This document provides an amendment to a solicitation for the renovation and repair of Building 20 at the Watervliet Arsenal in New York. Key details include:

  • The scope of work involves hazardous material removal, window, siding and door replacement, restroom and locker room renovations and accessibility upgrades, office renovations and associated HVAC and lighting work, entrance replacement including ramps and vestibules, and exterior masonry repairs.

  • The estimated construction cost is between $10-25 million.

  • The award date is projected for September 2022.

  • The solicitation number is W912DS22B0025.

  • The agency is the Department of the Army Corps of Engineers Engineering District New York.

  • The amendment revises drawings and specifications and provides responses to bidder questions.

View the file

Other files

File Type Posted
Bid Abstract_W912DS22B0025 BLG 20.pdf PDF
ATL No. CD4849E-01-07-20 Rev 1 Burns - Watervliet Ped Bridge.pdf PDF
09 90 00.pdf PDF
ATL No CD4849E-02-07-22 Rev 1 - Burns - Watervliet HVAC Pad.pdf PDF
09 06 00.pdf PDF
RBM Survey Report Watervliet Arsenal NY - Bldg 20 Phase 2 V1 - Final.pdf PDF
Site Visit Sign in Sheet 2022-09-16.pdf PDF
123796 Phase II Final Design - Addendum 003 Project Specifications Binder.pdf PDF
W912DS22B0025 Amend 0006.pdf PDF
WVA Building 20 - Bid Option - Drawing Breakdown.pdf PDF
RBM Survey Report Watervliet Arsenal NY - Bldg 20 V1 - Final w Attachments.pdf PDF
SGH Bridge Crane Steel Inspection Report 052022.pdf PDF
W912DS22B0025 Amend 0005.pdf PDF
Bid bond form SF24-16e.pdf PDF
123796 Arch Addendum002 S and S 3.pdf PDF
123796 Phase II Final Design - Addendum 002 Project Specifications Binder.pdf PDF
123796 Arch Addendum002 S and S 2.pdf PDF
123796 Arch Addendum002 S and S 1.pdf PDF
W912DS22B0025 Amend 0004.pdf PDF
W912DS22B0025 Amend 0003.pdf PDF
Site Visit sign-in Sheet 30-Aug-2022.pdf PDF
123796 Phase II Final Design - Addendum 01 Specification Binder R1-1.pdf PDF
123796_Full Binder_P2_RTA_ADD 001_Revised - V2.pdf PDF
W912DS22B0025 Amend 0002.pdf PDF
W912DS22B0025 Amend 0001.pdf PDF
123796 Phase II 100 percent Final Design Specification Binder - R3.pdf PDF
Pages from 101-125 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 125-156 123796_Full Binder_Phase 2 - V11.pdf PDF
W912DS22B0025.pdf PDF
Pages 26-56 from 123796_Full Binder_Phase 2 100 - V11.pdf PDF
123796 Phase II 100_ Final Design Specification Binder - R3 (1).pdf PDF
Pages from 72-100 123796_Full Binder_Phase 2 100 - V11.pdf PDF
Pages from 257-277 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages 1 to 25 from 123796 Full Binder Phase 2 V11.pdf PDF
Pages from 177-200 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 200-225 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 226-256 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 277-300 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 156-176 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 57-72 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 300-334 123796_Full Binder_Phase 2 - V11.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1. Revise and but not reissue draw ings A-011, AD201, A-425, A-432 and A-701. 2. Revise and reissue specifications sections 09 06 00 and 09 09 00. 3. Revise and but not reissue specifications sections 10 21 13

4. Update w age rates 5. Provide Geotech Reports. 6. Answ er Offerors Questions. Responses to offerors inquiries are provided "for info purposes only" and does not revise solicitation, plans and specif ications.

NOTE: Bidders must acknow ledge receipt of this amendment by the date specif ied in the proposal (or as amended) by one of the follow ing methods: in the space provided on SF1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208)

1. CONTRACT ID CODE PAGE OF PAGES

J 1 46

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 21-Sep-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS22B0025

X 9B. DATED (SEE ITEM 11)

24-Aug-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

21-Sep-2022

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS22B0025

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0007

TO BIDDERS:

The following changes shall be made to the drawings and specifications.

DRAWINGS:

1. The following DRAWINGS have been ADDED:

a. None

2. The following DRAWINGS have been DELETED:

3. The following DRAWINGS have been REVISED and REISSUED:

4. The following DRAWINGS have been REVISED but NOT REISSUED:

a. A-011

• Delete Note “PAINT EXISTING PARTIAL HEIGHT MASONRY WALL

AROUND ENTIRE INTERIOR PERIMETER OF SHOP. HEIGHT VARIES.”

• Delete Note “PAINT EXISTING FULL HEIGHT MASONRY WALL FROM

FLOOR TO UNDERSIDE OF ROOF DECK”

• Change Note “BASE BID: PAINT ALL EXPOSED STEEL COLUMNS

THROUGHOUT SHOP/MANUFACTURING AREA UP TO EXISTING "TAN"

LINE APPROXIMATELY TO 8'-0" HIGH

BID OPTION: PAINT ALL EXPOSED STEEL COLUMNS FULL HEIGHT

FROM TOP OF EXISTING "TAN" LINE TO UNDERSIDE OF EXISTING

ROOF DECK. INCLUDE ELEVATED PORTION OF MASONRY WALL JUST

BELOW THE ROOF DECK APPROXIMATELY 6'-0" HIGH AROUND ENTIRE

INTERIOR PERIMETER OF SHOP.” to read as follows:

“BID OPTION: PAINT ALL MASONRY AND EXPOSED

STRUCTURAL STEEL THROUGHOUT

SHOP/MANUFACTURING AREA FROM FLOOR TO

UNDERSIDE OF EXISTING ROOF DECK.”

