the existing containers as indicated. The Magma House location is an interim location and is not the intended final location of the containers. No additional base-course or foundation preparation is required at the Magma House location; the containers will be placed on the existing paved surface.

Connect the two containers to power at the Magma House location. Existing electrical infrastructure installed under the previous project shall be utilized where available; provide final connections required to serve the containers in accordance with Sheet E13. Temporary power serving the containers shall be removed at the completion of the Project as indicated on Sheet G12.

Each container shall comply with Section 01 50 00, including one A/C unit, three 4-foot LED ceiling light fixtures, two duplex GFI receptacles, a 125A-capacity panel, and a 60A exterior disconnect.

NPS will take ownership of the two containers following delivery, approved placement, and completion of the electrical connection. Following completion of Building 241, the containers are intended to be relocated from Magma House to the Rainshed/Building 241 area. NPS will assume responsibility for final relocation and final electrical connection at Building 241.

Room Finish Schedule: Spec Section - Finishes

09 00 00 In reference to the Room Finish Schedule, epoxy flooring, resilient cove base, and wainscot are required, but there is no spec section regarding these items. Please provide specific specs for these items. (A19)

See Spec Section 06 20 23 - Interior Finish Carpentry for Wainscot. The following specification sections will be added to the Contract Documents via amendment to support the Room Finish Schedule requirements:

-Section 09 65 00 – Resilient Base -Section 09 67 23 – Resinous Flooring

Provide the indicated finishes in accordance with Sheet A19 and the added specification sections.

8 Grounding Electrode Systems: 26 05 26

Please confirm which new structures require concrete-encased electrodes, driven ground rods, intersystem bonding terminals, and other grounding electrodes under Section 26 05 26, and identify required locations where these are not explicitly shown. (E2; E7-E8;

structural foundation sheets)

All new structures that have concrete footings that touch the earth with rebar that allows one continuous 20' feet run of 3/4" rebar concrete encased per NEC 250.50 and per adopted Hawaii codes. Existing buildings can utilize driven ground rods as noted on drawings E7 and E8. Main bonding jumpers are noted on drawings E7 and E8.

5-Ohm Ground Resistance Requirement:

26 05 26

Section 26 05 26 requires grounding-system resistance not to exceed 5 ohms. Please confirm whether electrical subcontractors are to include unlimited supplemental electrodes/modifications necessary to achieve 5 ohms or whether a defined base electrode configuration should be provided with additional measures handled if testing demonstrates they are required. (Electrical drawings)

Refer to Section 26 05 26. The Contractor shall include in its bid the grounding electrode system and any supplemental electrodes or modifications necessary to achieve a maximum grounding-system resistance of 5 ohms. Compliance with the 5-ohm requirement shall be verified by testing in accordance with Section 26 05 26.

10 Surveillance Equipment/CCTV: 28 23 00

Please confirm whether the new CCTV system is intended to be a standalone Genetec Security Center system or integrated into an existing National Park Service Genetec system. If it is an expansion of an existing system, please provide the existing Genetec version, System ID, and any applicable licensing or integration requirements. The specifications identify Genetec as the basis of design but do not identify whether this is a new or existing system.

The new CCTV system shall integrate with the Park's existing Verkada Command security environment and shall not be provided as a separate standalone Genetec system. The Contractor shall provide all video-surveillance equipment, software, licensing, interfaces, and integration components required for a complete operational system compatible with the existing Verkada environment. Section 28 23 00 will be revised accordingly. NPS IT/Security will provide the existing system information and administrative/network support necessary for final integration.

11 Surveillance Equipment/CCTV: 28 23 00

The drawings indicate nine surveillance cameras; however, the specification requires the video recording system to be sized for 50 cameras, 30-day retention, 12 hours per day of event recording, H.264 compression, and 2-megapixel cameras. Please confirm whether the 50-camera capacity is a firm project requirement or whether the recording system may be sized based on the cameras installed under this project. (E3, E-4)

The recording system may be sized based on the quantity of cameras installed under this project + 30 day retention + 24-hour recording.

12 Surveillance Equipment/CCTV: 28 23 00

The electrical drawings call out 360-degree video surveillance cameras, while the specifications identify Axis as the basis-of-design manufacturer without providing a specific camera model. Please confirm whether true 360-degree panoramic cameras are required or if an Axis multi-sensor camera providing equivalent coverage will be acceptable.

A multi-sensor (example quad lens) camera shall be sufficient if it provides coverage in all directions, except in circumstances where view directly below camera is needed, in which case a fish eye or 360 PTZ camera shall be used.

