W91364-18-B-5000 Renovate Hangar 885 Rickenbacker ANGB, Columbus OH
July 10, 2018
RFI 005- Please provide As-Built drawings for existing building.
Answer: The hanger underwent a large scale renovation in 1981. Those drawings are included which show how the additions were constructed.
These drawings do not show the thickness of the existing concrete floors in the building. The concrete floor thickness throughout the building is 14 inches thick.
Following drawings/documents are attached:
885S_1981Reno 885S_1953 885H_1981Reno 885F_1981Reno 885E_1981Reno 885A_1981Reno