Specifications-am-0003.pdf
PDF 13 MB Posted
- Solicitation number
- W9128A21R0004
About this file
This announcement constitutes a solicitation for a construction contract. The U.S. Army Corps of Engineers, Honolulu District is seeking proposals for Project Number 76897 to construct an aircraft maintenance hangar at Wheeler Army Airfield in Oahu, Hawaii. The project scope involves building the hangar, associated maintenance shops and facilities, airfield infrastructure, and utilities with a budget between $50-100 million. Proposals are due through the SAM.gov system and will be evaluated based on experience, past performance, management plan, small business participation plan, and price. Award will be made to the best value proposal determined through a trade-off analysis. The contract is a fixed-price design-build agreement for facilities intended to serve a minimum 40-year lifespan in accordance with DoD standards.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY21 PN76897 AIRCRAFT MAINTENANCE HANGAR PN76897
1.4 ENVIRONMENTAL PROTECTION REQUIREMENTS
Provide and maintain, during the life of the contract, environmental protection as defined. Plan for and provide environmental protective measures to control pollution that develops during construction practice.
Plan for and provide environmental protective measures required to correct conditions that develop during the construction of permanent or temporary environmental features associated with the project. Protect the environmental resources within the project boundaries and those affected outside the limits of permanent work during the entire duration of this Contract. Comply with federal, state, and local regulations pertaining to the environment, including water, air, solid waste, hazardous waste and substances, oily substances, and noise pollution.
Tests and procedures assessing whether construction operations comply with Applicable Environmental Laws may be required. Analytical work must be performed by qualified laboratories; and where required by law, the laboratories must be certified.
1.4.1 Conformance with the Environmental Management System
Perform work under this contract consistent with the policy and objectives identified in the installation's Environmental Management System (EMS).
Perform work in a manner that conforms to objectives and targets of the environmental programs and operational controls identified by the EMS.
Support Government personnel when environmental compliance and EMS audits are conducted by escorting auditors at the Project site, answering questions, and providing proof of records being maintained. Provide monitoring and measurement information as necessary to address environmental performance relative to environmental, energy, and transportation management goals. In the event an EMS nonconformance or environmental noncompliance associated with the contracted services, tasks, or actions occurs, take corrective and preventative actions. In addition, employees must be aware of their roles and responsibilities under the installation EMS and of how these EMS roles and responsibilities affect work performed under the contract.
Coordinate with the installation's EMS coordinator to identify training needs associated with environmental aspects and the EMS, and arrange training or take other action to meet these needs. Provide training documentation to the Contracting Officer. The Installation Environmental Office will retain associated environmental compliance records. Make EMS Awareness training completion certificates available to Government auditors during EMS audits and include the certificates in the Employee Training Records. See paragraph EMPLOYEE TRAINING RECORDS.
1.5 SPECIAL ENVIRONMENTAL REQUIREMENTS
Comply with the special environmental requirements listed here and attached at the end of this section. The Record of Environmental Consideration (REC) for this project is attached for reference.
1.6 QUALITY ASSURANCE
1.6.1 Preconstruction Survey and Protection of Features
This paragraph supplements the Contract Clause PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS. Prior to start of any onsite construction activities, perform a Preconstruction
SECTION 01 57 19 Page 13 (Am-0003)
DIRECTORATE OF PUBLIC WORKS
ENVIRONMENTAL DIVISION (IMHW-PWE)
BLDG. 105, WHEELER ARMY AIRFIELD
U.S. ARMY GARRISON, HAWAII
SCHOFIELD BARRACKS, HI 96857-5013
PHONE: (808) 656-2878, FAX: (808) 656-1039
Memo To:
From:
Date:
REC #:
FEWR #:
Re:
DPW
Environmental Division
Attached is the completed REC for the subject project. Please note compliance with the REC is contingent upon compliance with the comments from the below mentioned programs. Comments can be found in the Review and Concurrences section (page 6) or at the end of the REC form.