• Delete Note “REFURBISH METAL PANEL MASONRY CONNECTOR

WALKWAY BETWEEN B20 AND B35 THAT IS PRIMARILY USED FOR

FORK TRUCKS 1. REPAINT INTERIOR 2. NEW LIGHTING 3. REFURBISH

/REPLACE INTERIOR WALLS/WINDOWS”

b. AD201

• Change MASONRY REPAIR NOTE to read as follows:

• “AREAS SHOWN FOR BRICK AND MORTAR REPAIRS AND

REPOINTING ARE GENERAL MINIMUM RECOMMENDATIONS

BASED ON OBSERVED CONDITIONS. CONTRACTOR TO

EVALUATE, MAKE REPAIR RECOMMENDATIONS TO THE

CONTRACTING OFFICER FOR FURTHER SCOPE EVALUATION

AND FINAL DIRECTION PRIOR TO PROCEEDING WITH WORK.”

c. A-425

• Detail F4 – change “TLP-1” to “TLC-1”

d. A-432

• Details E4, E8, and B4 – change “TLP-1” to “TLC-1”

e. A-701 – ROOM FINISH LEGEND

• Change MATERIAL TLP-1 COLOR to “GREY”

• Add MATERIAL TLP-2 under SOLID SURFACE FABRICATION

• TLP-2 DESCRIPTION must be “PORCELAIN WALL TILE 12” x24” ”

• TLP-2 COLOR must be “ANTHRACITE”

• Add MATERIAL TLC-1 under SOLID SURFACE FABRICATION

• TLC-1 DESCRIPTION must be “CERAMIC WALL TILE 6” x 6” ”

SPECIFICATIONS:

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

a. 10 21 13

3. The following SPECIFICATIONS SECTIONS have been REVISED and REISSUED:

a. 09 06 00

b. 09 90 00

4. The following SPECIFICATIONS have been REVISED but NOT REISSUED:

a. 10 21 13

i. Change paragraph 2.2.5.2.e to read as follows:

• “Refer to Section 09 06 00 paragraph 2.3.7.1”

BIDDER’S QUESTIONS AND GOVERNMENT REPLY:

Questions that may be of general interest to all Bidders and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors “for information only” and do not revise the solicitation, plans or specifications.

Q&A number

Comment Response

48 The specification 10 26 00- Wall and Door Protection calling out for the Corner Guards. Neither specification or drawings provide the corner guard sizes and locations, please specify.

Spec section 10 26 00 has been deleted in its entirety as part of this amendment.

49 The specification 10 21 13- Toilet Compartments calling out for the Stainless Steel partitions with #4 finish. At the same time per the item 2. 3. 7. 1 of the specification 09 06 00- Schedules for Finishes Toilet Partitions shall have the Baked enamel finish. Stainless or painted steel?

Follow 09 06 00 the specification for toilet partition finish. Spec section 10 21 13 paragraph 2.2.5.2 has been revised in this amendment to refer to spec section 09 06 00.

50 Can you confirm what material is to be used at the walls in the bathrooms and backsplashes? The drawings show 12” x 24” tile with no manufacturer or series selected and the spec 09 06 00 read as 6” x 6” tile. These products are very different in price.

Please advise.

Utilize 12x24 wall tile in bathrooms.

For backsplash utilize 6” x 6” tile.

Specification section 09 06 00 has been revised and reissued in this amendment to clarify the tile specifications. Sheets A-425, A-432, A-701 have been revised but not reissued in this amendment to clarify where each type of tile must be used.

51 Masonry Repair Note on 201 calls for a unit price to be submitted for further scope evaluation and repair. Bid Schedule does not address this issue. Please advise.

Reference AD201 & AD202 keynote DA13 for scope of masonry work.

Utilize hatches on these sheets for approx. square foot area of masonry work required. A unit price for the work is not required and has been removed as part of this amendment.

52 What feeds the 3000A busway run? EP701 Substation 3A4 existing 1200A circuit breaker.

What are the “short pieces” of busway on drawings EP201 and

EP203?

These are unnamed busways. See EP704 2 “Unnamed Busway” serving WV12670 and WV12680 respectively.

These are 400A rated busways served from the 3000A main busway that originates from Substation 3A4.

This is busway “SW” shown on EP703. This is a 400A rated busway served from the 3000A main busway that originates from Substation 3A4.

54 We’ll need an idea of what the bus plug amperages and quantities are required for on ALL runs. We’ll quote a mix of different amperages for now to cover quantities, but we do not have all the information needed to quote the actual amperages for all required plugs

Busplug amperages are indicated on the single line diagrams EP701 through EP705. These are marked “D1” through “D8”. See “Disconnect Switch Schedule” on EP604 for associated switch ratings. For disconnect switches without a designation, assume a 30A rating.

Disconnect ratings and whether the disconnect switches were fused or unfused have not been verified.

Contractor to field verify and provide accordingly in field.

55 EP604 shows a busway designation schedule AND disconnect schedule. We presume the NEMA 3R disconnect schedule is also for bus plugs as the same designations are used on many of the busway runs. Is that true? Please note we do not offer bus plugs in NEMA 3R. They would be NEMA 1.

Correct, the disconnect schedule is for the busway disconnect switches (“bus plugs”). Noted on NEMA 1.

On the 3000A run, as shown on 1-lines EP701, 703 and 704…we will quote fusible bus plugs for the feeds shown, and as per spec.

In some cases, it shows an enclosed circuit breaker, but we’ll quote as a fusible bus plug as a bus plug will be required

Confirmed fusible bus plug is acceptable.

57 DC-MDP (Drawing EP705) will be by others. DC-MDP is within the scope of work

58 Clarification needed: Dry Type Transformers: AL or CU windings needed? Spec doesn’t say. Will quote AL unless told otherwise.

Proceed with Cu windings.

59 Clarification needed: Dry Type Transformers: 115 or 80 degree temperature rise needed? Spec mentions both. Will quote 115 unless told otherwise.

Proceed with 115.

60 Clarification needed: Panelboards: AL or CU windings needed?

Spec doesn’t say. Will quote AL unless told otherwise.

Proceed with Cu.

61 Clarification needed: Is 3000A busway run 3P4W and all other busway runs 3P3W?

The 3000A busway runs 3P3W.

62 The Addendum #5 issued Bid Form is calling out for the Manufacturing floor Interior painting & Epoxy floor finishes.

Please clarify if the Manufacturing floor Interior painting includes only “Repaint the Egress Pathways/ floor stripping” or all paintings including columns and walls in the Shop/Manufacturing Area 100A are an Option?

The scope of CLIN item No. 0010 “Manufacturing floor interior painting & epoxy floor finishes” is intended to include all interior painting within manufacturing floor area. This includes all items noted within that area on A-011 including items currently listed as “Base-Bid”. Sheet A-011 has been revised but not reisseud in this amendment.