13 Surveillance Equipment/CCTV 28 23 00

The drawings show PoE network switches at Buildings 43 and 241. Please confirm whether the network switches are contractor-furnished or Government-furnished. If contractor-furnished, please provide any NPS requirements for manufacturer, model, VLAN configuration, cybersecurity, or network management standards.

Network switches shall be OFOI.

14 Surveillance Equipment/CCTV 28 23 00 Please confirm who will provide IP addresses, VLAN assignments, network configuration, and connection to the NPS network. Also confirm whether the security contractor will be required to configure the switches or if configuration will be performed by NPS IT.

NPS IT shall provide networking support.

15 Surveillance Equipment/CCTV 28 23 00 Please confirm whether UPS equipment is required for the CCTV network switches, NVR, and associated security equipment, and if so, whether there is a required runtime.

The basis-of-design UPS for the video surveillance system is an Eaton/Tripp Lite SmartPro rack-mounted UPS system, or equal. Basis-of-design product data is provided with the Amendment for reference and to establish the general type and quality of equipment intended.

The basis-of-design reference does not establish a brand-specific requirement. Equal products may be provided in accordance with the Contract Documents and applicable Material and Workmanship requirements, subject to the Contracting Officer’s determination that the proposed product satisfies the required performance and functional characteristics.

The UPS system shall, at a minimum:

-Be rack-mounted and suitable for installation with the security system equipment.

-Operate from the project’s 120V, single-phase electrical system.

-Provide not less than 1,500 VA / 1,350 W output capacity.

-Provide line-interactive, sine-wave UPS operation.

-Be UL 1778 listed or provide an equivalent nationally recognized listing appropriate for the equipment.

-Be capable of connection to compatible external battery modules.

Be sized, including all required external battery modules, to maintain the required video surveillance system operation for a minimum of 24 continuous hours following loss of normal power.

The number and capacity of battery modules shall be based on the actual connected security-system load and the UPS manufacturer’s published runtime data or calculations. The 24-hour backup-power requirement governs over any shorter runtime shown in the basis-of-design product literature.

Product data for any proposed equal shall demonstrate compliance with the above salient characteristics and the complete Contract requirements.

16 Surveillance Equipment/CCTV 28 23 00 Please confirm whether a new Genetec operator workstation and monitors are required under this project or whether the Government will use an existing workstation.

Three operator workstations and monitors shall be provided as part of the contractor's scope, required under this project. There are no existing workstations at this time.

17 Surveillance Equipment/CCTV 28 23 00

The specification requires camera locations and fields of view to be confirmed with the Contracting Officer before the camera mounts are permanently secured. Please confirm whether a formal camera FOV submittal or pre-installation camera layout is required prior to installation.

Camera shop drawings showing camera types and model numbers and layout/locations are required for review and approval by NPS (Chief Ranger and Park Physical Security Coordinator) prior to installation.

18 Surveillance Equipment/CCTV 28 23 00

The specifications require final testing in the presence of the Contracting Officer and manufacturer's representative. Please confirm whether an on-site Axis and/or Genetec factory representative is required or whether a certified integrator representative will satisfy this requirement.

A certified integrator will satisfy this requirement.

19 Surveillance Equipment/CCTV 28 23 00 The specification requires eight hours of operational training and two hours of maintenance training. Please confirm the anticipated number of Government personnel attending and whether training must be conducted in a single session or may be split between sessions.

12-18 employees may attend the training. Training would ideally be split into multiple sessions. Training sessions schedule shall be determined between contractor and government.

Available Water During Construction

With the completion of the KVC Welcome Center expected during or after commencement of construction, will the renovated KVC project affect the necessary 22,000 gpd, or is that usage already factored in?

The 22,000 gpd minimum capacity requirement was based on historic water demand (including KVC) information from 2018 through 2022 and increased by 20% to account for increased visitation.

21 Demolition Preparation; 02 41 00 Do buildings 43 and 241 have grade beams installed, and is the as-built documentation available for verification?

Refer to HABS/HAER. See Attachment 5 HAER Drawings of the Solicitation for Building 43. The existing buildings 43 and 241 do not have existing grade beams installed.

Improvements to Water Treatment –

23 00 00 Please provide additional mechanical schedule to include pump equipment replacement or shall spec section 46 00 00 suffice? (M1)

Specification section 46 00 00 includes the pump improvements required.

Access Control – General Conditions

Primary Contractor Access from HWY11, Locked Gate: NPS informed contractors that this gate is to remain locked at all times including during contract work. Will the Prime Contractor need to provide a Security Guard posted for access control? (G11)

Gate must remain locked when vehicles are not entering or exiting for security. It is the contractors choice of how they ensure the gate remains locked when not actively in use.