Failure to comply with these requirements may result in fines, penalties, and supplemental environmental project costs, which will be paid by the organization against which the fine or penalty has been assessed, using applicable Army appropriations unless otherwise required by law. Payments of fines and penalties will be charged to the funding account of the operation causing the violation. Contracting Officers will ensure that contracts require contractors to pay fines or penalties resulting from their operations (Army Regulation 200-1, Chapter 15-1, d.)
Please read this document and indicate your acceptance of the conditions by signing below and returning a copy to DPW Environmental.
The undersigned has read this REC and agrees to incorporate the listed environmental protective measures into the planning and execution of this project.
Proponent Signature X____________________________________________ Date _____________________
If additional guidance is needed to meet these requirements, please contact the following personnel.
Section 01 57 19 Attachment Page 1
RECORD OF ENVIRONMENTAL CONSIDERATION
IMHW-PWE NEPA Office
REC #:
DPW Form 1, Mar 17, Record of Environmental Consideration (REC) This form is prescribed for use in DPW SOP IMHW-PWE No. 202 (DATE) Enclosure 1, Page 1 of 4
1. DATE: 11 Mar 2019
2. SUBMITTED BY THE PROPONENT:
Ryan Arne
DPW, Planning Division (Name, Organization) 808-656-1373 (o) 808-864-3877 (c)
(Phone Number) /s Ryan Arne/
(Signature)
3. DESCRIPTION OF PROPOSED ACTION:
Construct a modified standard design Aviation Maintenance Hangar for rotary wing aircraft. Work includes an aircraft hangar; associated maintenance shops; administrative space; parts and tool storage; a hazardous materials storage facility; petroleum, oil and lubricants(POL) storage building; Ground Support Equipment (GSE) enclosed storage building; Associated Support Items of Equipment (ASIOE) covered storage; hangar access apron; aircraft washing apron; aircraft wash access apron; airfield fire pump building; redundant power generator; cyber security; information systems; fire protection and alarm systems; Intrusion Detection System (IDS) installation; and Utility Monitoring Control Systems.
The 35% Design Drawings and Design Analysis were submitted to DPW stakeholders including DPW Environmental Division. 35% On Board Review was completed on 04 March 2019.
4. ESTIMATED START DATE & DURATION OF PROPOSED ACTION: October 2020
5. THIS ACTION HAS BEEN COORDINATED WITH THE FOLLOWING OFFICES/AGENCIES:
Office/Agency Name Concur/Non-Concur
Garrison Commander COL Stephen E. Dawson Concur Installation Commander MG Ronald P. Clark Concur
REC CHECKLIST
(Check before submitting)
X Detailed Project Description
X Location Map and Plans
X Date of Proposed Action
� Reason for Categorical Exclusion
X Impact Analysis Checklist
X
Section 01 57 19 Attachment Page 2
DPW Form 1, Mar 17, Record of Environmental Consideration (REC) Enclosure 1, Page 2 of 4 Pages
ENVIRONMENTAL IMPACT ANALYSIS (Any “YES” or “MAY” answers need to be explained in the “Discussion” section at the end of this checklist.) YES NO MAY
1. AIR QUALITY
a. Will the proposal cause air emissions such as smoke, dust, suspended particles, or air pollutants during construction or operations?
b. Will the proposal involve the removal, modification, or addition of an air emitting device (e.g., boilers, generators, or degreasers)?
2. WATER QUALITY
a. Is there potential for accidental spills of hazardous or toxic substances?
3. TOPOGRAPHY AND SOILS
a. Will there be any ground disturbance (e.g., excavating, coring, or fence installation?) Please specify acreage below in “Discussion.”
4. NATURAL RESOURCES
a. Will the proposal affect undeveloped areas, affect endangered or threatened species or their habitat, occur in areas with known invasive species infestations, or affect plant or animal critical habitat?
b. Will the proposal require removal or trimming of trees? Please provide map of tree location below in “Discussion.”
c. Does the project involve soil importing/exporting?
