This pre-solicitation synopsis and attachment describe requirements for energy savings performance contracts to be awarded by the U.S. Army Corps of Engineers. The Corps intends to solicit proposals and award multiple indefinite delivery/indefinite quantity contracts with a total programmatic capacity of $1.5 billion. Common services to be provided by energy services contractors include equipment and system design, installation, testing, and operations and maintenance. Energy savings project task order scopes may include improvements to boiler and chiller plants, building automation systems, HVAC equipment, lighting, building envelopes, distribution systems, motors, refrigeration, distributed power generation, and renewable energy. The geographic scope covers the continental U.S., Alaska, Hawaii, and overseas locations in Germany and Korea. The Corps plans to award 20 firm fixed-price, performance-based contracts for ordering periods of 5-year base and option terms, setting aside at least three for small businesses. Proposed markups for implementation, performance periods, and interest rates must be provided in the specified attachment spreadsheet.
Section J Attachment 18
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION J, ATTACHMENT 18
MARKUPS FOR PROPOSAL SUBMISSION
The purpose of the markup submittal spreadsheet at Section J, Attachment 17 is to establish the maximum mark-up percentages that may be applied to the appropriate Task Order category, listed below, over the term of the contract.
Maximum Implementation Mark-up The Prime Contractor shall propose a maximum mark-up to be applied as identified in section C of the RFP for the implementation costs of the project. Mark-up rate if for all technologies and is not requested as technology specific. Rate shall be entered in the spreadsheet contained in Section J, Attachment 17, provided as part of the Price Factor for evaluation, and a working electronic copy of the Excel spreadsheet shall also be provided with the submission of the Prime Contractor’s proposal.
Maximum Performance Period Mark-up The Prime Contractor shall propose a maximum mark-up to be applied as identified in section C of the RFP for the Performance Period costs of the project. Rate shall be entered in the spreadsheet contained in Section J, Attachment 17, provided as part of the Price Factor evaluation, and a working electronic copy of the Excel spreadsheet shall also be provided with the submission of the Prime Contractor’s proposal.
Maximum Interest Rate Mark-up This mark-up is the maximum, fixed, annual percentage rate that, when added to the treasury bill/ treasury constant maturity 10 year interest rate, will be the total percentage finance charge (not including finance processing fees) that the contractor will charge the Government as a total finance charge for all ECMs (sometimes referred to as the interest rate spread). The treasury rate in effect at the time of an ECM task order award will be used and the rate shall be for the time period of ECM amortization. The maximum interest rate mark-up shall be notated in the spreadsheet in Section J, Attachment 17, and a working copy of the Excel spreadsheet shall also be provided with the submission of the Prime Contractor’s proposal. This interest rate mark-up or spread shall only be the amount added to the treasury rate and not the addition of the mark-up and the treasury rate.