W912DS22B0025 Amend 0003.pdf

PDF 567 KB Posted

Attached to
Renovate & Repair – Building 20 Construction project at the Watervliet Arsenal, NY
Solicitation number
W912DS22B0025
Issued by

About this file

This amendment modifies a solicitation for the renovation and repair of Building 20 at the Watervliet Arsenal in New York. The U.S. Army Corps of Engineers seeks to perform hazardous material removal, window replacement, siding and door repairs, restroom and locker room renovations, office renovations and associated HVAC and lighting upgrades, entrance replacements including ramps and vestibules, stair hall and vestibule renovations, and exterior masonry repairs. The estimated cost ranges between $10-25 million. The amendment revises the bid schedule and notes a final date of September 13, 2022 for bidder questions. Offerors must submit pricing for all contract line items, including optional items, by the acceptance period ending in 90 days. The projected award date is September 2022 and period of performance is 545 days.

View the file

Other files

File Type Posted
Bid Abstract_W912DS22B0025 BLG 20.pdf PDF
ATL No. CD4849E-01-07-20 Rev 1 Burns - Watervliet Ped Bridge.pdf PDF
09 90 00.pdf PDF
W912DS22B0025 Amend 0007.pdf PDF
ATL No CD4849E-02-07-22 Rev 1 - Burns - Watervliet HVAC Pad.pdf PDF
09 06 00.pdf PDF
RBM Survey Report Watervliet Arsenal NY - Bldg 20 Phase 2 V1 - Final.pdf PDF
Site Visit Sign in Sheet 2022-09-16.pdf PDF
123796 Phase II Final Design - Addendum 003 Project Specifications Binder.pdf PDF
W912DS22B0025 Amend 0006.pdf PDF
WVA Building 20 - Bid Option - Drawing Breakdown.pdf PDF
RBM Survey Report Watervliet Arsenal NY - Bldg 20 V1 - Final w Attachments.pdf PDF
SGH Bridge Crane Steel Inspection Report 052022.pdf PDF
W912DS22B0025 Amend 0005.pdf PDF
Bid bond form SF24-16e.pdf PDF
123796 Arch Addendum002 S and S 3.pdf PDF
123796 Phase II Final Design - Addendum 002 Project Specifications Binder.pdf PDF
123796 Arch Addendum002 S and S 2.pdf PDF
123796 Arch Addendum002 S and S 1.pdf PDF
W912DS22B0025 Amend 0004.pdf PDF
Site Visit sign-in Sheet 30-Aug-2022.pdf PDF
123796 Phase II Final Design - Addendum 01 Specification Binder R1-1.pdf PDF
123796_Full Binder_P2_RTA_ADD 001_Revised - V2.pdf PDF
W912DS22B0025 Amend 0002.pdf PDF
W912DS22B0025 Amend 0001.pdf PDF
123796 Phase II 100 percent Final Design Specification Binder - R3.pdf PDF
Pages from 101-125 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 125-156 123796_Full Binder_Phase 2 - V11.pdf PDF
W912DS22B0025.pdf PDF
Pages 26-56 from 123796_Full Binder_Phase 2 100 - V11.pdf PDF
123796 Phase II 100_ Final Design Specification Binder - R3 (1).pdf PDF
Pages from 72-100 123796_Full Binder_Phase 2 100 - V11.pdf PDF
Pages from 257-277 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages 1 to 25 from 123796 Full Binder Phase 2 V11.pdf PDF
Pages from 177-200 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 200-225 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 226-256 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 277-300 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 156-176 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 57-72 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 300-334 123796_Full Binder_Phase 2 - V11.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this an amendment is to:

1.revise bid schedule

2. Post site visit sign-in 3.Final cut-off date for Bidder requests for information is 13-Sep-2022 at 02:00 pm EST.

NOTE: Bidders must acknow ledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow ing methods: in the space provided on SF1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208)

1. CONTRACT ID CODE PAGE OF PAGES

J 1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 01-Sep-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS22B0025

X 9B. DATED (SEE ITEM 11)

24-Aug-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

01-Sep-2022

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS22B0025

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

AMENDMENT 0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Renovation of Building 20

FFP

All work associated with the renovation of Building 20 and its supporting typical infrastructure as indicated in the corresponding construction documents and specifications.

FOB: Destination

PSC CD: Y1EA

NET AMT

0002 1 Job OPTION Replacement of electrical bus bars

FFP

0003 1 Job OPTION Manufacturing floor electric

FFP

0004 1 Job OPTION Install manufacturing floor cooling

FFP

0005 1 Job OPTION Install metal wall panels

FFP

0006 1 Job OPTION Install translucent wall panels in

FFP

lieu of metal wall panels

0007 1 Job OPTION Upgrades to entrance & 1st floor

FFP

renovations

0008 1 Job OPTION Replace windows at manufacturing

FFP

floor

0009 1 Job OPTION Replace windows at administrative

FFP

areas

TOTALS

Total Base Bid CLIN 0001 ____________________________________________

Total Options (CLINs Item 0002 thru 0009)________________________________

Total Estimated Base Bid + Options (CLIN Item 0001 thru 0009)________________

NOTES TO BIDDERS

(1) Total Offer shall include all costs associated with each item number including all bonding, overhead and profit.

(2) Offeror must submit a price for every CLIN. Failure to do so may result in Offer being unacceptable.

(3) Optional Items (Additives) may be exercised at any time within 180 calendar days after contract award. The Contracting Officer may exercise the Optional Items by written notice to the Contractor, postmarked within the period specified above. The Government may exercise any, all or none of the listed Optional Items in any order.

(4) Contract Duration is 545 Days.

(5) Offer Acceptance Period: Offers are to be valid for 90 calendar days for offer acceptance from the Offer Acceptance.

(End of Summary of Changes)