01731-00-Cutting_ _Patching.DOC

DOC document 38 KB Posted

Attached to
Award to Chance Construction on 22 Aug 09
Solicitation number
W912L109R0038
Issued by

About this file

CUTTING AND PATCHING

View the file

Other files

File Type Posted
QUESTIONS AND ANSWERS LA PORTE as of 21 JUL 09.doc DOC document
QUESTIONS AND ANSWERS LA PORTE AS OF 20 JUL 09.doc DOC document
QUESTIONS AND ANSWERS as of 8 Jul 09.doc DOC document
QUESTIONS AND ANSWERS as of 7 Jul 09.doc DOC document
QUESTIONS AND ANSWERS as of 6 JUL 09.doc DOC document
Addendum 2 Dimensioned Floor Plans 20090701.pdf PDF
QUESTIONS AND ANSWERS LA PORTE AS OF 29 JUN 09 —
9- Exhibit C 12-05.doc DOC document
Exhibit D-E-F Jan 08.doc DOC document
8 -Exhibit B 1205.doc DOC document
QUESTIONS AND ANSWERS as of 1 JUL 09.doc DOC document
08110-Steel Doors Frames.DOC DOC document
09651 - Resilient Tile Flooring and Accesories.DOC DOC document
ATTENDANCE ROSTER.pdf PDF
PREPROPOSAL MEETING MINUTES - LA PORTE FACILITIES.doc DOC document
PHOTOS.doc DOC document
Hurricane IKE B 1359 Drawings 20090506.pdf PDF
09512-Accoustical Ceiling.doc DOC document
09680 - Carpet.DOC DOC document
07210-Building Insulation.DOC DOC document
01001-00-General_Requirements.doc DOC document
01019-00-Contract_Considerations.DOC DOC document
AF Form 3052 Construction Cost Estimate Breakdown.xls XLS spreadsheet
Form WH-347-Wage report Form-BlanK.xls XLS spreadsheet
07620-Sheet Metal Flashing and Trim.DOC DOC document
01420-00-Environmental_Protection.doc DOC document
01700-00-Contract_Closeout.DOC DOC document
01300-00-Submittals 20090302.doc DOC document
09900 - Painting.doc DOC document
07591-Preparation for Reroofing 20090227 .doc DOC document
Contractor_Security_Policy_Letter.doc DOC document
Form 3065-Contract Progress Report.xls XLS spreadsheet
07550-Modified Bitumin Roofing 20090226.doc DOC document
Form 3064- Progress Schedule.xls XLS spreadsheet
09255-Gypsum Board Assemblies.DOC DOC document
07560-Cold Coal Tar Modified 20090227.doc DOC document
01105-00-Haz_Mat_Procedures.doc DOC document
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Copyright 1998, The American Institute of Architects (AIA)

SECTION 01731 - CUTTING AND PATCHING

This Section uses the term "Architect." Change this term to match that used to identify the design professional as defined in the General and Supplementary Conditions.

Verify that Section titles referenced in this Section are correct for this Project's Specifications; Section titles may have changed.

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes procedural requirements for cutting and patching.

B. Related Sections include the following:

List below only procedures that the reader might expect to find in this Section but are specified elsewhere.

Delete first subparagraph below if alterations are not required and Division 1 "Selective Demolition" Section is not used.

1. Division 1 Section "Selective Demolition" for demolition of selected portions of the building for alterations.

Subparagraph below is appropriate to items in many other Sections. See Evaluations.

2. Divisions 2 through 16 Sections for specific requirements and limitations applicable to cutting and patching individual parts of the Work.

Delete below if special cutting and patching requirements by mechanical and electrical trades are not required.

a. Requirements in this Section apply to mechanical and electrical installations. Refer to Divisions 15 and 16 Sections for other requirements and limitations applicable to cutting and patching mechanical and electrical installations.

1.3 DEFINITIONS

A. Cutting: Removal of existing construction necessary to permit installation or performance of other Work.

B. Patching: Fitting and repair work required to restore surfaces to original conditions after installation of other Work.

1.4 SUBMITTALS

Delete this Article if not required. Revise paragraph and subparagraphs below to include other submittal requirements. See Evaluations.

A. Cutting and Patching Proposal: Submit a proposal describing procedures at least 10 days before the time cutting and patching will be performed, requesting approval to proceed. Include the following information:

1. Extent: Describe cutting and patching, show how they will be performed, and indicate why they cannot be avoided.

2. Changes to Existing Construction: Describe anticipated results. Include changes to structural elements and operating components as well as changes in building's appearance and other significant visual elements.

3. Products: List products to be used and firms or entities that will perform the Work.

4. Dates: Indicate when cutting and patching will be performed.

Delete subparagraph below if utilities are not affected by cutting and patching. Expand to include special requirements to suit Project.