63 On the drawing A-011 there is a note stated that painting of all exposed steel columns is a Base bid; painting columns full height and 6’ masonry wall below roof deck is an Option. The latest Bid Form doesn’t include this Alternate, does it means that this option doesn’t require anymore?

The bid option noted on A-011 stating the following “PAINT ALL EXPOSED

STEEL COLUMNS FULL HEIGHT

FROM TOP OF EXISTING "TAN"

LINE TO UNDERSIDE OF EXISTING

ROOF DECK. INCLUDE ELEVATED

PORTION OF MASONRY WALL

JUST BELOW THE ROOF DECK

APPROXIMATELY 6'-0" HIGH

AROUND ENTIRE INTERIOR

PERIMETER OF SHOP.” must be priced as part of OPTIONAL CLIN 0010. CLIN 0010 shall also include painting CMU wall below windows at perimeter of manufacturing area, Repaint egress pathway striping, Paint full height CMU wall between manufacturing area and office/administrative/breakroom area (At column line 10), and paint exposed columns throughout manufacturing area from floor to underside of existing roof deck. Sheet A-011 has been revised but not reisseud in this amendment to reflect the above description of the painting option.

64 The Soil Report is missing. Per Geotechnical Information on the drawing S-001 the soil exist, done by Atlantic Testing Laboratories.

Please provide.

Both of the geotechnical investigaton reports for the project have been included in this amendment.

65 The Addendum #5 Bid Form had added Item 11 Option- masonry repair. The Masonry Repair Note on the drawing AD201 reads:

“Areas Shown for Brick and Mortar repairs and repointing are general Minimum Recommendations Based on Observed Conditions. Contractor to evaluate, Make Repair Recommendation and submit UNIT PRICING for the work to the contracting officer for further Scope evaluation and final direction prior proceeding with work. Since the masonry repair’s SCOPE of Work to be determine yet please convert the Item 11 Option into the masonry repair Allowance, please specify the Allowance Amount.

Reference AD201 & AD202 keynote DA13 for scope of masonry work.

Utilize hatches on these sheets for approx. square foot area of masonry work required. A unit price for the work is not required and has been removed as part of this amendment.

Sheet AD201 has been revised but not reissued as part of this amendment.

66 The Item 10 Option of the Bid Form calling out for the Epoxy Floor.

At today’s walkthrough we accidently found out that the existing floor is a wood floor specially designed for the oil and chemical spill absorption. That means that the existing wood floor is fully saturated with the oils and chemicals. The provided Epoxy Floor Speciation 09 67 23.13 is for the flooring over the concrete surface, not over the wood. Please provide a specification designed for epoxy over the wood floor saturated with the oils and chemicals or ADD Option Allowance for the Manufacturing Shop flooring, please specify the Allowance Amount.

Respondents to utilize a Marine Enamel based paint (Safety Yellow) for the wood portions of the manufacturing floor asile striping.

Specification Section 09 90 00 has been revised and reissued in this amendment to provide spec for manufacturing floor striping.

67 The drawing A-011 calling out for “Refurbish Metal Panel Masonry Connector walkway Between B20 and B35:

a. Repaint Interior

b. New Lighting

c. Refurbish/Replace Interior Walls/windows.

From my observation at todays walkthrough this connector doesn’t have the interior walls, Masonry, also doesn’t have any Windows.

The exterior panels are relatively new and in a good shape. Please advise

Scope associated with this work is limited to items shown on drawing A-

433. The referenced note has been deleted. Sheet A-011 has been revised but not reissued in this amendment.

68 There are separate individual Options to install Metal Wall Panels, Translucent Panels and Windows at Manufacturing floor.

a. Does it means that the existing panels and window removals shall be included in the base bid, or it’s means: “Remove existing…. and replace with…”?

b. Since each of them is an option in which of these alternates the steel framing shown on the drawing S-201shall be included?

Including them in the base bid wouldn’t work, for their installation the existing panels shall be removed and then reinstalled or provided new. Including steel in each Option will unreasonable increase the cost. Suggesting creating a separate Option for the Steel work and removal of the existing panels/windows.

a. Demolition of existing metal panels shall be covered in both CLIN 0005 & CLIN 0006 not base bid. The panels are not to be removed unless replaced with either new metal panel (CLIN 0005) or translucent panel system (CLIN 0006). Demolition of existing windows in manufacturing floor area shall be covered in CLIN 0008.

Windows shall not be removed unless new windows are installed as part of

CLIN 0008.

b. New steel shown in details E5/S- 505, E1/S-505 and A1/S-505 shall be priced with both CLIN 0005 & CLIN

0006. New steel shown in details C8/S-505 shall be priced with CLIN 0006. New steel shown in details C1/S-505, C5/S-505, E8/S-505 and E1/S-506 shall be priced with CLIN

69 Can USACE please provide an amperage for the electrical bus plugs as a basis of pricing? Suggest using the basis of pricing and make contractual adjustment after award based on actuals ($+/$-)

Busplug amperages are indicated on the single line diagrams EP701 through EP705. These are marked “D1” through “D8”. See “Disconnect Switch Schedule” on EP604 for associated switch ratings. For disconnect switches without a designation, assume a 30A rating.

Disconnect ratings and whether the disconnect switches were fused or unfused have not been verified.

Contractor to field verify and provide accordingly in field.

70 Can proposals be submitted electronically via email or DoD SAFE?

No, Contractors are required to deliver Bids to 26 Federal Plaza, Room 16- 300 at 02:00 pm Est.

71 Per the RFP, full bid documents are required on one CD-ROM. Since pricing will be received at the last minute and it will be handwritten in on the bid schedules, can the requirement for the CD be removed? If not, can the file with the final pricing be submitted via email or the file on the CD not include pricing?

CD-ROM is optional

72 If bidders do not include a CD with their proposal, will the proposals still be accepted and considered compliant?

Yes, bids will be consider acceptable if CD-ROM is not included.

73 Per the RFP, potential bidders are required to submit the following with their bid:

1. Signed SF1442.

2. Acknowledged amendments.

3. Filled out bid schedule and totals.

4. Bidders must check off box (d) in 52.204-8 Annual

Representations and Certifications (DEC 2019) for being on SAM.gov

1. Signed SF1442.

Response: Yes

2. Acknowledged amendments.

Response: Yes

3. Filled out bid schedule and totals.

Response: Yes

4. Bidders must check off box (d) in 52.204-8 Annual Representations and Certifications (DEC 2019) for being on SAM.gov

Response: Yes

74 Can the completed bid schedule and totals be placed at the end of the document and still be accepted and considered compliant?