Building 43 Water Closet Mounting/Carrier

22 25 29

In reviewing the plumbing schedule, it was noticed that the basis of design wall mounted water closet requires a wall bracket for proper installation. This bracket is too large for the intended wall size, where 17” is necessary for proper installation. Please review and modify the assembly to fit in the designated space or modify the wall size to accommodate the original wall mount bracket. (P-3, P-4)

Water closet shall be a floor mount fixture, basis of design Sloan 2029. The schedule on sheet P4 and spec section 22 40 00 will be revised accordingly.

Building 241 Water-System Operations / Shutdowns:

01 50 00; 01 11 00 Please confirm which portions of the water-treatment system must remain continuously operational during Building 241 demolition and erection and identify activities requiring temporary bypass, temporary water, protection, or approved shutdowns.

Refer to RFI 3. Water-system functions necessary to maintain required operations shall remain available throughout Building 241 demolition and reconstruction. Individual components may be temporarily taken offline only through approved sequencing and shutdowns in accordance with the Contract Documents.

Possible Substitution Request:

Metal Roofing

07 61 00

In reviewing the plans and spec section 07 61 00, Part 2.2 requests the material for the sheet metal roofing to be ‘Deep Corrugated Aluminum with no finish or other coating. In speaking to a PEMB vendor, the aluminum roofing could have a significant cost impact to the project. Would Kynar coated steel roofing be considered in lieu of the aluminum roofing requested?

No. This will not meet DOH SDWB and NSF standards for Drinking Water.

Helipad and Adjacent Road Clearance

There are two entrances to the helipad location. Do both entrances need to remain accessible at all times during construction? Additionally, is there a specific clearance needed on the connecting asphalt road to maintain for any barricades or containment?

Both entrances do not need to remain accessible at all times. One entrance needs to remain accessible at all times. Due to the access requirements for various users of the area, it is recommended that the south road that goes past the cell tower be the main access route for park and partner vehicles, as much as is feasible.

28 Active Volcano Hazards Are there any hazards, aside from possible tephra exposure, volcanic gas exposure, wildlife buffer areas (Nene) that contractors and subcontractors need to be aware of?

See section 01 35 23 1.2.A. Includes other potential hazards that maybe encountered. For wildlife requirements, see 01 11 40 3.3

LFA and Invasive Species Testing Requirements

Please confirm that LFA testing requirements are to include all construction activities, including but not limited to: Personal vehicles, professional/company vehicles, deliveries, construction equipment, etc.

Additionally, please confirm that this approximately 30 min process applies to all ownership, management, special inspections, and construction workers associated with the construction of this project.

All vehicles required to be tested, as per Specification 01 11 40 3.2. Inspections take 30 minutes but can take up to 1 hour (01 11 40 3.2.G.2.)

provided Specification 01 11 40 3.2.I. is adhered to.

Contact information for inspection requests will be provided at pre-construction meeting. 01 11 40 3.2 will be revised to include the following inpsection request requirements. Inspection requests MUST include:

1.Details for vehicles:

a.Company or firm name, b.number of vehicles per each company or firm, c.date(s) and time(s) they will arrive for inspection.

2.Materials and equipment: For anything other than vehicles, or if any of those work trucks or personal vehicles will be towing trailers of any kind, or if they are flatbed trucks or larger, with materials or equipment, more details are required. State what the materials or equipment being towed are so they can be identified by inspectors as they arrive.

3.If the item is a larger truck specify what kind, i.e. dump truck, cement truck, semi with trailer bringing pallets, flat rack or a shipping container. This information might prompt additional questions, especially closed containers.

Sand Filter Rehabilitation (CLIN Option 6)

During the pre-proposal site visit, the existing valves associated with the water treatment sand filters appeared to be aged and potentially beyond their useful service life. If CLIN Option 6 is awarded, are these existing valves intended to be replaced as part of the sand filter rehabilitation scope? If replacement is required, please identify the valves to be replaced and provide the applicable valve type, size, material, performance requirements, and specification requirements.

Under Option B / CLIN 6, replace the existing slow sand filter valves identified below:

A total of six (6) 4" valves -- 3 influent and 3 effulent.

Replacement valves shall be ductile-iron gate valves, NSF/ANSI/CAN 61 certified for potable-water service (NIBCO or approved equal), with end connections matching the existing piping and suitable for the installed condition, including direct burial where applicable. Valve materials and installation shall comply with Section 46 00 00 and applicable AWWA requirements.

The Contract Documents will be revised as necessary to identify the valves included in the replacement scope.

Sliding Door Specifications

Specifications for the sliding doors are missing from the RFP docs. Could you please provide the missing specs.

