Amendment 0008 Attachment.pdf
PDF 3 MB Posted
- Attached to
- Cape Cod Canal, Buzzards Bay, MA ? Painting and Steel Repairs, Vertical Lift Railroad Bridge
- Solicitation number
- W912WJ25B0001
About this file
Amendment 0008 Attachment is a supplemental document related to a U.S. Army Corps of Engineers solicitation for painting and steel repairs on the Vertical Lift Railroad Bridge at Cape Cod Canal. The project involves comprehensive surface preparation and painting of the entire bridge structure, including blast cleaning all metalwork to bare metal and applying a three-coat high-performance paint system. Additionally, limited steel repairs will be required at the towers and center span, with strict requirements to maintain the bridge's operational balance and functionality.
The solicitation (W912WJ25B0001) is an unrestricted contract with an estimated value between $10-25 million and a performance period of approximately 545 days. Critical operational constraints include maintaining an open navigation channel, accommodating daily railroad operations for Mass Coastal Railroad and MBTA passenger services, and requiring extensive coordination with marine traffic controllers. The project involves a 1935-constructed three-span steel truss bridge with a 544-foot main lift span and 136-foot vertical clearance, located in Buzzards Bay, Massachusetts, with NAICS code 238320.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Abstract.pdf | ||
| Amendment 0008.pdf | ||
| Specifications - Amendment 0008.pdf | ||
| Amendment 0007.pdf | ||
| Specifications - Amendment 0006.pdf | ||
| Amendment 0006.pdf | ||
| Amendment 0005.pdf | ||
| Amendment 0004.pdf | ||
| Amendment 0003.pdf | ||
| USCG Bridge Lighting Regulations.pdf | ||
| Amendment 0002.pdf | ||
| Amendment 0001.pdf | ||
| 1935-ERECTION-PLAN.pdf | ||
| SHOP_DRAWINGS-1_TO_50.pdf | ||
| 2022 Routine Inspection Report.pdf | ||
| SHOP_DRAWINGS-51_TO_100.pdf | ||
| Record Drawing Index.docx | DOCX document | |
| 1934-ORIGINAL-COE-DESIGN-DRAWINGS.pdf | ||
| 1934-OPERATING-MACHINERY-SHOP-DRAWINGS.pdf | ||
| SHOP_DRAWINGS-102_TO_154.pdf | ||
| 2022 Routine Inspection ME Final Report.pdf | ||
| 1936-OPER-HOUSE.pdf | ||
| Drawing Index.xlsx | XLSX spreadsheet |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CCC-133_S-903-rev1
| CCC-133_S-101-rev1 |
| Amendment 0008 Attachment |
File details come from the government source that posted it. Updated .