1. Signed SF1442.

2. Acknowledged amendments.

3. Bidders must check off box (d) in 52.204-8 Annual Representations and Certifications (DEC 2019) for being on SAM.gov

4. Filled out bid schedule and totals

Yes, it will be accepted.

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following have been added by full text:

UPDATED WAGE RATES 09-19-22

"General Decision Number: NY20220002 08/05/2022

Superseded General Decision Number: NY20210002

State: New York MY 09/19/2022

Construction Types: Building, Heavy and Highway

Counties: Albany, Columbia, Fulton, Greene, Montgomery, Rensselaer, Saratoga, Schenectady, Schoharie and Washington Counties in New York.

BUILDING CONSTRUCTION PROJECTS (For all counties except

COLUMBIA, FULTON, GREENE & MONTGOMERY) (does not include single family homes and apartments up to a including 4 stories), HEAVY

AND HIGHWAY CONSTRUCTION PROJECTS

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).

|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $15.00 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2022. |

|If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $11.25 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2022. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at https://www.dol.gov/agencies/whd/government-contracts.

Modification Number Publication Date

0 01/07/2022 1 02/18/2022 2 02/25/2022 3 05/13/2022 4 05/20/2022 5 07/08/2022 6 07/22/2022 7 08/05/2022

* ASBE0040-002 05/01/2022

Rates Fringes

Asbestos/Insulator Worker SCOPE OF WORK: includes application of all insulating materials, protective, coverings, coating and finishing to all types of mechanical systems.....................$ 38.40 24.42

HAZARDOUS MATERIAL HANDLER

Duties limited to preparation wetting;

stripping; removal;

scrapping; vacuuming;

bagging; and disposing of all insulation materials, whether they contain asbestos or not from mechancial systems..........$ 38.40 24.42

BOIL0197-002 01/01/2021

Rates Fringes

BOILERMAKER......................$ 38.59 26.00

BRNY0002-019 07/01/2018

Rates Fringes

BRICKLAYER

BRICKLAYERS, STONE MASONS,

CEMENT MASONS, PLASTERERS,

POINTERS, CAULKERS &

CLEANERS....................$ 36.19 20.48

HEAVY & HIGHWAY

CONSTRUCTION

CEMENT MASONS..............$ 37.23 19.51

MARBLE, TILE & TERRAZZO

FINISHERS...................$ 27.16 16.85

MARBLE, TILE & TERRAZZO

WORKERS.....................$ 34.66 19.58

CARP0279-006 07/01/2019

Rates Fringes

Carpenters:

HEAVY AND HIGHWAY

CONSTRUCTION (COLUMBIA AND

GREENE COUNTIES)

Carpenters, Millwrights, Pile Drivers...............$ 38.09 29.08

* CARP0291-005 07/01/2022

Rates Fringes

Carpenters:

SARATOGA COUNTY

BUILDING....................$ 34.00 23.18

WASHINGTON COUNTY

BUILDING....................$ 29.00 22.46

PAID HOLIDAYS: Labor Day, provided the employee has been on the payroll the calender week or any of the holiday week preceding the holiday and works the day after the holiday.

* CARP0291-008 07/01/2022

ALBANY, FULTON, MONTGOMERY, RENSSELAER, SCHENECTADY AND

SCHOHARIE COUNTIES

Carpenters:

BUILDING CONSTRUCTION

(Excluding Montgomery County) Carpenters & Soft Floor Layers.....................$ 34.00 23.18 Piledriver.................$ 31.68 20.60

HEAVY & HIGHWAY

CONSTRUCTION

Carpenters.................$ 37.52 23.55

* CARP0291-010 07/01/2022

Rates Fringes

Carpenters:

CARPENTERS..................$ 37.52 23.55

DIVER TENDERS...............$ 34.02 21.10

DIVERS (Dry Day)............$ 38.52 23.55

DIVERS......................$ 62.52 23.55

PILEDRIVERS.................$ 33.02 21.10

* ELEC0236-001 06/01/2022

ALBANY; COLUMBIA; FULTON; GREENE (that portion North of a line following the south limits of the city of Catskill);

MONTGOMERY; RENSSELAER, SARATOGA; SCHENECTADY; SCHOHARIE;

WASHINGTON

ELECTRICIAN......................$ 45.00 30.59

ELEC0363-004 04/01/2022

GREENE COUNTY (Portion of)

Rates Fringes

ELECTRICIAN......................$ 44.00 3%+36.67+a

FOOTNOTE:

a. Paid Holidays: New Year's Day, President's Day, Memorial Day, Fourth of July, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day, Day after Thanksgiving, Christmas Day

ELEC1249-003 05/04/2020

Rates Fringes

ELECTRICIAN (LINE

CONSTRUCTION: LIGHTING AND

TRAFFIC SIGNAL Including any and all Fiber Optic Cable necessary for Traffic Signal Systems, Traffic Monitoring systems and Road Weather information systems) Flagman.....................$ 27.72 6.75%+33.90 Groundman (Truck Driver)....$ 36.96 6.75%+33.90 Groundman Truck Driver (tractor trailer unit)......$ 39.27 6.75%+33.90 Lineman & Technician........$ 46.20 6.75%+33.90 Mechanic....................$ 36.96 6.75%+33.90

FOOTNOTE:

a. New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, plus President's Day, Good Friday, Decoration Day, Election Day for the President of the United States and Election Day for the Governor of the State of New York, provided the employee works the day before or the day after the holiday.