5. ARCHAEOLOGICAL/HISTORIC RESOURCES
a. Will the proposal alter or destroy any archeological sites, landscapes, or buildings that are over 50 years old?
6. LAND USE
a. Will the proposal result in a change in operations, activities, or land use occurring at the site or facility?
7. NOISE ENVIRONMENT
a. Will there be any changes to the numbers, types, and operations of aircraft, vehicles, or weapon systems that could affect noise levels?
8. TRAFFIC
a. Will the proposal generate or increase vehicular traffic?
b. Will there be a requirement to construct, reroute or alter roadways?
Section 01 57 19 Attachment Page 3
DPW Form 1, Mar 17, Record of Environmental Consideration (REC) Enclosure 1, Page 3 of 4
ENVIRONMENTAL IMPACT ANALYSIS (Any “YES” or “MAY” answers need to be explained in the “Discussion” section at the end of this checklist.) YES NO MAY
9. HAZARDOUS MATERIALS/WASTE OR TOXIC SUBSTANCES
a. Will the proposal result in the disturbance of lead-based paint or asbestos- containing material?
b. Will the proposal result in the use, storage, or disposal of hazardous materials?
c. Will the proposal involve pesticide application (e.g., herbicide or insecticide)?
10. UTILITIES SYSTEMS
a. Will the proposal require disposal or alterations to existing utility systems or drainage systems (e.g., power, drinking water, waste water, storm water)? Please specify type of utility affected in “Discussion.”
DISCUSSION (Annotate items answered “YES” or “MAY” and provide a brief explanation of the potential impacts and mitigation measures to be implemented. Provide answers to the questions of how much, whom, where, when, and how? Contact the DPW Environmental Division at 656-3075 if assistance is needed.)
1.a. Project involves construction of 81,000 sf aircraft maintenance hangar which will involve heavy equipment operation. These activities are expected to emit smoke and dust as equipment moves dirt and concrete is produced and placed for the building foundation. Heavy lift cranes will be used to swing in place a steel frame.
1.b. There may be power generation equipment utilized during construction.
2.a. There may be accidental spills of POL at the construction site from POL leaks of heavy equipment.
3.a. There will be cut and fill excavation on site disposal for the building foundation, hangar access apron and wash apron. The soil is expected to be moved within the site or to another future hangar site nearby.
4.c. See 3.a.
6.a. Site will change from an open grassy field to an aircraft maintenance hangar for 30 UH-60 Blackhawk helicopters.
7.a. Helicopter noise will move from the north apron to the new south apron after the 30 Blackhawks move.
10.a. Project will include tie ins to the existing water, waste water, storm and electrical systems on post.
Section 01 57 19 Attachment Page 4
(See 32 CFR Part 651, Environmental Analysis of Army Actions)
(For Environmental Division use)
Concurrence is contingent upon compliance with comments provided.
4-Sep-2020
X
Section 01 57 19 Attachment Page 5
DPW Environmental Program
The following programs have comments:
Section 01 57 19 Attachment Page 6
Clean Water Program Comments:
REC #: (4533) WAAF, Construct Aviation Maintenance Hangar Reviewed by: Melissa Evans-Shontofski DATE: 1 April 2019
Spill response kits MUST be available for use ON-SITE during ALL periods of activity when a potential exists for fuel, oil, or chemical release (leak/spill). Workers on-site must be knowledgeable concerning spill response procedures. Please report all spills to the DPW Environmental Spill Reporting Hotline at 808-656-1111 during business hours or 808-656- 3272 for after hours.
Implement sediment and erosion control BMPs consistent with the City and County of Honolulu's Best Management Practices Manual for Construction Sites in Honolulu throughout the duration of construction activities to minimize soil runoff from the project site and prevent sediment from entering the storm sewer system. Implement sediment and erosion construction BMP control measures for any excavation, trenching and grading activity.
The construction staging and material storage areas shall not be located close to excavated areas and the contractor shall keep the construction staging area clean at all times and store only items needed for construction at the time.