5. Utilities: List utilities that cutting and patching procedures will disturb or affect. List utilities that will be relocated and those that will be temporarily out of service. Indicate how long service will be disrupted.

First subparagraph below shifts responsibility for cutting and patching structural work from Architect to Contractor. Revise to suit Project and local regulations. Be careful not to violate state laws or public policy, which may require Structural Engineer to take responsibility.

6. Structural Elements: Where cutting and patching involve adding reinforcement to structural elements, submit details and engineering calculations showing integration of reinforcement with original structure.

7. Contracting Officer’s Approval: Obtain approval of cutting and patching proposal before cutting and patching. Approval does not waive right to later require removal and replacement of unsatisfactory work.

1.5 QUALITY ASSURANCE

This Article contains requirements that expand provisions contained in AIA Document A201.

A. Structural Elements: Do not cut and patch structural elements in a manner that could change their load-carrying capacity or load-deflection ratio.

B. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as intended or that results in increased maintenance or decreased operational life or safety, unless otherwise indicated.

List below is an example only. Revise to suit Project's operating systems. With advice of counsel, delete below if Architect's approval is not required. If list is deleted, delete optional text in paragraph above.

1. Primary operational systems and equipment.

2. Air or smoke barriers.

3. Fire-protection systems.

4. Control systems.

5. Communication systems.

6. Conveying systems.

7. Electrical wiring systems.

8. Operating systems of special construction in Division 13 Sections.

Normally delete below. Revise if cutting and patching are extensive or if careful coordination between several trades is necessary to avoid conflicts.

C. Cutting and Patching Conference: Before proceeding, meet at Project site with parties involved in cutting and patching, including mechanical and electrical trades. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding.

1.6 WARRANTY

Delete this Article if no warranties exist that would be affected.

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during cutting and patching operations, by methods and with materials so as not to void existing warranties, where applicable.

PART 2 - PRODUCTS

2.1 MATERIALS

A. General: Comply with requirements specified in other Sections of these Specifications.

B. Existing Materials: Use materials identical to existing materials. For exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible.

1. If identical materials are unavailable or cannot be used, use materials that, when installed, will match the visual and functional performance of existing materials.

Insert specific material requirements here if not specified elsewhere. Material and installation requirements are better specified in individual Sections. See Evaluations.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine surfaces to be cut and patched and conditions under which cutting and patching are to be performed.

1. Compatibility: Before patching, verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers.

2. Proceed with installation only after unsafe or unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Temporary Support: Provide temporary support of Work to be cut.

B. Protection: Protect existing construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.

C. Adjoining Areas: Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.

Retain below where Owner continues to occupy other portions of an existing facility.

D. Existing Services: Where existing services are required to be removed, relocated, or abandoned, bypass such services before cutting to minimize interruption of services to occupied areas.

3.3 PERFORMANCE

A. General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay.

1. Cut existing construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.

B. Cutting: Cut existing construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations.

1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots as small as possible, neatly to size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.

2. Existing Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces.

3. Concrete or Masonry: Cut using a cutting machine, such as an abrasive saw or a diamond-core drill.

4. Excavating and Backfilling: Comply with requirements in applicable Division 2 Sections where required by cutting and patching operations.

Coordinate subparagraph below with Divisions 15 and 16 to avoid duplication or conflicts. If retaining, revise to suit Project.

5. Mechanical and Electrical Services: Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after cutting.

Retain subparagraph below if required to prevent multiple cutting and patching in the same area. Add specific requirements for multiple contracts and special conditions requiring coordination.

6. Proceed with patching after construction operations requiring cutting are complete.

C. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other Work. Patch with durable seams that are as invisible as possible. Provide materials and comply with installation requirements specified in other Sections of these Specifications.

1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate integrity of installation.

2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.

Insert specific refinishing requirements for floors, walls, and ceilings. Revise subparagraph and associated subparagraph below to suit Project.

3. Floors and Walls: Where walls or partitions that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish, color, texture, and appearance. Remove existing floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.

a. Where patching occurs in a painted surface, apply primer and intermediate paint coats over the patch and apply final paint coat over entire unbroken surface containing the patch. Provide additional coats until patch blends with adjacent surfaces.

Delete or revise first subparagraph below to suit Project.

4. Ceilings: Patch, repair, or rehang existing ceilings as necessary to provide an even-plane surface of uniform appearance.

5. Exterior Building Enclosure: Patch components in a manner that restores enclosure to a weathertight condition.

Insert specific installation requirements if not specified elsewhere. Specific installation requirements are better specified in individual Sections.

END OF SECTION 01731

CUTTING AND PATCHING

01731 - 1