ELEC1249-004 05/03/2021

Rates Fringes

ELECTRICIAN (Line Construction) Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :

Flagman....................$ 32.82 7%+34.40 Groundman digging machine operator...................$ 49.23 7%+34.40 Groundman truck driver (tractor trailer unit).....$ 46.50 7%+34.40 Groundman Truck driver.....$ 43.76 7%+34.40 Lineman and Technician.....$ 54.70 7%+35.40 Mechanic...................$ 43.76 7%+34.40 Substation:

Cable Splicer..............$ 60.17 7%+35.40

Flagman....................$ 32.82 7%+34.40 Ground man truck driver....$ 43.76 7%+34.40 Groundman digging machine operator...................$ 49.23 7%+34.40 Groundman truck driver (tractor trailer unit).....$ 46.50 7%+34.40 Lineman & Technician.......$ 54.70 7%+35.40 Mechanic...................$ 43.76 7%+34.40 Switching structures;

railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation Cable Splicer..............$ 61.62 7%+35.40 Flagman....................$ 33.61 7%+34.40 Groundman Digging Machine Operator...................$ 50.42 7%+34.40 Groundman Truck Driver (tractor-trailer unit).....$ 47.62 7%+34.40 Groundman Truck Driver.....$ 44.82 7%+34.40 Lineman & Technician.......$ 56.02 7%+35.40 Mechanic...................$ 44.82 7%+34.40

FOOTNOTE:

a. PAID HOLIDAYS: New Year's Day, Presidents' Day, Memorial

Day, Good Friday, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, and Election Day for the President of the United States and Election Day for the Governor of New York State, provided the employee works two days before or two days after the holiday.

ELEC1249-007 05/02/2022

COLUMBIA COUNTY

Rates Fringes

ELECTRICIAN (LIGHTING AND

TRAFFIC SIGNAL INCLUDING ANY

AND ALL FIBER OPTIC CABLE

NECESSARY FOR THE TRAFFIC

SIGNAL SYSTEMS, TRAFFIC

MONITORING SYSTEMS AND ROAD

WEATHER INFORMATION SYSTEMS)

Flagman.....................$ 28.91 7%+34.90 Groundman Digging Machine Operator....................$ 43.37 7%+34.90 Groundman Truck Driver (Tractor-trailer unit)......$ 40.96 7%+34.90 Groundman Truck Driver......$ 38.55 7%+34.90 Lineman and Technician......$ 48.19 7%+36.90 Mechanic....................$ 38.55 7%+34.90

PAID HOLIDAYS:

a. Memorial Day, New Year's Day, President's Day, Good Friday, Decoration Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, and Election Day for the President of the United States and Election Day for the Governor of New York State, provided the employee works two days before or two days after the holiday.

ELEC1249-008 01/01/2022

Rates Fringes

ELECTRICIAN (Line Construction)

TELEPHONE, CATV

FIBEROPTICS CABLE AND

EQUIPMENT

Cable splicer..............$ 36.28 3%+5.14 Groundman..................$ 18.25 3%+5.14 Installer Repairman- Teledata Lineman/Technician- Equipment Operator.........$ 34.43 3%+5.14 Tree Trimmer................$ 28.25 3%+10.23

a. New Year's Day, President's Day, Good Friday, Decoration Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, Day after Thanksgiving, Christmas Day.

ELEV0035-001 01/01/2022

ALBANY; COLUMBIA (Towns of Claverack, Hillsdale, Ghent, Stockport, Austerlitz, Canaan, New Lebanon, Chatham, Kinderhook, Styvesant and Greenport); FULTON; GREENE (Towns of Durham, Greenville, New Baltimore, Coxcsackie and Athens);

MONTGOMERY, RENSSELAER, SARATOGA, SCHENECTADY, SCHOHARIE

AND

WASHINGTON COUNTIES

Elevator Constructor.............$ 50.78 36.885+a+b a.Vacation: 6%/under 5 years based on regular hourly rate for all hours worked. 8%/over 5 years based on regular hourly rate for all hours worked.

b. PAID HOLIDAYS: New Year's Day; Memorial Day;

Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.

ELEV0138-004 01/01/2022

COLUMBIA COUNTY (THE TOWNS OF ANCRAM, CLERMONT, COPAKE,

GALLATIN, GERMANTOWN, LIVINGSTON, AND TAGHKANIC); GREEN

COUNTY

(THE TOWNS OF HUNTER AND CATSKILL)

ELEVATOR MECHANIC................$ 64.63 36.885+a+b

FOOTNOTE:

a.Vacation: 6%/under 5 years based on regular hourly rate for all hours worked. 8%/over 5 years based on regular hourly rate for all hours worked.

b. PAID HOLIDAYS: New Year's Day; Memorial Day;

Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.

ENGI0158-008 07/01/2018

BUILDING

EXCLUDING MONTGOMERY COUNTY

POWER EQUIPMENT OPERATOR

GROUP A(1)..................$ 43.79 25.70+a GROUP A.....................$ 43.30 25.70+a 1..........................$ 45.04 25.70+a 2..........................$ 46.04 25.70+a GROUP B.....................$ 42.28 25.70+a GROUP C.....................$ 39.38 25.70+a

Hazardous work - Anytime Operating Engineers are involved with level C or above, $2.50 per hour over regular rate.

FOOTNOTE:

a. Paid Holidays: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day.

POWER EQUIPMENT OPERATOR CLASSIFICATIONS (BUILDING):

GROUP A(1): Crane, hydraulic cranes, tower crane, locomotive crane, piledriver, cableway, derricks, whirlies, dragline, boom truck (over 5 tons)

GROUP A(1): Crane Premiums:

1 over 150'- $1.00 2 over 200'- $2.00

GROUP A: Shovel, All Excavators (including rubber tire full swing), gradalls, power road grader, all CMI equipment, front-end rubber tire loader, tractor-mounted drill (quarry master), mucking machine, concrete central mix plant, concrete pump, Belcrete system, automated asphalt concrete plant and tractor road paver, boom truck (5 tons and under), maintenance engineer, self contained crawler, drill-hydraulic rock drill.

