IMPLEMENTATION OF SOIL EROSION AND SEDIMENT CONTROL MEASURES
(GENERAL SEQUENCE OF CONSTRUCTION OPERATIONS)
1. NOTIFY MORRIS COUNTY SCD IN WRITING AT LEAST 72 HOURS IN ADVANCE OF ANY
SOIL DISTURBANCE. (1 DAY)
2. REMOVE ANY TREES SO INDICATED WITHIN AREA DESIGNATED "LIMIT OF PROJECT".
(ACTIVITIES ARE LIMITED TO TREE CUTTING AND REMOVAL AND DO NOT CALL FOR
SOIL DISTURBANCE. FURTHERMORE, THE REMOVAL OF TREES SHALL NOT BE
PERMITTED BETWEEN APRIL 1 AND NOVEMBER 15 IN ACCORDANCE WITH
RESTRICTIONS TO PROTECT THE INDIANA BAT, AN ENDANGERED SPECIES;
COORDINATE WITH BASE'S ONSITE BIOLOGIST AS NECESSARY). (WEEKS 1 - 12)
3. PLACE SUPER SILT FENCE, GENERALLY ALONG PERIMETER OF SITE DISTURBANCE.
(WEEKS 1 - 12, CONCURRENT WITH ITEM #2)
4. DEMOLISH EXISTING BUILDINGS AND INFRASTRUCTURE. (WEEKS 12 - 36)
5. CONSTRUCT NEW UTILITIES, STORM SEWER, INLETS AND OUTFALL AS PER
CONSTRUCTION DRAWINGS. (WEEKS 36 - 52)
6. CONSTRUCT NEW BUILDINGS, ROADWAY AND PARKING AS PER CONSTRUCTION
PLANS. (WEEKS 36 - 91, CONCURRENT WITH ITEM #5)
7. INSTALL ANY REMAINING SITE IMPROVEMENTS - i.e., SIGNAGE, TOPSOIL & SEEDING, ETC. - AND REMOVE ANY S.E.S.C. MEASURES FOLLOWING INSPECTION BY MORRIS
COUNTY SCD. (WEEKS 91 - 104).
DURATION OF PROJECT: APPROXIMATELY TWO (2) YEARS OR LESS.
STANDARD FOR TOPSOIL
TOPSOILING ENTAILS THE DISTRIBUTION OF SUITABLE QUALITY SOIL ON AREAS TO BE VEGETATED.
TO IMPROVE THE SOIL MEDIUM FOR PLANT ESTABLISHMENT AND MAINTENANCE.
TOP SOIL SHOULD BE USED WHERE SOILS ARE: SANDS, GRAVELY SOILS, CLAYS, SILTY CLAYS, VERY SHALLOW
OR WHERE THEY ARE EXTREMELY ACID (LESS THAN 4.0) OR SALTY (CONDUCTIVITY GREATER THAN 1.0
MILL MHOS PER CENTIMETER); OR WHERE TOPSOIL IS AVAILABLE ON SITE AND ASSURANCE OF IMPROVED
TOPSOIL SHOULD BE FRIABLE AND LOAMY, FREE OF DEBRIS, OBJECTIONABLE WEEDS AND STONES, AND
CONTAIN NO TOXIC SUBSTANCE THAT MAY BE HARMFUL TO PLANT GROWTH. A PH RANGE OF 5.0-7.5 IS
ACCEPTABLE. SOLUBLE SALTS SHOULD NOT BE EXCESSIVE (CONDUCTIVITY LESS THAN 0.5 MILLIMHOS PER
CENTIMETER). TOPSOIL HAULED IN FROM OFF SITE SHOULD HAVE A MINIMUM ORGANIC MATTER CONTENT
OF 2.75 PERCENT. ORGANIC MATTER CONTENT MAY BE RAISED BY ADDITIVES.
FIELD EXPLORATION SHOULD BE MADE TO DETERMINE WHETHER QUANTITY AND OR QUALITY OF SURFACE
STRIPPING SHOULD BE CONFINED TO THE IMMEDIATE CONSTRUCTION AREA.
WHERE FEASIBLE, LIME MAY BE APPLIED BEFORE STRIPPING AT A RATE DETERMINED BY SOIL TESTS
TO BRING THE SOIL PH TO 6.5. IN LIEU OF SOIL TESTS, SEE LIME RATE GUIDE IN SEEDBED
PREPARATION FOR PERMANENT VEGETATIVE COVER, PAGE 3.2.1.
