Bid Abstract_W912DS22B0025 BLG 20.pdf

PDF 914 KB Posted

Attached to
Renovate & Repair – Building 20 Construction project at the Watervliet Arsenal, NY
Solicitation number
W912DS22B0025
Issued by

About this file

This abstract of offers is for a construction project to renovate and repair portions of Building 20 at the Watervliet Arsenal in New York. The project includes hazardous material removal, window, siding and door replacements, restroom and locker room renovations, office renovations and associated HVAC and lighting work, entrance renovations including ramps and vestibules, exterior masonry repairs, and other facility improvements. The estimated construction cost is between $10-25 million. Three contractors submitted bids by the September 22nd deadline, with total offer prices ranging from approximately $38.8-41.9 million. Award is projected for September 2022. The work will be undertaken by the New York District of the U.S. Army Corps of Engineers to upgrade and maintain facilities at the oldest continuously operating cannon manufacturing arsenal in the United States.

View the file

Other files

File Type Posted
ATL No. CD4849E-01-07-20 Rev 1 Burns - Watervliet Ped Bridge.pdf PDF
09 90 00.pdf PDF
W912DS22B0025 Amend 0007.pdf PDF
ATL No CD4849E-02-07-22 Rev 1 - Burns - Watervliet HVAC Pad.pdf PDF
09 06 00.pdf PDF
RBM Survey Report Watervliet Arsenal NY - Bldg 20 Phase 2 V1 - Final.pdf PDF
Site Visit Sign in Sheet 2022-09-16.pdf PDF
123796 Phase II Final Design - Addendum 003 Project Specifications Binder.pdf PDF
W912DS22B0025 Amend 0006.pdf PDF
WVA Building 20 - Bid Option - Drawing Breakdown.pdf PDF
RBM Survey Report Watervliet Arsenal NY - Bldg 20 V1 - Final w Attachments.pdf PDF
SGH Bridge Crane Steel Inspection Report 052022.pdf PDF
W912DS22B0025 Amend 0005.pdf PDF
Bid bond form SF24-16e.pdf PDF
123796 Arch Addendum002 S and S 3.pdf PDF
123796 Phase II Final Design - Addendum 002 Project Specifications Binder.pdf PDF
123796 Arch Addendum002 S and S 2.pdf PDF
123796 Arch Addendum002 S and S 1.pdf PDF
W912DS22B0025 Amend 0004.pdf PDF
W912DS22B0025 Amend 0003.pdf PDF
Site Visit sign-in Sheet 30-Aug-2022.pdf PDF
123796 Phase II Final Design - Addendum 01 Specification Binder R1-1.pdf PDF
123796_Full Binder_P2_RTA_ADD 001_Revised - V2.pdf PDF
W912DS22B0025 Amend 0002.pdf PDF
W912DS22B0025 Amend 0001.pdf PDF
123796 Phase II 100 percent Final Design Specification Binder - R3.pdf PDF
Pages from 101-125 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 125-156 123796_Full Binder_Phase 2 - V11.pdf PDF
W912DS22B0025.pdf PDF
Pages 26-56 from 123796_Full Binder_Phase 2 100 - V11.pdf PDF
123796 Phase II 100_ Final Design Specification Binder - R3 (1).pdf PDF
Pages from 72-100 123796_Full Binder_Phase 2 100 - V11.pdf PDF
Pages from 257-277 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages 1 to 25 from 123796 Full Binder Phase 2 V11.pdf PDF
Pages from 177-200 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 200-225 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 226-256 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 277-300 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 156-176 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 57-72 123796_Full Binder_Phase 2 - V11.pdf PDF
Pages from 300-334 123796_Full Binder_Phase 2 - V11.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAGE

S

7A. ITEM

NO.

7C. EST.

QUANTITY

D.

UNIT

E. UNIT

PRICE

F. ESTIMATED

AMOUNT

D. UNIT

PRICE

D. UNIT

PRICE

0001 1 Job $11,189,339.00

0002 1 Job $9,595,124.00

0003 1 Job $3,497,061.00

0004 1 Job $4,221,811.00

0005 1 Job $1,020,804.00

0006 1 Job $681,525.00

0007 1 Job $486,665.00

0008 1 Job $749,526.00

0009 1 Job $640,137.00

0010 1 Job $667,345.00

0011 1 Job $119,167.00

Total Base $11,189,339.00

Optional CLINS $21,680,165.00

Total Base+ Options $32,869,504.00

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is usable

NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88)

Replace windows at administrative areas $437,009.00 $463,590.00

Manufacturing floor Interior painting & epoxy floor finishes $760,700.00 $81,990.00