The sliding doors (Type A and Type E Rolling Doors) are to be fabricated in accordance with the contract documents and shop drawings submitted for review. No specification will be forthcoming. Reference 08 33 00 + A17/A19 for additional information.

GC1 excavation – base vs. Option B

01 27 00, 3.1.A/F; C51, C57-C58

Section 01 27 00 assigns GC1 capacity excavation to Option B. Sheets C51 and C57 identify approximately 3,825 CY of excavation without the option designation used elsewhere on those sheets. Please confirm that the capacity excavation, sump excavation, and associated grading belong to Option B, and identify the subgrade preparation required under the base contract if Option B is not exercised.

CLIN 1 includes the removal/replacement of the liner and construction of the berm for GC 1. Option B includes the capacity expansion of GC1 and geotextile underlayment for the liner. If Option B is not exercised, provide subgrade preparation for the replacement liner in accordance with Specification Section 33 47 13 and as per manufacturer's recommendations.

Slow sand filter piping – base vs.

Option B

01 27 00, 3.1.A/F; C51/C53

Section 01 27 00 assigns filter media replacement to the base contract and piping replacement to Option B. C51 includes underdrain piping replacement in an unbracketed callout, while C53 identifies the collection piping as optional. Please confirm the applicable CLIN for piping removal and replacement and the required treatment of existing piping during base-contract media replacement.

Option B includes the removal/replacement of sand filter underdrain piping. If Option B is not exercised, utilize means and methods to protect existing underdrain pipe in place during media removal/replacement.

B43 sanitary sewer – base vs.

option

01 27 00, 3.1.B; C61

Section 01 27 00 includes the new septic tank and conversion of the existing cesspool to a seepage pit under CLIN 2. C61 states that all improvements on that sheet are optional. Please confirm whether the sewer improvements are base-contract work and, if optional, identify the applicable option.

The sewer improvements are base-contract work under CLIN 2. Note 1 on sheet C61 and C62 will be revised.

Collection pipe diameter Construction Phasing Memo, recommendations;

C51/C57

The phasing memo recommends installing a new splitter box and 24-inch pipe to GC2. C57 identifies 30-inch corrugated HDPE piping to both catchments, while C51 includes 24-inch piping callouts. Please confirm the required diameter for each splitter-box outlet and connecting pipe and revise conflicting references.

The HDPE piping to each catchment shall be 30-inch diameter.

Steel tank repair limits

01 27 00, 3.1.A; 09 91 13

CLIN 1 includes preparation, repair, and painting of Tanks 1-4. Please identify the required repairs by tank, including any plate replacement, welding, leak repair, or other structural work, and provide quantities/details sufficient for lump-sum pricing. Please distinguish required repairs from conditions to be evaluated after surface preparation.

"Repair" will be removed from CLIN 1 definition for clarity. The scope of work for Tanks 1-4 is exterior painting including the surface preparation required per spec 09 91 13.

Redwood tank repair limits

01 27 00, 3.1.D; 01 35 91, 3.3

CLIN 4 defines specific minor repairs, while the contractor-prepared Historic Structure Report must recommend additional preservation work. Contractor requests NPS create an allowance or force account budget to cover the repairs noted by the contractor-prepared Historic Structure Report. It is difficult to quantify the value of this work prior to bid, which may result in wildly different assumptions by the contractors bidding the work.

An allowance or force account budget is not considered at this time. The work included in the CLIN 4 lump-sum price consists of the assessment and Historic Structure Report together with the specific preservation and repair work identified in the Contract Documents, including cleaning and treatment of the redwood staves, replacement of the bottom two steel hoops/tension rods, vegetation and soil removal, grading, stone-wall vegetation removal, and associated drainage work. The Historic Structure Report shall document existing conditions and identify and prioritize additional preservation recommendations in accordance with Section 01 35 91. Recommendations contained in the Historic Structure Report that are beyond the repair work specifically identified in the Contract Documents are not included in the CLIN 4 lump-sum scope unless separately authorized by the Contracting Officer. If conditions are identified during the assessment that warrant additional work, the Contractor shall notify the Contracting Officer and shall not proceed with such additional work unless directed in writing via a contract modification.

Asbestos pipe pricing basis 01 11 00, 1.12.B; 02 82 00; C2-C7, Note 12;

Hazardous Material Survey

The underground cement pipe was inaccessible during the hazardous materials survey and must be tested. Because the actual dispensation of the material cannot be determined until the pipe is exposed and tested, contractor requests an allowance or force account buget to cover this cost. It will be difficult to compare bids if all parties use different assumptions for the amount of material ultimately removed.