VEGETATIVE GROWTH IS DESIRED.
METHOD AND MATERIALS
II STRIPPING AND STOCKPILING
SOIL JUSTIFIES STRIPPING.
A.
B.
C.
I. MATERIALS
WHERE APPLICABLE
DEFINITION
PURPOSE
1. THE CONTRACTOR SHALL PREPARE A PLAN FOR THE PROPER DEWATERING OF
EACH STREAM CROSSING PRIOR TO EXCAVATING THE STREAM BED. PLAN
SHALL BE FORWARDED TO THE ENGINEER AND MORRIS COUNTY SOIL
CONSERVATION DISTRICT FOR APPROVAL. THE DISTRICT SHALL BE NOTIFIED
FOR INSPECTION PRIOR TO EACH STREAM CROSSING CONSTRUCTION.
2. ANY AREAS USED FOR THE CONTRACTOR'S STAGING, INCLUDING BUT NOT
LIMITED TO, TEMPORARY STORAGE OF STOCKPILED MATERIALS ( E.G. CRUSHED
STONE, QUARRY PROCESS STONE, SELECT FILL, EXCAVATED MATERIALS, ETC.),
SHALL BE ENTIRELY PROTECTED BY A SILT FENCE ALONG THE LOW ELEVATION
SIDE TO CONTROL SEDIMENT RUNOFF.
3. PRIOR TO CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR
NOTIFYING THE MORRIS COUNTY SOIL CONSERVATION DISTRICT OF ANY
STAGING AND/OR STOCKPILE LOCATION AREAS AND FOR OBTAINING A SOIL
EROSION AND SEDIMENT CONTROL CERTIFICATION FOR THESE AREAS.
4. A CRUSHED STONE, VEHICLE WHEEL-CLEANING BLANKET SHALL BE INSTALLED
AT THE CONTRACTOR'S STAGING YARD AND/OR STOCKPILE AREAS TO PREVENT
OFF-SITE TRACING OF SEDIMENT BY CONSTRUCTION VEHICLES ONTO PUBLIC
ROADS. BLANKET SHALL BE 15 FT. X 50 FT. X 6 IN. (MINIMUM), CRUSHED STONE
2-1/2 INCHES IN DIAMETER. SAID BLANKET SHALL BE UNDERLAIN WITH A
SUITABLE SYNTHETIC SEDIMENT FILTER FABRIC AND MAINTAINED IN GOOD
ORDER.
MORRIS COUNTY SOIL CONSERVATION DISTRICT NOTES FOR ROAD WORK
WOOD - FIBER OR PAPER-FIBER MULCH AT THE RATE OF 1,500 POUNDS PER ACRE MAY BEC.
IMMEDIATELY PRIOR TO TOPSOIL DISTRIBUTION, THE SURFACE SHOULD BE SCARIFIED AND DE-COMPACTED
EMPLOY NEEDED EROSION CONTROL PRACTICES SUCH AS DIVERSIONS, GRADE STABILIZATION
STRUCTURES, CHANNEL STABILIZATION MEASURES, SEDIMENTATION BASINS, AND WATERWAYS. SEE
TOPSOIL SHOULD BE HANDLED ONLY WHEN ITS IS DRY ENOUGH TO WORK WITHOUT DAMAGING SOIL
STRUCTURE; I.E., LESS THAN FIELD CAPACITY ( SEE GLOSSARY).