At the end of each day, the project site shall be checked by the contractor to confirm that no construction materials remain exposed to the environment; all equipment and tools are located in the proper place; and all excavated rock, excess soil from grading, and construction waste are swept and transferred to the Stockpile area where appropriate control measures are provided.
Contractor MUST control vehicle track-out to paved roadways.
Project involves painting. Please ensure that any storm drains are protected from any potential paint spills.
No construction shall be performed during heavy rainstorms.
The project will include installation of new water lines. Hydrotesting of this waterline will require a NPDES Form F Application for HAR, Ch 11-55, NPDES Individual Permit Authorizing Discharges of Hydrotesting Waters. A Hydrotesting Best Management Practices (BMPs) Plan shall be included.
This project will disturb more than one acre and will require NPDES permit coverage (i.e., with Form C or NOI Form C from the Department of Health). Please refer to the attached Construction Site Runoff Control (CSRC) Program policy (https://home.army.mil/hawaii/application/files/9015/4992/9927/Construction_Site_Runoff_Co ntrol_Enforcement_Program20_Jan_17.pdf).
• The Storm Water Pollution Prevention Plan (SWPPP) and permit application must be submitted to DPW ENV Clean Water for review and issuance of a Letter of Authorization, as a requirement of USAG-HI’s MS4 permit. Training slides will have to be viewed by applicable staff to complete the SWPPP submission. DPW Environmental staff will be required to perform inspections in accordance to the CSRC Program. BMPs shall be used in accordance with the SWPPP. Compliance with the requirements of the USAG-HI’s Municipal Separate Storm Sewer System permit (HIS000090) is required at all times during the project.
Section 01 57 19 Attachment Page 7
• The contractor shall be responsible for conformance with the applicable provisions of the water quality and water pollution control standards contained in the Hawaii Administrative Rules, Title 11, Chapter 54, "Water Quality Standards" And Title 11, Chapter 55, "Water Pollution Control". Best Management Practices shall be employed at all times during the construction period, and shall include appropriate provisions for the mentioned concrete batch plant. Please note that The State of Hawaii Department of Health has listed Waikele Stream, which runs through Wheeler as an impaired water and is currently developing Total Maximum Daily Loads (TMDLs). Construction permits may be impacted by requirements of the TMDL compliance
Adherence to DoD Policy/Army policy regarding Low Impact Development to fulfill Energy Independence and Security Act Section 438 requirements is required for federal facilities introducing 5,000 square feet or more of new impervious surface. Follow 2017 (or successive) Army guidance regarding LID implementation: https://mrsi.erdc.dren.mil/sustain/cx/lid/.
Any and all low impact development features shall come with designer’s recommendations for operation and maintenance or an operation and maintenance manual.
The as-builts shall include information on the storm drainage system, to include any low impact development features installed.
Please contact a member of the Clean Water Program Team if you have questions or concerns: Melissa: Melissa.l.evans-shontofski.civ@mail.mil- 808-656-7001 Tirzah: tirzah.y.glebes.civ@mail.mil - (808) 656-3086
(Am-0003)
Section 01 57 19 Attachment Page 8 https://mrsi.erdc.dren.mil/sustain/cx/lid/ mailto:Melissa.l.evans-shontofski.civ@mail.mil-mailto:tirzah.y.glebes.civ@mail.mil
CLEAN AIR/SAFE DRINKING WATER PROGRAM COMMENTS
Date: 4/1/2019
WAAF, Construct Aviation Maintenance Hangar
1. Take reasonable precautions to minimize fugitive dust generated from construction activities. Please see Hawaii Administrative Rules 11-60.1-33, “Fugitive Dust” for a description of reasonable precautions: http://health.hawaii.gov/cab/files/2014/07/HAR_11-60_1-typed.pdf.