GROUP B: Backhoe, (rubber-tired backhoe/loader combination), bulldozer, pushcat, tractor, traxcavator, scraper, LeTourneau grader, form fine grader, road roller, blacktop roller, blacktop spreader, power brooms, sweepers, trenching machine, Barber Green loader, side booms, hydrohammer, concrete spreader, concrete finishing machine, one drum hoist, power hoisting (single drum), hoist - two drum or more, three drum engine, power hoisting (two drum and over), two drum and swinging engine, three drum swinging engine, hod hoist, A-L frame winches, cord and well drillers (one drum), post hole digger, model CHB Vibro-Tamp or similar machine, batch bin and plant operator, dinkey locomotive, skid steer loader, track excavator 5/8 cu. yd. or smaller

GROUP C: Fork lift, high lift, lull, oiler, fireman and heavy- duty greaser, boilers, and steam generators, pump, vibrator, motor mixer, air compressor, dust collector, welding machine, well point, mechanical heater, generators, temporary light plants, concrete pumps, electric submersible pump 4"" and over, murphy type diesel generator, conveyor, elevators, concrete mixer and belcrete power pack (belcrete system), seeding, and mulching machines, pumps

ENGI0158-026 07/01/2018

HEAVY & HIGHWAY

Rates Fringes

Power equipment operators:

GROUP 1.....................$ 43.47 26.05+a GROUP 2.....................$ 42.56 26.05+a

GROUP 3.....................$ 39.99 26.05+a GROUP 4.....................$ 47.47 26.05+a GROUP 5.....................$ 46.47 26.05+a GROUP 6.....................$ 45.47 26.05+a GROUP 7.....................$ 45.08 26.05+a

POWER EQUIPMENT OPERATOR CLASSIFICATIONS (HEAVY & HIGHWAY):

GROUP 1: Asphalt Curb Machine, Self Propelled, Slipform, Automated Concrete Spreader (CMI Type), Automatic Fine Grader, Backhoe (Except Tractor Mounted, Rubber Tired), Backhoe Excavator Full Swing (CAT 212 or similar type), Back Filling Machine, Belt Placer (CMI Type), Blacktop Plant (Automated), Boom truck , Cableway, Caisson Auger, Central Mix Concrete Plant (Automated), Concrete Curb Machine, Self Propelled, Slipform, Concrete Pump, Crane, Cherry Picker, Derricks (steel erection), Dragline, Overhead Crane (Gantry or Straddle type), Pile Driver, Truck Crane, Directional Drilling Machine, Dredge, Dual Drum Paver, Excavator (All Purpose Hydraulically Operated) (Gradall or Similar), Front End Loader ( 4 cu. yd. and Over), Head Tower (Sauerman or Equal), Hoist (Two or Three Drum), Holland Loader, Maintenance Engineer, Mine Hoist, Mucking Machine or Mole Pavement Breaker(SP) Wertgen; PB-and similar type, Power Grader, Profiler (over 105 H.P.)

Quad 9, Quarry Master (or equivalent), Scraper, Fireman, Form Tamper, Grout Pump, Gunite Machine, Hammers (Hydraulic self-propelled), Hydra-Spiker, ride-on, Hydraulic Pump (jacking system), Hydro-Blaster (Water), Mulching Machine, Oiler, Parapet Concrete or Pavement, Shovel, Side Boom, Slip Form Paver, Tractor Drawn, BeltType Loader, Truck or Trailer Mounted Log , Chipper (Self Feeder), Tug Operator (Manned Rented Equipment Excluded), Tunnel Shovel

GROUP 2: Asphalt Paver, Backhoe (Tractor Mounted, Rubber Tired), Bituminous Recycler Machine, Bituminous Spreader and Mixer, Blacktop Plant (NonAutomated), Blast or Rotary Drill (Truck or Tractor Mounted), Boring Machine, Cage

Hoist, Central Mix Plant (NonAutomated) and All Concrete Batching Plants, Cherry Picker (5 tons capacity and under), Concrete Paver (Over 16S), Crawler Drill, Self-contained, Crusher, Diesel Power Unit, Drill Rigs, Tractor Mounted, Front End Loader (Under 4 cu. yd.), Greaseman/Lubrication Engineer, HiPressure Boiler (15 lbs. and over), Hoist (One Drum), Hydro-Axe, Kolman Plant Loader and Similar Type Loaders, L.C.M. Work Boat Operator, Locomotive Mixer (for stabilized base selfpropelled), Monorail Machine, Plant Engineer, Profiler (105 H.P. and under), Grinder, Post Hole Digger and Post Driver, Power Broom (towed), Power Heaterman, Power Sweeper, Revinius Widener, Roller (Grade and Fill), Scarifier, ride-on, Shell Winder, Skid steer loader (Bobcat or similar), Span-Saw, ride-on, Steam Cleaner, Pug Mill, Pump Crete Ready Mix Concrete Plant Refrigeration Equipment (for soil stabilization)Road Widener, Roller (all above subgrade), Sea Mule, Self-contained Ride-on Rock Drill, Excluding Air-Track Type Drill, Skidder, Tractor with Dozer and/or Pusher, Trencher.

Tugger Hoist, Vermeer saw (ride on, any size or type), Winch, Winch Cat

GROUP 3: A Frame Winch Hoist on Truck , Articulated Heavy Hauler, Aggregate Plant, Asphalt or Concrete Grooving, Machine (ride on), Ballast Regulator, Ride-on Boiler (used in conjunction with production), Bituminous Heater, self-propelled, Boat (powered), Cement and Bin Operator, Compressors, Dust Collectors, Fork Lift, Generators, Pumps, Welding Machines, Light Plants, Heaters (hands-off equipment), Concrete Pavement Spreader and Finisher, Concrete Paver or Mixer (16S and under), Concrete Saw (self-propelled), Conveyor, Deck Hand, Directional Drill Machine Locator, Drill, (Core), Drill, (Well,) Farm Tractor with accessories, Fine Grade Machine, Tamper, ride-on, Tie

Extractor, ride-on, Tie Handler, ride-on, Tie Inserter, ride-on, Tie Spacer, ride-on, Tire Repair, Track Liner, ride-on, Tractor, Tractor (with towed accessories), Vibratory Compactor, Vibro Tamp, Well Point

GROUP 4: Tower Cranes

GROUP 5: Cranes 50 tons and over

GROUP 6: Cranes 49 tons and below

GROUP 7: Master Mechanic

FOOTNOTE:

a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day

IRON0012-011 07/01/2019

ALBANY; COLUMBIA; FULTON (Albin, Bleecker, Broad, Johnstown, Mayfield, Northampton and Perth); GREENE, MONTGOMERY (Amsterdam, Charleston, Florida, Glen, Mohawk and Root);

RENSSELAER, SARATOGA; SCHENECTADY; SCHOHARIE; and

WASHINGTON

COUNTIES:

Ironworkers:

Sheeter, Bucker-up..........$ 31.80 28.59 Sheeter.....................$ 31.80 28.59 Structural, Ornamental, Rodman, Machinery Mover, Rigger, Fence Erector, Reinforcing, Stone Derrickmen..................$ 31.55 28.59

* IRON0440-007 07/01/2022

FULTON (Twps. of Caroga, Ephratah, Oppenheim, Stratford);

MONTGOMERY (Twps of Canajoharie, Minden, Palatine, St.