For bidding purposes, assume approximately 318 linear feet of underground 24-inch pipe is Asbestos Cement Pipe (ACP) and shall be removed and disposed of properly. Include testing to confirm pipe material prior to disturbance or removal.

Existing cesspool suitability

01 27 00, 3.1.B; C61-C62

Please provide available records and investigations establishing the existing cesspool dimensions, condition, and suitability for conversion to the proposed seepage pit. Identify required testing, rehabilitation, and acceptance criteria, and clarify the scope if field investigation determines it cannot serve the proposed system.

Existing dimensions and condition of cesspool are unknown. Testing, rehabilitation, and acceptance criteria shall be in accordance with Hawaii DOH regulations. Septic tank installation shall be performed by HI certified installer.

Foundation voids/unsuitable material

Geotechnical Report, Sections 6-7; 31 20 00

The geotechnical report identifies subsurface voids and soft pumice/tephra and recommends verification and remediation. Please identify the required investigation method and extent beneath proposed foundations, the design criteria/details for void remediation, and the bid quantities or limits for removal and replacement beyond the depicted foundation excavations.

Refer to detail for filling voids on Civil sheets, 9/C23. No void quantity is available at this time. There is no required investigation of the area, only filling voids if/as they are found in project excavation.

22,000 GPD

measurement/baseline

01 11 00, 1.9.F; Construction Phasing Memo/Calcs

Please define where and over what period compliance with the 22,000 GPD minimum will be measured. Provide current usable storage capacities, normal operating levels, and recent water demand/production data, and confirm whether the issued phasing analysis remains the Government accepted planning baseline.

The 22,000 gallons-per-day requirement is a system-wide minimum water-supply requirement and is not intended to be measured at a single catchment, slow sand filter, tank, or other individual component.

In accordance with Section 01 11 00, the Contractor shall maintain the Park water system's ability to provide a minimum of 22,000 gallons per day for the duration of the Project. Compliance may be achieved through continued operation and sequencing of the existing collection, treatment, storage, and distribution system and, when approved by the Contracting Officer and coordinated with Park Water System Operators, through temporary bypass piping and/or potable-water hauling.

The Park has approximately 1,000,000 gallons of usable potable-water storage. Storage tanks are normally maintained at high operating levels and are to be filled to capacity, to the extent operationally practicable, before major water-system components are taken offline. The existing slow sand filtration system has a maximum production capacity of approximately 32,000 gallons per day under normal operating conditions.

Refer to the HAVO 326181 Construction Phasing Memo and supporting calculations for the Government's accepted planning basis for construction sequencing. The analysis assumes conservative low-rainfall conditions and increased water demand and concludes that up to two of the following may be taken offline simultaneously while maintaining water service: Ground Catchment 1, Building 241, and Building 43. All three shall not be taken offline simultaneously.

The Contractor shall develop and submit a project-specific Phasing Plan with the Construction Baseline Schedule demonstrating how the 22,000- GPD requirement will be maintained throughout construction. Actual sequencing and proposed interruptions remain subject to coordination with and approval by the Contracting Officer and Park Water System Operators.

Shutdown windows

01 11 00, 1.9.C; C60

Utility outages are limited to two to four hours. Please confirm whether this limit applies to isolation of individual treatment components and the pump/control replacement work shown on C60, and identify whether longer coordinated shutdowns may be approved where finished-water service remains available.

The limit does apply, however, longer coordinated shutdowns will be considered upon request.

Sand filter return-to-service

46 00 00, 3.7-3.8; C53

Section 46 00 00 requires filter-to-waste operation until the filter matures and turbidity is below 1 NTU. Please confirm any additional sampling, biological maturation, duration, or DOH approval requirements before returning each filter to service. Identify the approved discharge location and responsibility for operating and monitoring the filter during maturation.

Turbidity monitoring is the recommended method for filter maturation based on AWWA standards/manuals. DOH Surface Water Treatment Rule requires filter-to-waste during filter maturation, but does not include specific requirements for monitoring. Coordinate discharge location with Contracting Officer.

Historic tank interior access

01 35 91, 3.3

The Historic Structure Report requires assessment of interior and exterior architectural and structural elements. Please confirm whether entry into each redwood tank is required and identify available access and safety requirements, considering the current state of some of the tanks.

Section 01 35 91 requires the Contractor-prepared Historic Structure Report to include an existing-conditions assessment of both exterior and interior architectural and structural elements of the five historic redwood water tanks. The Contract does not specifically require personnel to physically enter each tank.