2. All connections to the drinking water system must have prior approval and coordination with DPW
OMD Facilities Branch. Please use attached DPW Memorandum for Cross-Connection and Backflow Control for guidance:
-Section 5c. pertains to New Construction and Renovation projects -Section 7 pertains to Backflow Prevention installation -Section 8 pertains to new hose bibbs -Section 9 pertains to Fire Suppression Systems -Sections 10 and 11 pertain to irrigation and temporary connections
3. Please make sure that all new drinking water pipes, fittings, and fixtures installed meet the EPA new
"lead-free" standard. See EPA flyer “How To Identify Lead Free Certification Marks for Drinking Water System and Plumbing Products” http://nepis.epa.gov/Exe/ZyPDF.cgi?Dockey=P100LVYK.txt
4. All portable diesel-fired emergency generator engines that stays in one location for more than 12 months are subject to the following EPA Clean Air Act regulations:
a. The generator must be installed, operated, and maintained according to the manufacturer’s instructions.
b. A non-resettable hour meter must be installed. The hours of operation must be recorded.
Records must differentiate between maintenance/testing hours and actual emergency use hours.
Please direct any requested information and questions to:
Kim DeCaprio, kimberly.c.decaprio.civ@mail.mil, 656-3107 Aleu’i Lyman, aleuikaimaikalani.a.lyman.ctr@mail.mil, 656-3104
Section 01 57 19 Attachment Page 9
Record of Environmental Consideration for Construct Aviation Maintenance Hangar, Wheeler Army Airfield
Recycling Program Comments (POC: Dale Kanehisa, 656-5411 or dale.t.kanehisa.civ@mail.mil):
Army goal is to achieve at least 60% of construction and demolition material recycling. The project planning shall incorporate recycling and reuse measures to reduce the amount of construction and demolition waste requiring landfill disposal or incineration. This includes cardboard, scrap metal, concrete, asphalt, excess soil and greenwaste, which should be taken to an appropriate recycling or reuse facility. The Design Specifications will need to include a requirement for the contractor to provide a report on a quarterly basis detailing the amount (weight) of construction and demolition debris recycled/salvaged/reused, and the amount of waste disposed (at a landfill or waste-to-energy facility). A sample report form is attached. The report along with corresponding weight receipts will need to be submitted to the DPW Environmental Recycling Program. Point of contact for submittal of the report is included at the top of the form.
Section 01 57 19 Attachment Page 10
Email this form and corresponding weight receipts to: whitney.m.brunson.ctr@mail.mil Revised 8/1/2013 ATTN: Solid Waste/Recycling Program, DPW Environmental
Project Title:
Project #:
Asphalt Concrete Dirt Metals Wood Waste Green Waste Corrugated Cardboard Deconstruction Total % Diversion:
Other: ________________ (a+c)/(a+b+c) x 100 Total (tons)
1. Were deconstruction options considered for this project as outlined in PWTB 200-1-23? YES / NO If not, please provide justification:
2. Was 50% of the material diverted from the landfill per EO 13514 and Army Regulation 420-1? YES / NO If not, please provide justification:
Name of company: Contact Phone #:
Person completing form: Signature:
Period covered: From: To:
Type of Material Name of Disposal Facility (a) Recycled (tons)
(b) Class III Landfill Disposal (tons)
(c) Reused (tons)
Summary of Solid Waste Disposal and Diversion Negative Response Required
(Am-0003)
Section 01 57 19 Attachment Page 11 dale.kanehisa Text Box dale.t.kanehisa.civ@mail.mil
Record of Environmental Consideration for WAAF, Construct Aviation Maintenance Hangar
SPCC Comments (POC: Fritz Miller, 656-3106, or frederick.j.miller42.civ@mail.mil)
Ensure all new oil storage tanks and fuel tanks are compliant with the Environmental Protection Agency’s Spill Prevention Controls and Countermeasures (SPCC) regulation found in 40 CFR
112. This includes, but is not limited to, secondary containment, overfill protection devices, and primary and emergency venting. USAG-HI SPCC Plan Appendix F, Design Construction and Installation Requirements for Factory/Shop Fabricated Aboveground Storage Tanks provides details of all fuel/oil tank requirements.
