This pre-solicitation synopsis announces the U.S. Army Corps of Engineers' intent to solicit proposals for multiple indefinite delivery/indefinite quantity energy savings performance contracts totaling $1.5 billion to design, construct, and operate energy savings projects for government installations. The objective is to help meet energy savings goals under the Energy Policy Act of 1992. Common services to be provided by energy service contractors include equipment design, installation, testing, and operations, maintenance, and repair across a wide range of energy savings measures. The planned acquisition includes a 5-year base and 5-year option ordering period and will cover domestic and overseas government locations. At least three of twenty planned fixed-price, performance-based contracts will be set aside for small businesses. Proposals are expected to be solicited approximately 15 days following this pre-solicitation synopsis through solicitation W912DY-12-R-0046.
Section J Attachment 3
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION J, ATTACHMENT 3
Savings
| 1 |
| Baseline MBTU of project |
| 2 |
| Saved MBTU of project |
| 3 |
| Percent of baseline saved |
| 4 |
| Baseline water use of project |
| 5 |
| Saved water use of project |
| 6 |
| Percent of baseline saved |
| 7 |
| Annual Energy savings of project in dollars |
| 8 |
| Annual maintenance savings of project in dollars |
| 9 |
| Was annual M&V required? |
| 10 |
| Were payments based on guaranteed savings? |
| 11 |
| Total annual maintenance cost in dollars |
Financial
| 1 |
| Construction price |
| 2 |
| Identify total ECM price |
| 3 |
| Identify total project development and direct costs |
| 4 |
| Financed price |
| 5 |
| Financier |
| 6 |
| Financier POC, name, location, Phone number |
| 7 |
| Identify firm that provided the design and engineering |
| 8 |
| Identify firm providing the maintenance |
| 9 |
| identify it ECM's were competitively bid |
Other
| 1 |
| Number of years Prime Contractor has been performing energy projects |
| 2 |
| Number of years Prime Contractor has been performing Third Party Financed energy projects |
| 3 |
| Any other information |
Project Number ___ Data Sheet
Basic Information
| 1 |
| Project title |
| 2 |
| Project location |
| 3 |
| Primary function and size of the facility |
| 4 |
| Type project |
| DOD, Gov, Private |
| 5 |
| Technologies that were implemented |
Contractual
| 1 |
| Contract number / Task Order number |
| 2 |
| TO award date |
Planned construction complete date
| 4 |
| Actual construction complete date |
| 5 |
| Planned duration of maintenance support |
| 6 |
| Term of contract |
| 7 |
| Identify uncontrollable problems |
Implementation
| 1 |
| Percentage of work self performed |
| 2 |
| Percentage of work subcontracted to large business |
| 3 |
| Percentage of work to small business |
| 4 |
| Maintenance performance contractor |
| 5 |
| Customer POC, name, address, phone number |
File details come from the government source that posted it. Updated .