A UNIFORM APPLICATION TO A DEPTH OF 5 INCHES (UNSETTLED). SOILS WITH A PH OF 4.0 OR LESS OR
CONTAINING IRON SULFIDE SHALL BE COVERED WITH A MINIMUM DEPTH OF 12 INCHES OF SOIL HAVING
EMULSIFIED ASPHALT - (SS-1, CSS-1, CMS-2, MS-2, RS-1, RS-2, CRS-1, AND
APPLY 0.04 GAL./SQ./YD. OR 194 GAL./ACRE ON FLAT SLOPES LESS THAN 8 FEET
HIGH. ON SLOPES 8 FEET OR MORE HIGH, USE 0.075 GAL./SY. YD. OR
SYNTHETIC OR ORGANIC BINDERS - BINDERS SUCH AS CURASOL, DCA-70, PETRO-SET,
AND TERRA-TRACK MAY BE USED AT RATES RECOMMENDED BY THE MANUFACTURER TO
MULCH MATERIAL SHOULD BE UNROTTED SMALL GRAIN STRAW, HAY FREE OF SEEDS, OR SALT HAY TO
BE APPLIED AT A RATE OF 1-1/2 TO 2 TONS PER ACRE (70 TO 90 POUNDS PER 1,000 SQUARE
FEET), EXCEPT THAT WHERE A CRIMPER IS USED INSTEAD OF A LIQUID MULCH-BINDER (TACKIFYING
OR ADHESIVE AGENT), THE RATE OF APPLICATION MUST BE DOUBLED THE LOWER RATE. MULCH
SPREAD UNIFORMLY BY HAND OR MECHANICALLY SO THAT APPROXIMATELY 75% TO 95% OF THE SOIL
SURFACE WILL BE COVERED. FOR UNIFORM DISTRIBUTION OF HAND-SPREAD MULCH, DIVIDE AREA
INTO APPROXIMATELY 1,000 SQUARE FEET SECTIONS AND DISTRIBUTE 70 TO 90 POUNDS, WITHIN EACH
MULCH ANCHORING SHOULD BE ACCOMPLISHED IMMEDIATELY AFTER PLACEMENT TO MINIMIZE LOSS BY
WIND OR WATER. THIS MAY BE DONE BY ONE OF THE FOLLOWING METHODS, DEPENDING UPON THE
PEG AND TWINE - DRIVE 8 TO 10 INCH WOODEN PEGS TO WITHIN 2 TO 3 INCHES OF THE SOIL
SURFACE EVERY 4 FEET IN ALL DIRECTIONS. STAKE MAY BE DRIVEN BEFORE OR AFTER
APPLYING MULCH. SECURE MULCH TO SOIL SURFACE BY STRETCHING TWINE BETWEEN PEGS IN A
CRISS-CROSS AND A SQUARE PATTERN. SECURE TWINE NETTING AROUND EACH PEG WITH TWO
MULCH NETTINGS - STAPLE PAPER, JUTE, COTTON, OR PLASTIC NETTINGS TO THE SOIL
SURFACE. USE A DEGRADABLE NETTING IN AREAS TO BE MOWED.
CRIMPER (MULCH ANCHORING TOOL) - A TRACTOR DRAWN IMPLEMENT, SOMEWHAT LIKE A DISC-
HARROW, ESPECIALLY DESIGNED TO PUSH OR CUT SOME OF THE BROADCAST LONG FIBER MULCH 3
TO 4 INCHES INTO THE SOIL SO AS TO ANCHOR IT AND LEAVE PART STANDING UPRIGHT. THIS
TECHNIQUE IS LIMITED TO AREAS TRAVERSABLE BY A TRACTOR, WHICH MUST OPERATE ON THE
CONTOUR OF SLOPE. STRAW MULCH RATE MUST BE 3 TONS PER ACRES. NO TACKIFYING OR
LIQUID MULCH-BINDER - MAY BE USED TO ANCHOR SALT HAY, HAY OR STRAW MULCHES.
APPLICATION SHOULD BE HEAVIER AT EDGES WHERE WIND CATCHES THE MULCH, IN VALLEYS,
AND AT CRESTS OF BANKS. REMAINDER OF AREA SHOULD BE UNIFORM IN APPEARANCE
OR MORE ROUND TURNS.
ADHESIVE AGENT IS REQUIRED.
B.
A.
ANCHOR MULCH MATERIAL.
USE ONE OF THE FOLLOWING:
(2)
CRS-2).
363 GAL./ACRE.
(1)
TO A DEPTH OF 6" TO PROVIDE A GOOD BOND WITH THE TOPSOIL.
STANDARDS 4.2 THROUGH 4.16.
IV APPLYING TOPSOIL
A PH OF 5.0 OR MORE.
CHOPPER-BLOWER MUST NOT GRIND THE MATERIAL.
SIZE OF THE AREA, STEEPNESS OF SLOPE, AND COST.
B.
C.
SECTION.
A.
A.
V MULCHING
B.
C.
D.
STANDARD FOR TOPSOIL
A 4-6 INCH STRIPPING DEPTH IS COMMON, BUT MAY VARY DEPENDING ON THE PARTICULAR SOIL.