The Contractor's qualified Historic Preservation Treatment Specialist shall propose, as part of the Historic Preservation Treatment Plan, the means and methods necessary to obtain sufficient information to document and assess the interior and exterior condition of each tank. The assessment method shall minimize risk to personnel and avoid damage to historic materials. Remote inspection methods may be proposed where they provide adequate information to satisfy the Historic Structure Report requirements. Additional non-destructive or minimally invasive investigative methods may also be proposed where appropriate and shall be subject to Government review prior to use.

If physical entry into a tank is proposed or determined necessary, the Contractor shall comply with the confined-space and other applicable safety requirements of the Contract and OSHA. The Contractor is responsible for determining and implementing the appropriate access, fall-protection, confined-space, rescue, and other safety measures associated with its proposed means and methods.

Use of an Uncrewed Aircraft System (UAS) is not required by the Contract. If the Contractor proposes UAS as an inspection method, its use is subject to prior NPS authorization and all applicable FAA, DOI, and NPS requirements, including NPS Reference Manual 60 and DOI OPM-11. Any proposed UAS must comply with applicable DOI/NDAA restrictions regarding covered UAS, and the required UAS safety and authorization documentation shall be submitted and approved before operation within NPS boundaries.

The supplemental Redwood Water Tanks Vanishing Treasures Report provides prior condition information and treatment recommendations for reference; its recommendations do not independently expand the construction scope beyond the requirements of the Contract Documents.

Geotextile discrepancy

33 47 13, 2.2; C57; Basis of Design Product Files

The drawings and specifications require 32 oz/sy nonwoven geotextile, while the Basis of Design Product Files identify 30 oz material. Please confirm whether 30 oz material meeting the remaining specified properties is acceptable or whether 32 oz/sy is mandatory.

32 oz/sy material is included in the Basis of Design Product Files (page 203) and is required.

Septic/treatment approval status

01 31 00, 1.9; C61-C62; 46 00 00

Section 01 31 00 lists no Government-furnished permits. Please identify existing design approvals and outstanding agency approvals for the septic/seepage system and potable-water treatment modifications, including which submissions require Government/design-team action and which are contractor responsibilities.

No separate Contractor permit application is required for Government design approval of the septic/seepage system or the water-treatment modifications shown in the Contract Documents. NPS will coordinate required NPS Office of Public Health/Public Health Consultant review and any required coordination with the applicable primacy agency.

Construct the septic/seepage system in accordance with Sheets C61-C62 and Section 33 34 00, and perform the water-treatment work in accordance with the applicable Contract Documents.

The Contractor remains responsible for permits, approvals, and utility coordination expressly assigned to the Contractor by the Contract Documents or resulting from the Contractor's means and methods, including applicable electrical utility hookup, temporary utility, stormwater, and NPDES requirements.

Contract completion dates

Solicitation SF1442, Block 11 (p.1); continuation sheet (p.3); H, Special Requirement 1 (p.15)

The solicitation includes a 610-day period after NTP, CLIN performance dates of November 1, 2026- July 3, 2028, and a December 21, 2028 delivery date. Please confirm that 610 calendar days after actual NTP governs completion and identify the anticipated award/NTP dates for proposal scheduling.

The contract duration is 610 calendar days from the Contractor's receipt of the Notice to Proceed. Any calendar dates identified in the solicitation that are inconsistent with the 610-calendar-day duration will be revised by amendment.

The 610-calendar-day period is the Contract Period and is not intended solely as the date for achieving Substantial Completion. The Contractor shall plan and prosecute the Work so that all contract requirements necessary for completion are accomplished within the Contract Period. Except for the post-construction archeological reporting process addressed in RFI 103 and Section 01 35 13.22, as revised by Addendum No. 1.

In accordance with Sections 01 32 16 and 01 77 00, the Contractor's schedule shall include startup, testing, inspections, commissioning, required closeout submittals, Substantial Completion procedures, punch-list work, and final completion/acceptance activities. Substantial Completion shall therefore be scheduled sufficiently in advance of the Contract End Date to permit completion of the remaining punch-list and closeout activities within the Contract Period.

The Contractor shall complete punch-list work within 30 calendar days following Substantial Completion, but in no event shall that provision extend the Contract Period unless an extension is authorized by the Contracting Officer.

Anticipated award and NTP dates cannot be provided at this time; however, if this changes, please note any dates provided are planning dates only and will be identified/updated by amendment as appropriate. The actual Contract End Date will be established from the actual NTP date based on the 610-calendar-day Contract Period.

JV experience/self-performance

Solicitation L, Project Experience/Past Performance;

H, Special Requirement 2

Please confirm how projects performed by individual JV members will be evaluated under Project Experience and Past Performance, including the documentation required to establish their relevance to proposed responsibilities. Also confirm whether on-site work performed directly by either JV member counts toward the prime contractor 15% self-performance requirement.

