Amendment 0002.pdf
PDF 590 KB Posted
- Attached to
- Cape Cod Canal, Buzzards Bay, MA ? Painting and Steel Repairs, Vertical Lift Railroad Bridge
- Solicitation number
- W912WJ25B0001
About this file
This is Amendment 0002 to solicitation W912WJ25B0001, providing responses to seven contractor questions regarding a bridge painting and repair project. The amendment, issued by the U.S. Army Corps of Engineers New England District on January 17, 2025, does not extend the proposal due date.
Key clarifications include: contractors may propose platforms spanning the entire bridge length if they can demonstrate no impact to wind loading and train travel in their Containment and Span Balance Plan; regreasing is not required after daily cleaning; interior spaces of front tower leg columns do not require painting; navigation light visibility must be maintained through clear plastic windows or adjusted containment; contractors must follow state VOC regulations; drawings are available on both SAM.gov and PIEE; and blast abrasives must comply with SSPC-AB 2 standards with oil content testing required once per containment. The original scope, terms, and conditions remain unchanged except for these clarifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Abstract.pdf | ||
| Amendment 0008.pdf | ||
| Amendment 0008 Attachment.pdf | ||
| Specifications - Amendment 0008.pdf | ||
| Amendment 0007.pdf | ||
| Specifications - Amendment 0006.pdf | ||
| Amendment 0006.pdf | ||
| Amendment 0005.pdf | ||
| Amendment 0004.pdf | ||
| Amendment 0003.pdf | ||
| USCG Bridge Lighting Regulations.pdf | ||
| Amendment 0001.pdf | ||
| 1935-ERECTION-PLAN.pdf | ||
| SHOP_DRAWINGS-1_TO_50.pdf | ||
| 2022 Routine Inspection Report.pdf | ||
| SHOP_DRAWINGS-51_TO_100.pdf | ||
| Record Drawing Index.docx | DOCX document | |
| 1934-ORIGINAL-COE-DESIGN-DRAWINGS.pdf | ||
| 1934-OPERATING-MACHINERY-SHOP-DRAWINGS.pdf | ||
| SHOP_DRAWINGS-102_TO_154.pdf | ||
| 2022 Routine Inspection ME Final Report.pdf | ||
| 1936-OPER-HOUSE.pdf | ||
| Drawing Index.xlsx | XLSX spreadsheet |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This amendment provides responses to requests for information (RFIs). All other aspects remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 17-Jan-2025
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ25B0001
X 9B. DATED (SEE ITEM 11)
10-Dec-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
17-Jan-2025
CODE
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912WJ25B0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0002
1. The specifications state that the Contractor can only work on 3 bays at a time, and equipment needs to be removed to allow unimpeded train travel at the end of the workday. Would the Contractor be allowed to install a platform below the bridge deck that spans the entire length of the bridge?
Separately, would the Contractor be allowed to install a platform that hangs from the top of the center span that stretches across the entire length?
GOV Response: The government’s restrictions are related to wind loading and ensuring train travel is not impacted. Additionally, there are vertical limitations both below and above the bridge deck related to train and marine vessel traffic. If the Contractor can demonstrate that these items are not impacted in their Containment and Span Balance Plan, which will be reviewed and approved by the Government, the Government is willing to consider both of these staging approaches.
2. The specifications state that the Contractor needs to clean the surfaces to be painted, which require removal of existing grease. Does the Contractor need to regrease these areas at the close of each workday?
GOV Response: No, the contractor is not required to regrease these areas.
3. Do we need to paint the interior space on the front tower “leg” columns, which support the counterweight rails?
GOV Response: No
4. It appears there are navigation lights on the bridge. Does the Contractor need to maintain access and visibility to these aids, or does the Government have other means of providing navigational aid on the bridge to support traveling marine vessels.
GOV Response: The Contractor must ensure that their containment does not obstruct visibility of navigation aids in their current state. If necessary, the Contractor may use clear plastic window or adjust the containment to avoid blocking lights. If navigation aids are obstructed, the Contractor must provide equivalent or better aids outside the containment per "USCG Bridge Lighting and Other Lighting Regulations 33 CFR 118.65." Refer to Specification Section 09 97 02, Paragraph 1.3.3.2 which states, ‘The plan shall address procedures to maintain visibility of safety lighting for both navigation and aviation interests.’ For additional information related to the USCG requirements for bridge lighting and other signals, please refer to the USCG Bridge Lighting Regulations.
5. Is there a maximum VOC limitation on the coating?
GOV Response: The Contractor is required to follow State Regulations regarding VOC limitations for paint products. Refer to Spec Section 09 97 02 subpart 2.2.
W912WJ25B0001
6. Just to confirm, the specifications state: "See Spec Section 01 11 00 paragraph 1.2 Existing Record
Drawings". Are these the same drawings on the PIEE Solicitation module link?” (the drawings on the PIEE link are attached) GOV Response: There are attachments on Sam.Gov as well as PIEE. PIEE has the Contract Solicitation, Contract Specifications, and Contract Drawings. All other attachments referenced in the specifications, such as the record drawings, can be found on the Sam.Gov posting.
7. Are there any inspection or test requirements for blast abrasives?
GOV Response: Blast abrasives shall comply with SSPC-AB 2, Abrasive Standard No. 2. Cleanliness of Recycled Ferrous Metallic Abrasives. Specifically, a single random sample of the abrasive work mix shall be tested for oil content in accordance with ASTM D7393. The test shall be performed once per containment.
(End of Summary of Changes)
File details come from the government source that posted it. Updated .