Consider constructing a permanent fuel truck/modular fuel system parking area to provide the secondary containment required by EPA regulations. The containment would need to hold 110% of largest tank (3300 gal) in the storage area. The containment would require a manually operated drain valve to release water after it is inspected to ensure there is no fuel.
Section 01 57 19 Attachment Page 12
USAG-HI SPCCP
APPENDIX F
Design, Construction and Installation Requirements for Factory/Shop Fabricated Aboveground Storage Tanks
[40 CFR 112.8(b), 40 CFR 112.8(c), 40 CFR 112.12(b), 40 CFR 112.12(c); SPCCP Paragraph 4.2]
Section 01 57 19 Attachment Page 13
Table of Contents
1.0. Introduction
2.0. Regulatory Drivers
3.0. Definitions
4.0. Approval Process
5.0. General AST Construction Requirements
6.0. Tank Location
7.0. Security
8.0. Tank Containment
9.0. Tank Foundation and Support
10.0. Leak Detection
11.0. Liquid Level Equipment
12.0. Overfill Protection Device (Spill Bucket)
13.0. Venting Requirements
14.0. Corrosion Prevention
15.0. Aboveground Fuel Lines
16.0. Bonding and Grounding
17.0. Testing Requirements for Tanks and Piping
18.0. Identification and Markings
19.0. Generator Base Tanks
20.0. Tanks Inside Buildings
21.0. Auxiliary Fuel Tanks Installed on Truck Beds
22.0. Field Erected Storage Tanks
Section 01 57 19 Attachment Page 14 http://www.garrison.hawaii.army.mil/sustainability/SpillPreventionResponse.aspx
1.0. Introduction.
1.1. Aboveground Storage Tanks (ASTs) are subject to the Spill Prevention, Control and
Countermeasure (SPCC) regulations codified in Title 40 of the Code of Federal Regulations (CFR)
Part 112 and the U.S. Army Garrison-Hawaii (USAG-HI) SPCC Plan.
1.2. Compliance with the AST design, construction and installation requirements described in this document is mandatory and an integral part of USAG-HI’s SPCC Plan signed by the Garrison
Commander. Any deviations must be approved by the Director of Public Works (DPW).
1.3. AST inspections, maintenance, recordkeeping, training and spill reporting requirements for installed tank systems are described in the USAG-HI SPCC Plan available at:
https://www.garrison.hawaii.army.mil/sustainability/SpillPreventionResponse.aspx
2.0. Regulatory Drivers.
USAG-HI’s design, construction and installation requirements for factory-fabricated fuel storage tanks incorporates the following regulatory drivers:
USAG-HI SPCC Plan
29 CFR 1910.106 – Flammable Liquids
40 CFR 112.8 – Oil Pollution Prevention
National Fire Protection Association (NFPA) 30 – Flammable and Combustible Liquids
Code, 2015 Edition
NFPA 37 – Standard for the Installation and Use of Stationary Combustion Engines and Gas
Turbines
NFPA 70 - National Electric Code
NFPA 110 - Standard for Emergency and Standby Power Systems
International Fire Code (IFC) – Flammable and Combustible Liquid
Steel Tank Institute (STI) SP001 standard - 5th Edition, September 2011
Department of Defense (DoD) standard designs; AW 78-24-27 - Standard Fueling Systems;
Aboveground Vertical Fuel Tanks with Floating Pan and Fixed Roofs
Unified Facility Criteria (UFC) 3-460-01; Design: Petroleum Fuels Facilities
UFC 3-460-03, Operation and Maintenance: Maintenance of Petroleum Systems
UFGS 13202A, Fuel Storage Systems
40 CFR 280 – Technical Standards and Corrective Action Requirements for Owners and
Operators of Underground Storage Tanks (UST)
