B09_Att_(26)_Supplemental-Technical-Addendum_02_0004.xlsx
XLSX spreadsheet 17 KB Posted
- Solicitation number
- 140P2026R0091
About this file
This is a Supplemental Technical Addendum (Amendment 0004) to Solicitation 140P2026R0091 for the HAVO 326181 Rehabilitate Rainshed & Water Treatment System project located at Hawaii Volcanoes National Park, Volcano, Hawaii. The amendment clarifies requirements for temporary storage containers and Government relocation coordination in Section 01 50 00 (Temporary Facilities and Controls) as referenced in drawings G11 and G12.
The revised contract direction establishes that the Contractor must treat procurement, delivery, placement, and utility connections for twelve (12) temporary storage containers as an early preconstruction activity with priority following Notice to Proceed. The National Park Service (NPS) retains responsibility for inventorying, packing, relocating, organizing, and returning its owned contents from Buildings 43 and 241. The amendment specifies that the Contractor shall assume up to eight (8) weeks for Government relocation upon acceptance and availability of the temporary storage containers, with this period intended to occur concurrently with preconstruction activities and other work not requiring area turnover. The Contractor must sequence work to minimize impacts from Government relocation, and demolition or other work requiring cleared areas shall not commence until the Contracting Officer confirms area availability. The amendment supersedes the prior Government relocation duration stated in RFI 102 from Amendment 0003 and clarifies that Offerors should not rely on separate Government moving services to reduce the stated eight-week planning duration.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Supplemental Addendum
| HAVO 326181 – AMENDMENT 0004 – SUPPLEMENTAL TECHNICAL ADDENDUM |
| Solicitation 140P2026R0091 | Rehabilitate Rainshed & Water Treatment System |
| Item No. | Document Type | Sheet No. / Spec Section | Sheet / Section Title | Location / Reference | Change Type | Original Text / Condition | Revised Text / Direction | Reason / Source | Accompanying Attachment |
| 54 | Specifications / Drawings | 01 50 00 / G11 / G12 | Temporary Facilities and Controls; Staging & Access | Section 01 50 00 – Temporary Storage Containers; G11 Note 5; G12 Detail 2 | Revise / Clarify | Contract Documents require twelve (12) temporary storage containers for NPS use and coordination of container installation/removal, but do not establish early preconstruction priority for container availability or the revised Government relocation planning duration for Building 43 contents. | Clarify temporary storage and NPS relocation coordination as follows: The Contractor shall treat procurement, delivery, placement, and required utility connections for the twelve (12) temporary storage containers as an **early preconstruction activity** and shall prioritize this work following Notice to Proceed. |
NPS will remain responsible for inventorying, packing, relocating, organizing, and returning NPS-owned stored contents located under Buildings 43 and 241.
Upon Government acceptance and availability of the temporary storage containers, assume for proposal and scheduling purposes that Government relocation may require **up to eight (8) weeks**. The relocation period is intended to occur concurrently with Contractor preconstruction activities and other Work that does not require turnover of the affected areas.
The Contractor shall sequence the Work to minimize impacts associated with Government relocation. Demolition or other Work requiring cleared areas beneath Buildings 43 and 241 shall not commence until the Contracting Officer confirms the applicable area is available to the Contractor.
The Government may utilize separate moving services to assist with and potentially expedite relocation; Offerors shall not rely on such services to reduce the stated eight-week planning duration.
This clarification supersedes the prior Government relocation duration stated in RFI 102 under Amendment 0003. Revised RFI 102 / Government Coordination No