Johnsville):

IRONWORKER

Structural, Ornamental, Rodman, Machinery Mover, Rigger, Fence Erector, Reinforcement, and Stone Derrickman..................$ 31.25 29.19

LABO0017-001 07/01/2019

COLUMBIA COUNTY (Twps of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont and the City of Hudson)

LABORER

COLUMBIA COUNTY (Townships of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont, and the City of Hudson) (Asbestos, lead, toxic and hazardous waste abatement and any other environmental related work) HEAVY & HIGHWAY GROUP 1:...................$ 38.90 27.15+a

GROUP 2:...................$ 43.15 27.15+a GREENE COUNTY (Township of Catskill) HEAVY & HIGHWAY:

GROUP 1:...................$ 34.15 27.15+a GROUP 2:...................$ 38.90 27.15+a GROUP 3:...................$ 43.15 27.15+a GROUP 4:...................$ 48.00 27.15+a

TUNNEL, SHAFT & CAISSON

WORK

GROUP 1....................$ 48.05 29.50+a

For HEAVY & HIGHWAY CLASSIFICATIONS in COLUMBIA COUNTY (Townships of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont and the City of Hudson)

HEAVY & HIGHWAY CLASSIFICATIONS

GROUP 1: Asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective equipment and clothing are not required

GROUP 2: Asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective clothing and equipment is required

For HEAVY & HIGHWAY CLASSIFICATIONS in GREENE COUNTY (Township of Catskill)

FOOTNOTE:

a. PAID HOLIDAYS: New Years Day, President's Day, Memorial Day, Independence Day, Lincoln's Birthday, Labor Day, Election Day, Veterans Day, Thanksgiving Day, Christmas Day, provided the employee is an employee of the company prior to the scheduled holiday and reports to work the first day following the holiday unless prevented from doing so for legitimate reasons.

GROUP 1: Flagperson, gateperson

GROUP 2: General laborers, chuck tender, handling and distributing drinking water, distributing all tools and supplies of laborers, nipper, powder carrier, magazine tender, warehouse laborers, concrete man, vibrator man, mason tender, mortar man, spraying, brushing and covering of concrete for curing and preservative purposes, traffic striper, scaffold builder, concrete curb and sidewalk form setter; permanent traffic striping and reflective devices, placing and maintenance of all flares, cones, lights, signs, barricades, traffic patterns, and all temporary reflective type materials for traffic control, custodial work, traffic directors, temporary heat or light tenders, tool room, dewatering pump men, pitman, dumpmen, snow removal and firewatch, asphalt man, joint setter, signal person, pipelayer, pipe lining and relining, wellpoints, conduit and duct layer, wire puller, rip rap and dry stone layer, steel rod carrier, core drill, rock splitter, Hilti gun air or electric, jackhammer, bush hammer, pavement breaker, chipping hammer, wagon drill, air track, jib rig, joy drill, gunite and sand blasting, coal passer and other machine operators, power tool operator, sprayer and nozzle man on mulching and seeding machine, all guard rail and fence, all seeding and sod laying, all landscape work, grade checker, all bridge work, walk behind self-propelled power saw, grinder, groover or similar type machine, walk behind tamper and roller of all types, salvage, stripping, wrecking and dismantling laborer (including barman, cutting torch and burner man), sheeting and shoring coming under laborers jurisdiction, bit grinder, operator of form pin puller and drivers, sandblasting, joint and jet sealer, filling and wiring baskets for gabion walls, permanent sign man, median barrier, sta-wall or similar type product, chain saw operator, railroad track laborer, waterproofer, pre-stressed and pre-cast concrete brick, block and stone pavers, power tools used to perform work usually done by laborers, power buggy and pumpcrete operator, fireproof, plaster and caustic pump, asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous materials abatement when protective clothing and equipment is not required, power brush cutter, retention liners, artificial turf, retaining walls, walk behind surface planer, welding related to laborers work, remote controlled equipment normally operated by laborers, all technician work including but not limited to stitching, seaming, heat welding, fireproof sprayer, mortar mixer, concrete finisher, form setter for concrete curbs and flatwork.

Gunite nozzle man, stone cutters, granite stone layer, manhole, catch basin or inlet installing, laser men.

Ground man on milling machine

GROUP 3 Ingersoll Rand heavy duty crawler-master HCMZ, any drill using a 4"" or larger bit, asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective clothing and equipment is required, all working foremen including grade, pipe concrete, clearing, blacktop, drill, paving and blaster etc., Hydraulic drill or similar, forklift for masonry only, Blaster and asphalt screedman

GROUP 4: Asbestos, toxic, lead or hazardous material abatement foreman

For TUNNEL, SHAFT & CAISSON WORK CLASSIFICATIONS

a. PAID HOLIDAYS: New Years Day, President's Day, Memorial Day, Independence Day, Labor Day, Election Day, Veterans Day, Thanksgiving Day, Christmas Day

GROUP 1: Laborer, Pit and Dumpman, Chuck Tender, Brakeman and Powderman;

Miner and all machine men, Safety Miner, all shaft work, caisson work, drilling, blow pipe, all air tools, tugger, scaling, nipper gunniting from pot to nozzle, bit grinder, signal man (top and bottom), shield driven tunnel, mixed face and soft ground liner plate tunnel in free air

LABO0035-001 07/01/2017

FULTON (TWPS OF CAROGA, EPHRATA, OPPENHEIM, AND STRAFORD);

MONTGOMERY (TWPS OF CANAJOHARIE, MINDEN AND PALATINE, ROOT

AND

ST. JOHNSVILLE)

Laborers Building Construction Asbestos Removal............$ 24.00 20.64+a Blasters, Form Setters, MotorBuggy Operator (Rider Type)......................$ 23.00 20.64+a Hazardous Waste Removal Hazardous waste removal includes wetting, stripping, removal, scrapping, vaccuuming, bagging and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems.........$ 24.00 20.64+a

HEAVY & HIGHWAY:

GROUP 1:...................$ 28.05 23.74+a GROUP 2:...................$ 28.25 23.74+a GROUP 3:...................$ 28.45 23.74+a GROUP 4:...................$ 28.65 23.74+a Laborers....................$ 22.50 20.64+a

Pipelayers, Motor Mixers, Motor Buggy Operator (Walk Behind) Power Lift (Walk Behind)...............$ 22.65 20.64+a Wagon Drill Operator........$ 22.90 20.64+a

FOOTNOTE:

a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.