Hawaii Administrative Rules (HAR) Title 11-281 - Underground Storage Tanks
3.0. Definitions.
3.1. Aboveground Storage Tank (AST). A tank or container designed to operate at pressures ranging from atmospheric pressure through a gauge pressure of one psig measured at the top of the tank. The tank may be sitting on the ground or set on supports, such as saddles, skids or legs, etc., and
(Am-0003)
Section 01 57 19 Attachment Page 15 https://www.garrison.hawaii.army.mil/sustainability/SpillPreventionResponse.aspx may be installed in a vault. Included are shop- abricated tanks, field-erected tanks, and portable containers with a capacity of 55 U.S. gallons (208 liters) or greater. [Ref.: STI SP001]
3.2. Anti-siphon valve. A device to prevent any siphoning due to damaged fuel lines, broken pumps, leaky or leaking fuel pumps. This device is not a check valve. [Ref.: STI SP001]
3.3. Continuous Release Detection Method (CRDM) – A means of detecting a release of liquid through inherent design. CRDM is passive because it does not require sensors or power to operate.
Liquid releases are visually detected by facility operators. The system shall be designed in accordance with good engineering practice. Several acceptable and commonly used CRDM systems are as follows:
• Release prevention barrier (RPB) (described in definition of release prevention barrier).
• Secondary containment AST, including double-wall AST or double-bottom AST.
• Elevated AST, with or without release prevention barrier. [Ref.: STI SP001]
3.4. Factory/Shop-fabricated AST - Is a welded metal AST fabricated in a manufacturing facility, or an AST not otherwise identified as field-erected, with a volume less than or equal to 50,000 U.S.
gallons (189,271 liters). [Ref.: STI SP001]
3.5. Double Wall AST (Secondary Containment Tank). A tank that has an inner and outer wall with an interstitial space (annulus) between the walls and that has a means for monitoring the interstitial space for a leak. The tank may also be constructed with an integral secondary containment dike such as pans, boxes or containers designed to contain the contents of the primary tank if the primary tank fails. A secondary containment AST may be open or closed to the atmosphere. If precipitation cannot readily enter the integral secondary containment, then the containment need only be sized for the primary tank volume. If precipitation can enter the secondary containment, then the secondary containment is sized to contain the primary tank volume and with sufficient freeboard to contain precipitation. [Ref.: 40 CFR 112.8(c)(2); 2015 NFPA 30.3.3.51.5; STI SP001]
3.6. Leak Gauge. A leak gauge is designed for use on AST’s that have a double wall containment.
The gauge top mounts to a monitoring pipe or over the top of the interstitial space, it is designed to monitor the bottom of that space and visually alert the owner/operator of any liquid that may get into the secondary containment. A standard float type gauge is acceptable. [Ref.: STI SP001]
3.7. Liquid Level Gauge. A device that is easily readable that automatically indicates the actual fuel level in the AST. A standard float type gauge is acceptable. [Ref.: STI SP001]
3.8. Overfill Protection Device (Spill Bucket). Systems, procedures, or devices used to prevent liquid in ASTs from running over or spilling out of the AST during the filling process. A person who is physically present and in control of a shutoff device during the entire tank filling process is an acceptable procedure to achieve overfill protection. For USTs, spill buckets shall have a 5-gallon minimum storage capacity and shall be double wall construction. [Ref.: 40 CFR 112.8(c)(8)(i-v); 40
CFR 280.30; HAR 11-281; STI SP001]
Section 01 57 19 Attachment Page 16
3.9. Release Prevention Barrier (RPB) – A liquid containment barrier that is installed under the
AST. Its purpose is to divert leaks toward the perimeter of the AST where they can be easily detected, as well as to prevent liquid from contaminating the environment. RPBs are composed of materials compatible with the liquid stored in the AST and meet appropriate engineering standards.