STOCKPILES OF TOPSOIL SHOULD BE SITUATED SO AS NOT TO OBSTRUCT NATURAL DRAINAGE OR CAUSE
STOCKPILES SHOULD BE VEGETATED IN ACCORDANCE WITH STANDARDS PREVIOUSLY DESCRIBED HEREIN;
SEE 3.1 OR 3.2. WEEDS SHOULD NOT BE ALLOWED TO GROW ON STOCKPILES.
GRADE AS NEEDED AND FEASIBLE TO PERMIT THE USE OF CONVENTIONAL EQUIPMENT FOR SEEDBED
PREPARATION, SEEDING, MULCH APPLICATION AND ANCHORING, AND MAINTENANCE. SEE PAGE 4.1.
SUBSOIL SHOULD BE TESTED FOR LIME REQUIREMENTS AND LIMESTONE, IF NEEDED, SHOULD BE
APPLIED TO BRING SOIL PH TO 6.5 AND INCORPORATE INTO THE SOIL AS NEARLY AS PRACTICAL TO
II STRIPPING AND STOCKPILING CONTINUED
OFF-SITE ENVIRONMENTAL DAMAGE.
III SITE PREPARATION
A DEPTH OF 4 INCHES.
A.
B.
D.
E.
F.
1. ALL SOIL EROSION AND SEDIMENT CONTROL PRACTICES WILL BE INSTALLED IN ACCORDANCE WITH
THE STANDARDS FOR SOIL EROSION AND SEDIMENT CONTROL IN NEW JERSEY, AND WILL BE IN PLACE
PRIOR TO ANY MAJOR SOIL DISTURBANCE, OR IN THEIR PROPER SEQUENCE AND MAINTAINED UNTIL
PERMANENT PROTECTION IS ESTABLISHED.
2. ANY DISTURBED AREA THAT WILL BE LEFT EXPOSED FOR MORE THAN THIRTY (30) DAYS AND NOT
SUBJECT TO CONSTRUCTION TRAFFIC SHALL IMMEDIATELY RECEIVE A TEMPORARY SEEDING. IF THE
SEASON PROHIBITS TEMPORARY SEEDING, THE DISTURBED AREAS WILL BE MULCHED WITH STRAW
OR HAY AND TACKED IN ACCORDANCE WITH THE NEW JERSEY STANDARDS. SEE NOTE 21 BELOW.
MORRIS COUNTY SOIL CONSERVATION DISTRICT SOIL EROSION AND
SEDIMENT CONTROL NOTES
3. PERMANENT VEGETATION IS TO BE ESTABLISHED ON EXPOSED AREAS WITHIN TEN (10) DAYS AFTER
FINAL GRADING. MULCH IS TO BE USED FOR PROTECTION UNTIL VEGETATION IS ESTABLISHED. SEE
NOTE 22 BELOW.
4. IMMEDIATELY FOLLOWING INITIAL DISTURBANCE OR ROUGH GRADING. ALL CRITICAL AREAS (STEEP
SLOPES, SANDY SOILS, WET CONDITIONS) SUBJECT TO EROSION WILL RECEIVE A TEMPORARY
SEEDING IN ACCORDANCE WITH NOTE 21 BELOW.
5. TEMPORARY DIVERSION BERMS ARE TO BE INSTALLED ON ALL CLEARED ROADWAYS AND EASEMENT
AREAS. SEE THE DIVERSION DETAIL.
6. PERMANENT SEEDING AND STABILIZATION TO BE IN ACCORDANCE WITH THE “STANDARDS FOR
PERMANENT VEGETATIVE COVER FOR SOIL STABILIZATION COVER”. SPECIFIED RATES AND LOCATIONS
SHALL BE ON THE APPROVED SOIL EROSION AND SEDIMENT CONTROL PLAN.
7. THE SITE SHALL AT ALL TIMES BE GRADED AND MAINTAINED SO THAT ALL STORMWATER RUNOFF IS
DIVERTED TO SOIL EROSION AND SEDIMENT CONTROL FACILITIES.
8. ALL SEDIMENTATION STRUCTURES (SILT FENCE, INLET FILTERS, AND SEDIMENT BASINS) WILL BE
INSPECTED AND MAINTAINED DAILY.