Masonry Repairs $87,000.00 $80,100.00

Upgrades to entrance & 1st floor renovations $950,000.00 $774,900.00

Replace windows at manufacturing $747,000.00 $162,990.00

Install metal wall panels $1,400,000.00 $945,711.00

Install translucent wall panels in lieu of metal wall panels

$1,560,300.00 $1,260,981.00

Manufacturing floor electric $810,200.00 $951,381.00

Install manufacturing floor cooling $2,661,000.00 $3,199,500.00

Renovation of Building 20 $16,917,000.00 $13,963,140.00

Replacement of electrical bus bars $6,781,500.00 $8,766,000.00

6. NUMBER OF AMENDMENTS ISSUED C. REASONABLE CONTRACT

(Including Profit)

C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED

7B. DESCRIPTION OF OFFERED ITEM E. ESTIMATED

AMOUNT

E. ESTIMATED

AMOUNT

B. BID SECURITY (Type and amount)

4. ISSUING OFFICE

U.S. Army Corps of Engineers, New York District Contracting Division

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

NAME AND TITLE OF CERTIFYING OFFICIAL: Mohenda Surage, Supervisory Contract Specialist

SIGNATURE DATE SIGNED

22 September 2022

5. PROJECT TITLE

: Renovate & Repair Facility – Building 20 Construction project at the Watervliet Arsenal, NY

8. GOVERNMENT ESTIMATE

(Check A, B or C and complete D, E, and F)

9. OFFERS

NO. 1 NO. 2

A. OFFEROR

Kallidus Technologies Inc

A. OFFEROR

Intercontinental Contruction Contracting Inc

A. HIRED LABOR

B. REASONABLE CONTRACT

(Without Profit)

B. BID SECURITY (Type and amount)

ABSTRACT OF OFFERS - CONSTRUCTION 1. SOLICITATION NUMBER

W912DS22B0025

2. DATE ISSUED

24 August 2022

3. DATE OPENED

22 September 2022

$33,111,700.00 $30,650,283.00

$13,963,140.00$16,917,000.00

$16,194,700.00 $16,687,143.00

PAGES

D. UNIT PRICE D.

UNIT

PRICE

D.

UNIT

PRICE

E. ESTIMATED

AMOUNT

0001 1 Job $14,535,752.00 $14,800,000.00

$15,731,798.00

0002 1 Job $9,335,823.00 $6,825,000.00

$8,366,617.00

0003 1 Job $1,009,276.00 $4,925,000.00

$3,798,282.00

0004 1 Job $2,981,291.00 $7,900,000.00

$3,612,731.00

0005 1 Job $2,806,180.00 $2,670,000.00 $1,474,733.00

0006 1 Job $3,474,890.00 $1,400,000.00

$2,080,733.00

0007 1 Job $2,243,643.00 $760,000.00

$487,731.00

0008 1 Job $1,305,105.00 $512,000.00

$582,971.00

0009 1 Job $1,115,348.00 $575,000.00

$708,887.00

0010 1 Job $1,275,000.00

$773,414.00

0011 1 Job $320,000.00 $62,575.00

Total Base $14,535,752.00 $14,800,000.00 $15,731,798.00 Optional

CLINS $24,271,556.00 $27,162,000.00 $21,948,097.00

Total Base+ Options $38,807,308.00 $41,962,000.00 $37,679,895.00

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is usable

OPTIONAL FORM 1419A

(11-88)

3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED

A. ITEM NO. B. ESTIMATED

QUANTITY

C. UNIT

E. ESTIMATED AMOUNT E. ESTIMATED AMOUNT D. UNIT PRICE E. ESTIMATED

AMOUNT

2. PROJECT TITLE

: Renovate & Repair Facility – Building 20 Construction project at the Watervliet Arsenal, NY

4. OFFERS (Continued)

NO.: 3 NO.: 4 NO.: 5 NO.: 6

A. OFFEROR

Enfield Enterprises LLC

A. OFFEROR

Benaka Inc

A. OFFEROR

Doyon Technical Services

LLC

A. OFFEROR

B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)

ABSTRACT OF OFFERS - CONSTRUCTION CONTINUATION SHEET

1. SOLICITATION NUMBER

W912DS22B0025

INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.

Renovation of Building 20

Replacement of electrical bus bars

Manufacturing floor electric

Install manufacturing floor cooling

Install metal wall panels

Install translucent wall panels in lieu of metal wall panels

Upgrades to entrance & 1st floor renovations

Replace windows at manufacturing

Replace windows at administrative areas

Manufacturing floor Interior painting & epoxy floor finishes

Masonry Repairs

Bid Abstract_W912DS22B0025
Bid Abstract_W912DS22B0025 Page 2
2022-09-23T16:38:26-0400
SURAGE.MOHENDA.RAMESH.1250484549

File details come from the government source that posted it. Updated .