EOD Complex 016701 RTA Submittal
SECTION 01 22 00.00 10
PRICE AND PAYMENT PROCEDURES
08/15
ADDENDUM 08/ 07/ 2019
PART 1 GENERAL
1.1 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
ADDENDUM 08/ 07/ 2019**********************************************************
1. 1. 1 Wet l ands Mi t i gat i on Cr edi t s
1. 1. 1. 1 Payment
Payment wi l l be made f or pur chase of mi t i gat i on cr edi t s i n accor dance wi t h t he Speci f i cat i ons.
1. 1. 1. 2 Measurement
The t ot al quant i t y f or whi ch payment wi l l be made wi l l be based on pr oof of pur chase of 7. 83 Acr es of mi t i gat i on cr edi t s f r om an NJDEP- appr oved wet l and mi t i gat i on bank ser vi ng t he Wat er shed Management Ar ea Rockaway Ri ver ( 06CA) .
1. 1. 1. 3 Uni t of Measur e
Uni t of measur e: cr edi t s.
1.1.2 Ri par i an Zone Mi t i gat i on Cr edi t s
1. 1. 2. 1 Payment
Payment wi l l be made f or pur chase of mi t i gat i on cr edi t s i n accor dance wi t h t he Speci f i cat i ons.
1. 1. 2. 2 Measurement
The t ot al quant i t y f or whi ch payment wi l l be made wi l l be based on pr oof of pur chase of 8. 24 Acr es of mi t i gat i on cr edi t s f r om an NJDEP- appr oved wet l and mi t i gat i on bank ser vi ng t he Wat er shed Management Ar ea Rockaway Ri ver ( 06CA) .
SECTION 01 22 00.00 10 Page 1
EOD Complex 016701 RTA Submittal
1.1.2.3 Uni t of Measur e
Uni t of measur e: cr edi t s.
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * ADDENDUM 08/ 07/ 2019
1.2 PRICING OF CONTRACTOR-FURNISHSD AND INSTALLED PRQPERTY AND GOVERNMENT
FURNISHED CONTRACTOR-INSTALLED PROPERTY
The contractor shall promptly furnish and shall cause any sub-contractor or supplier to furnish, in like manner, unit prices and descriptive data required by the Government for Property Record purposes of fixtures, and equipment furnished and/or installed by the contractor or subcontractor, except prices do not need to be provided for Government-furnished Property.
This information shall be listed in the RMS CQC Module furnished by the Government.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 CONTRACT COST BREAKDOWN
The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.
-- End of Section --
SECTION 01 22 00.00 10 Page 2
| 01 22 00.00 10 - PRICE AND PAYMENT PROCEDURES |
| PART 1 GENERAL |
| 1.1 SINGLE JOB PAYMENT ITEMS |
| 1.1.1 Wetlands Mitigation Credits |
| 1.1.1.1 Payment |
| 1.1.1.2 Measurement |
| 1.1.1.3 Unit of Measure |
| 1.1.2 Riparian Zone Mitigation Credits |
| 1.1.2.1 Payment |
| 1.1.2.2 Measurement |
| 1.1.2.3 Unit of Measure |
1.2 PRICING OF CONTRACTOR-FURNISHSD AND INSTALLED PRQPERTY AND GOVERNMENT
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.1 CONTRACT COST BREAKDOWN |