9. STOCKPILES SHALL NOT BE LOCATED WITHIN 50’ OF A FLOODPLAIN, SLOPE, DRAINAGE FACILITY, OR
ROADWAY. ALL STOCKPILES BASES SHALL HAVE A SILT FENCE PROPERLY ENTRENCHED AT THE TOE
OF SLOPE.
10. A STABILIZED CONSTRUCTION ACCESS WILL BE INSTALLED, WHENEVER AN EARTHEN ROAD
INTERSECTS WITH A PAVED ROAD. SEE THE STABILIZED CONSTRUCTION ACCESS DETAIL AND CHART
FOR DIMENSIONS.
11. ALL NEW ROADWAYS WILL BE TREATED WITH SUITABLE SUBBASE UPON ESTABLISHMENT OF FINAL
GRADE ELEVATIONS.
12. PAVED ROADWAYS MUST BE KEPT CLEAN AT ALL TIMES.
13. BEFORE DISCHARGE POINTS BECOME OPERATIONAL, ALL STORM DRAINAGE OUTLETS WILL BE
STABILIZED AS REQUIRED.
14. ALL DEWATERING OPERATIONS MUST BE DISCHARGED DIRECTLY INTO A SEDIMENT FILTER AREA. THE
FILTER SHOULD BE COMPOSED OF A FABRIC OR APPROVED MATERIAL. SEE THE DEWATERING DETAIL.
15. ALL SEDIMENT BASINS WILL BE CLEANED WHEN THE CAPACITY HAS BEEN REDUCED BY 50%. A CLEAN
OUT ELEVATION WILL BE IDENTIFIED ON THE PLAN AND A MARKER INSTALLED ON THE SITE.
16. DURING AND AFTER CONSTRUCTION, THE APPLICANT WILL BE RESPONSIBLE FOR THE MAINTENANCE
AND UPKEEP OF THE DRAINAGE STRUCTURES, VEGETATION COVER, AND ANY OTHER MEASURES
DEEMED APPROPRIATE BY THE DISTRICT. SAID RESPONSIBILITY WILL END WHEN COMPLETED WORK IS
APPROVED BY THE MORRIS COUNTY SOIL CONSERVATION DISTRICT.
17. ALL TREES OUTSIDE THE DISTURBANCE LIMIT INDICATED ON THE SUBJECT PLAN OR THOSE TREES
WITHIN THE DISTURBANCE AREA WHICH ARE DESIGNATED TO REMAIN AFTER CONSTRUCTION ARE TO
BE PROTECTED WITH TREE PROTECTION DEVICES. SEE THE TREE PROTECTION DETAIL.
18. THE MORRIS COUNTY SOIL CONSERVATION DISTRICT MAY REQUEST ADDITIONAL MEASURES TO
MINIMIZE ON SITE OR OFF SITE EROSION PROBLEMS DURING CONSTRUCTION.
19. THE MORRIS COUNTY SOIL CONSERVATION DISTRICT MUST BE NOTIFIED, IN WRITING, AT LEAST 72
HOURS PRIOR TO ANY LAND DISTURBANCE, AND A PRE-CONSTRUCTION MEETING HELD.
20. CONTRACTOR TO SET UP A MEETING WITH THE INSPECTOR FOR PERIODIC INSPECTIONS OF THE
TEMPORARY SEDIMENT BASIN PRIOR TO AND DURING ITS CONSTRUCTION.
21. TOPSOIL STOCKPILE PROTECTION
A) APPLY GROUND LIMESTONE AT A RATE OF 90 LBS PER 1000 SQ. FT.
B) APPLY FERTILIZER (10-20-10) AT A RATE OF 11 LBS. PER 1000 SQ. FT.
C) APPLY PERENNIAL RYEGRASS SEED AT 1 LB. PER 1000 SQ. FT. AND ANNUAL RYEGRASS AT 1 LB.
PER 1000 SQ. FT.
D) MULCH STOCKPILE WITH STRAW OR HAY AT A RATE OF 90 LBS. PER 1000 SQ. FT.
E) APPLY A LIQUID MULCH BINDER OR TACK TO STRAW OR HAY MULCH.
F) PROPERTY ENTRENCH A SILT FENCE AT THE BOTTOM OF THE STOCKPILE.
24. TEMPORARY STABILIZATION SPECIFICATIONS
G) APPLY GROUND LIMESTONE AT A RATE OF 90 LBS PER 1000 SQ. FT.