Confirmed. For an offer submitted by a joint venture, the joint venture is the prime Offeror/Contractor. The individual firms comprising the joint venture are joint-venture members and are not considered subcontractors to the joint venture solely by virtue of their status as JV members.

For purposes of Project Experience and Past Performance, relevant experience and performance of the joint venture itself and of the individual JV members may be submitted and will be evaluated in accordance with the solicitation. The proposal should identify the JV member that performed each cited project, describe that member's role and responsibilities, and explain the relevance of that experience to the work the member is proposed to perform under this contract.

For purposes of Section H, Special Requirement 2, on-site work performed directly by the joint venture through either of its JV members will be considered work performed by the prime Contractor toward the 15 percent self-performance requirement. Work performed by subcontractors to the joint venture or to its individual members does not count as prime-contractor self-performance.

Equipment warranties with proposal

46 00 00, 3.6.A; Solicitation L

Section 46 00 00 requires equipment warranties as part of the bid submittal package. Please confirm which equipment warranties must accompany the proposal, whether supplier standard warranty documents are sufficient, and where these documents should be included within the prescribed proposal volumes/page limits.

Section 46 00 00 applies to the water-treatment equipment identified in that section, including the associated pumping equipment. The intent of Paragraph 3.6 is to establish the minimum warranty requirements applicable to the equipment furnished under the Contract. Warranty documentation is not required with the offeror’s proposal. Prior to approval of the applicable equipment submittal, the Contractor shall provide manufacturer/supplier warranty documentation demonstrating that the proposed equipment complies with the warranty requirements of Section 46 00 00, Paragraph 3.6. Manufacturer or supplier standard warranty documentation is acceptable provided it demonstrates compliance with the specified requirements. Where the standard warranty does not expressly satisfy all requirements of Paragraph 3.6, supplemental documentation shall be provided confirming compliance. Final approved warranties shall also be included in the applicable Operation and Maintenance documentation in accordance with the Contract requirements.

Proposal deadline/time zone

Solicitation SF1442, Blocks 7-8 and 13.a (p.1); L.C-D (p.52)

SF1442 Block 13.a establishes the proposal deadline as October 23, 2026 at 1600 local time. Block 7 identifies the issuing office in Denver, Colorado; Block 8 refers offerors to Section L, which requires submission by email. The project is located in Hawaii. Please confirm whether the deadline is 1600 Denver local time (Mountain Daylight Time) or 1600 Hawaii local time (Hawaii Standard Time), and state the governing time zone explicitly in an amendment.

NPS Response: The proposal submission deadline is to be submitted by local Hawaii Standard Time (HST).

AIS/BABA/domestic sourcing

Solicitation I, FAR 52.225-11 (pp.24-28); L, FAR 52.225-12 (p.48)

The solicitation incorporates FAR 52.225-11, Buy American - Construction Materials Under Trade Agreements, and FAR 52.225-12. Please confirm whether any separate American Iron and Steel (AIS) requirements or Build America, Buy America requirements apply to this project in addition to the cited FAR provisions. If so, identify the controlling contract/funding provision, covered products, required manufacturer certifications, and applicable exemptions or waivers. If no additional requirements apply, please confirm the cited FAR provisions govern domestic sourcing.

The solicitation incorporates FAR 52.225‑11, Buy American—Construction Materials Under Trade Agreements, and FAR 52.225‑12, Notice of Buy American Requirement—Construction Materials Under Trade Agreements. These clauses constitute the sole domestic preference requirements for this project.

HDPE substitution

33 40 00 - Storm Drainage, 2.1.A.1 (33 40 00-1)

Section 33 40 00, paragraph 2.1.A.1 requires PE4710 HDPE meeting ANSI/AWWA C906, ASTM F714, and ASTM D3035, with ductile iron pipe size (DIPS) DR21. A supplier reports that the specified DIPS pipe is unavailable for the small project quantities and proposes 36-inch IPS DR17 and 10-inch IPS DR17 as alternatives. Please confirm whether these sizes and dimension ratio are acceptable for the corresponding rainwater collection pipe runs, subject to compliance with the specified resin and applicable standards. Please identify any required revisions to nominal sizes, hydraulic capacity, connection details, fittings/adapters, collection-box penetrations, and supports. This request concerns the solid-wall DIPS HDPE specified in Section 33 40 00 and does not propose substitution of the separate corrugated HDPE catchment piping.