GROUP 1: Common Laborers, Flagman, Outboard and Hand boats

GROUP 2: Bull Float, Chain Saw, Concrete aggregate bin, Concrete Bootman, Gin Buggy, Hand or Machine Vibrator, Jackhammer, Mason Tender, Mortar Mixer, Pavement Breaker, Handlers of all steel mesh, Small generators for laborer's tools, Installation of bridge drainage, Pipelayers, Vibrator type rollers, Tamper, Drill doctor, Tail or Screw Operator on asphalt paver, Water pump operator (1 1/2"" and single diaphragm), Nozzle (asphalt, gunnite, seeding and sand blasting), Laborers on chain link fence erection, Rock splitter and power unit, Pusher type concrete saw and all other gas, electric, oil, and air tool operators, Wrecking laborers

GROUP 3: All rock or drilling machine operators (except quarry master and similar type), Acetylene torch operators, and Asphalt paver, Powderman

GROUP 4: Blasterers, Form setters, Stone or Granite Curb setters

LABO0157-001 07/01/2017

FULTON (Twps. of Bleeker, Mayfield, Northhampton, Johnstown, Broadalbin and Perth); MONTGOMERY (Twps. of Mohawk, Glen, Charleston, Amsterdam, and Florida); SARATOGA (Twps. of Day, Hadley, Edinburg, Corinth, Moreau, South Glens Falls, Providence, Greenfield, Wilton, Northcumberland, Galway, Milton, Saratoga Springs, Charlton, Ballston, Malta and Clifton Park); SCHENECTADY and SCHOHARIE COUNTIES.

LABORER

BUILDING:

GROUP 1....................$ 28.74 20.14+a GROUP 2....................$ 30.09 20.14+a

HEAVY & HIGHWAY:

GROUP 1:...................$ 30.55 21.29+a GROUP 2:...................$ 30.75 21.29+a GROUP 3:...................$ 30.95 21.29+a GROUP 4:...................$ 31.15 21.29+a GROUP 5:...................$ 32.55 21.29+a

LABORER CLASSIFICATIONS

Group 1: Common Laborers

Group 2: Asbestos and Toxic Materials

Commercial projects valued at $800,000 or less and/or industrial projects valued at $100,000 or less, excluding demolition work (the complete razing of structures) 75% of the basic wage scale with full benefits will apply

FOOTNOTE:

a. PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day

LABORER CLASSIFICATIONS

GROUP 1: Common laborers, flagman, outboard & hand boats

GROUP 2: Bull float, chain saw, concrete aggregate bin, concrete bootman, gin buggy, hand or machine vibrator, jackhammer, mason tender, mortar mixer, pavement breaker, handlers of all steel mesh, small generators for laborers' tools, installation of bridge drainage, pipelayers, vibrator type rollers, tamper, drill doctor, tail or screw operator on asphalt paver, water pump operator (1 1/2"") and single diaphragm), nozzle (asphalt, gunnite, seeding, and sand blasting), laborers on chain fence erection, rock splitter and power unit, pusher type concrete saw and all other gas, electric, oil, and air tool operators, wrecking laborers

GROUP 3: All rock drilling machine operators (except quarry master and similar type), acetylene torch operator, and asphalt paver, powderman

GROUP 4: Blasterers, form setters, stone or granite curb setters

GROUP 5: Hazardous waste removal

* LABO0190-001 07/01/2022

ALBANY; GREEN; RENSSELAER COUNTY, WASHINGTON COUNTY,

SARATOGA

COUNTY (Townships of Stillwater, Halfmoon, Saratoga)

Laborers:

BUILDING:

GROUP 1....................$ 32.86 24.57

GROUP 2....................$ 34.21 24.57

LABORERS CLASSIFICATIONS

GROUP 1: Common Laborers

GROUP 2: Hazardous waste removal Commercial projects valued at $800,000 or less and/or industrial projects valued at $100,000 or less excluding demolition work, (complete razing of structures) will receive 75% of basic wage scale with full fringes will apply

LABO0190-002 07/01/2018

ALBANY; RENSSELAER; COLUMBIA (Twps. of Stuyvesant, Stockport, Kinderhook, New Lebanon, Cannan, Ghent, Chatham, Austerlitz).

GREENE (except Catskill Township). WASHINGTON

COUNTY. SARATAGO

COUNTY (Townships of Stillwater, Halfmoon Saratoga)

HEAVY & HIGHWAY:

GROUP 1:...................$ 30.94 22.70

GROUP 2:...................$ 31.14 22.70

GROUP 3:...................$ 31.34 22.70

GROUP 4:...................$ 31.54 22.70

GROUP 5:...................$ 32.94 22.70

FOOTNOTE:

PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.

LABORERS CLASSIFICATIONS

GROUP 1: Common laborers, flagmen, outboard and hand boats

GROUP 2: Bull float, chain saw, concrete aggregated bin, concrete bootman, gin buggy, hand or machine vibrator, jackhammer, mason tender, mortar mixer, pavement breaker, handlers of all steel mesh, small generators for laborers' tools, installation of bridge drainage, pipelayers, vibrator type rollers, tampers, drill doctor, Tail or screw operator on asphalt paver, Water pump operator (1 1/2"" and single diaphragm), Nozzle (asphalt, gunnite, seeding, and sand blasting) Laborers on chain link fence erection, rock splitter and power unit, pusher type concrete saw and all other gas, electric, oil, air tool operators, and wrecking laborers

GROUP 3: All rock air drilling machine operators (except quarry master and similar type), acetylene torch operators, and asphalt paver, powderman

GROUP 4: Blasterers, form setters, stone or granite curb setters

GROUP 5: Hazardous waste removal

LABO0235-006 05/01/2018

COLUMBIA (Twps. of Greenport, Claverack, Hillsdale, Livingston, Germantown, Taghkanic, Copake, Clermont, Gallatin, Ancram):

HEAVY & HIGHWAY

GROUP 1....................$ 24.40 29.75+a GROUP 2....................$ 28.16…