H) APPLY FERTILIZER (10-20-10) AT A RATE OF 11 LBS. PER 1000 SQ. FT.
I) APPLY PERENNIAL RYEGRASS SEED AT 1 LB. PER 1000 SQ. FT. AND ANNUAL RYEGRASS AT 1 LB.
PER 1000 SQ. FT.
J) MULCH STOCKPILE WITH STRAW OR HAY AT A RATE OF 90 LBS. PER 1000 SQ. FT.
K) APPLY A LIQUID MULCH BINDER OR TACK TO STRAW OR HAY MULCH.
25. PERMANENT STABILIZATION SPECIFICATIONS
L) APPLY TOPSOIL TO A DEPTH OF 5 INCHES (UNSETTLED).
M) APPLY GROUND LIMESTONE AT A RATE OF 90 LBS PER 1000 SQ. FT. AND WORK FOUR INCHES INTO
N) SOIL.
O) APPLY FERTILIZER (10-20-10) AT A OF RATE 11 LBS. PER 1000 SQ. FT.
P) APPLY HARD FESCUE SEED AT 2.7 LBS. PER 1000 SQ. FT. AND CREEPING RED FESCUE SEED AT
Q) 0.7 LBS PER 1000 SQ. FT. AND PERENNIAL RYEGRASS SEED AT 0.25 LBS PER 1000 SQ. FT.
R) MULCH STOCKPILE WITH STRAW OR HAY AT A RATE OF 90 LBS. PER 1000 SQ. FT.
S) APPLY A LIQUID MULCH BINDER OR TACK TO STRAW OR HAY MULCH.
* NOTE: 72 HOURS PRIOR TO ANY SOIL DISTURBANCE, NOTICE IN WRITING,
* SHALL BE GIVEN TO THE MORRIS COUNTY SOIL CONSERVATION
* DISTRICT AND A PRE-CONSTRUCTION MEETING HELD.
NOTE: ALL NAMES GIVEN ABOVE ARE REGISTERED TRADE NAMES. THIS DOES NOT CONSTITUTE
A RECOMMENDATION OF THESE PRODUCTS TO THE EXCLUSION OF OTHER PRODUCTS.
MULCHING IS REQUIRED ON ALL SEEDING. MULCH WILL INSURE AGAINST EROSION BEFORE GRASS IS
ESTABLISHED AND WILL PROMOTE FASTER AND EARLIER ESTABLISHMENT. ( THE EXISTENCE OF
SATISFACTORY PERMANENT VEGETATION AT THE TIME OF PROJECT OR UNIT COMPLETION SHALL BE
DEEMED AS COMPLIANCE WITH THIS MULCH REQUIREMENTS.
S E
D I M
E N
T
A
N D
E
R O
S I O
N
C O
N T
R O
L
N
O T
E S
J U
L Y
P E
O D
C
G d w g
CG802
W D
S D
X
J
L O
C K
M
S
O U
T H
M
M
A Y
E R
M
P
O E
A N
S I
D
RTA SUBMITTAL
P I C
A T
I N
A
S
E N
A L
N
W
J
R S
E Y
E X
P L O
S I V
E
O
R D
N A
N C
E
D
I S
P O
S A
L
E
O D
T E
C H
N O
L O
G
F
C
I L I T
Y
F Y
P
N
N E
W
Y
O R
K
D
I S
T R
I C
T
N E
W
Y
O R
K
N
W
O R
K
U S
A
R M
Y
C
O R
P S
F
E
N G
I N
E E
R S
C H
E C
K E
D
B
Y
D R
A W
N
B
Y
I S
S U
E
D
A T
E
SHEET ID
F I L E
N A
M E
B
C
D
E
F
G
2 3 4 5 6 7 8 9 10
S O
L I C
I T
A T
I O
N
N
O
D E
S I G
N E
D
B
Y
A
M A
R K
S I Z
E
S U
B M
I T
T E
D
B
Y
D A
T E
C O
N T
R A
C T
US Army Corps of Engineers
C A
T E
G O
C
D
E
D E
S C
R I P
T I O
N
P P r o j e c t s
C
A D
B
I M
S h e e t s C i v i l P
E O
D C
G d w g u g a m
A D
D E
N D
U M
File details come from the government source that posted it.