8" HDPE and 30" HDPE pipe covered in Section 33 40 00, paragraph 2.1.A.1 can be ASTM D3350, AASHTO M294. Profile wall – Type S, 2 ft minimum burial depth, 10 ft maximum burial depth, bell and spigot joint with water-tight, non-cleating, O-ring gasket, ASTM F477.

QC Supervisor conflicting requirements

Section 01 40 00, Quality Requirements, paragraphs 1.5.B.1–3 (page 01 40 00-4)

Paragraph 1.5.B.1 permits the Contractor’s Quality Control Supervisor to perform other duties, while paragraph 1.5.B.2 requires the same individual to be assigned no other duties. Please clarify which requirement governs. May the Quality Control Supervisor hold another project role, provided the required QC responsibilities and on-site presence are maintained, or must this individual be dedicated exclusively to quality control? Please revise the conflicting provisions accordingly.

Paragraph 1.5.B.2 governs. The Quality Control Supervisor shall be dedicated to the quality-control function and shall not simultaneously serve in another primary project role, including Project Manager, Superintendent, or SSHO. Paragraph 1.5.B.1 will be revised to eliminate the conflicting language.

Reuse of concrete/asphalt

Section 01 74 19, Construction Waste Management and Disposal, paragraphs 1.3.B and 1.4.B, and attached worksheet identifying the 60% diversion goal; Section 31 20 00, Earth Moving, paragraph 2.2.

To support the project’s waste diversion goal, will the Park permit concrete and asphalt generated by project demolition to be processed and reused on site as crushed concrete aggregate or asphalt millings, or stockpiled off site for Park maintenance personnel to use elsewhere? Reinforcing steel will be removed from the concrete and segregated for recycling.

Please identify acceptable uses, approved stockpile locations, and any required processing, gradation, testing, or environmental acceptance criteria. For material retained for future Park use, please clarify responsibility for hauling, stockpile management, and acceptance. Please also confirm whether either approach will count toward the project’s waste diversion goal and identify the documentation required to receive that credit.

The park does not want concrete aggregate or asphalt millings. Concrete aggregate can be used for construction purposes, as applicable and appropriate, however, all extra material must be removed from the park and disposed of legally. Asphalt millings cannot be reused unless directly under location where asphalt will be placed. It cannot be used for shouldering.

Past-performance questionnaires Solicitation Section M.B.3, Past Performance Evaluation (page 59); Section L, Volume I, Factor 2 – Past Performance (page 57); Section L, Volume II, General References (page 58); Attachment 12, General References.

Section M.B.3 states that past performance will be evaluated using survey responses, CPARS data, and other relevant information. However, no project-specific past performance questionnaire or survey form appears to be included in the solicitation attachments. The provided General References form is identified in Section L as supporting the responsibility determination. Please confirm whether offerors must distribute or submit past performance questionnaires, or whether the Government will independently contact project references identified in the proposal. If questionnaires are required, please provide the form and instructions identifying who submits completed responses, the submission method, and the deadline.

The language in Section M.B.3 referencing the use of past performance survey responses was included inadvertently and does not apply to this solicitation. In accordance with our updated internal policy, the Government is not utilizing, reviewing, or completing any past performance questionnaires or surveys for this requirement. For that reason, no project‑specific past performance questionnaire was included in the solicitation package. Offerors are not required to distribute or submit past performance questionnaires. The Government will evaluate past performance using CPARS data and any other information that is readily available to the Government through existing sources. The General References form identified in Section L applies only to the responsibility determination and does not serve as a past performance survey instrument.

Utility coordination/allowance

Section 01 73 40, paragraphs 3.2.A.1 and 3.2.A.4;

Section 01 31 00, paragraphs 1.9.C.1–2; Section 01 27 00, paragraph 1.1.C.

The specifications assign Hawaiian Electric and Hawaiian Telcom service coordination to the contractor and require the contractor to carry all utility fees and charges associated with service upgrades. Based on experience during previous project phases, these utilities require the account holder/ratepayer to initiate service requests. The contractor has no direct contractual relationship with the utilities and cannot independently obtain binding commitments for scope, pricing, or service dates. Utility charges were therefore addressed through an allowance in previous phases.

Please confirm that NPS will initiate the required service requests as the account holder and authorize contractor coordination thereafter. Please also establish a common allowance for utility-company charges for proposal pricing, identify the costs covered by that allowance, and specify how actual charges above or below the allowance will be reconciled. If an allowance will not be provided, please furnish the utility-approved scope and binding pricing commitments on which offerors are to base their lump-sum proposals.

The existing Building 43 electrical service shall remain a 1-phase, 200-amp overhead service. The Project does not increase the service size or change the existing voltage or phase.

The Contractor shall replace the existing meter base and…

This is the start of the file's text. The full file is on GovTribe.