Examples are steel (as in steel doublebottom tanks), concrete, elastomeric liners or other suitable materials, provided the above criteria are met. [Ref.: STI SP001]
3.10. Vents.
3.10.1. Emergency Relief Vent. An opening, construction method, or device that will automatically relieve excessive internal pressure due to an exposure fire. [Ref.: 2015 NFPA 30.3.3.60.1]
3.10.2. Normal (Primary) Vent. An opening, construction method, or device that allows the relief of excessive internal pressure or vacuum during normal storage and operations. As a minimum size, all normal vents shall be at least 1-¼ inches in inside diameter. It must have a bug proof, rain cap secured on top of the vent. The vent must be at least 3 feet higher than the highest point within a 10-foot radius of the ATS. [Ref.: 2015 NFPA 30.3.3.60.2; STI SP001]
4.0. Approval Process.
4.1. Underground Storage Tanks (USTs) and stationary Aboveground Storage Tanks (ASTs) shall not be installed on USAG-HI and its sub-installations without prior approval from the DPW.
4.2. Proponents of new constructions, repair or replacement of stationary storage tank projects must submit a Facilities Engineering Work Request (FEWR) to the DPW and a Record of Environmental
Consideration (REC), IMPC-HI-PW Form 29, Jul 07, to the DPW Environmental Division (ED) for review and approval before execution of the project. All designs, installations, replacements, upgrades and repairs of aboveground and underground storage tanks, their associated piping and monitoring equipment must be reviewed and approved by the DPW-ED as part of the REC process.
4.3. A copy of the tank system design and as built drawings must be provided to the DPW-ED for record keeping in accordance with 40 CFR 112.8 and the STI SP001 standard.
4.4. USAG-HI requires, whenever feasible, that preference to install elevated, double wall ASTs equipped with Continuous Release Detection Method (CRDM) instead of USTs be given in all new tank installations. While the short-term cost may be higher, the long-term total cost of ownership of
ASTs compared to USTs is typically much lower due to fewer incidents, environmental cleanups and regulatory citations. Furthermore, when comparing inspection requirements for underground tanks to aboveground tanks, the visual inspection of elevated ASTs is considerably simpler and less costly than conducting the tests required on USTs.
4.5. In accordance with Army Regulation (AR) 200-1, USAG-HI does not allow the installation of
USTs for the purpose of storing used oil. If permitted by the DPW for new POL products, USTs shall be double-walled steel fiberglass reinforced with interstitial monitoring and automatic tank gauging and cathodically protected. [Ref.: 40 CFR 280; HAR 281]
(Am-0003)
Section 01 57 19 Attachment Page 17
4.6. Used POL stored in ASTs must meet the requirements of this document plus additional applicable requirements of the Resource Conservation and Recovery Act (RCRA) regulation for used oil management and storage as codified in 40 CFR 279.22.
5.0. General AST Construction Requirements.
5.1. Aboveground petroleum fuel tanks shall conform to all Federal, State, Local regulations and guidelines, and with the requirements described in this document. This includes indoors and outdoors tanks for permanent placement as part of new construction, as replacement of existing storage tank systems, day tanks and base fuel tank on emergency standby generators, and tanks used for temporary storage by construction contractors and military units.
5.2. ASTs, including generator base tanks, must be made of steel and Underwriters Laboratories
(UL) listed. Acceptable UL standards for flammable liquids in ASTs are: UL 142, Standard for Steel
Aboveground Tanks for Flammable and Combustible Liquids; UL 2080 Standard for Fire Resistant
Tanks for Flammable and Combustible Liquids; or UL 2085, Standard for Protected Aboveground
Tanks for Flammable and Combustible. [Ref.: 2015 NFPA 30.21.4.2.1.1; 29 CFR
1910.106(b)(1)(i)(a); STI SP001]
5.3. Each major component of the tank system shall have a nameplate secured or stamped to the equipment with the manufacturer's name, type or style, model or serial number, storage capacity, and rating number. As a minimum, nameplates shall be provided for the storage tank, including the base tank of generators and emergency venting devices.
5.4. ASTs must be cylindrical horizontal, whenever possible, to prevent rainwater from pooling on top of the tank or must be covered or installed with rainshields, especially if a rectangular style tank is to be installed, or the tank roof shall be sloped to prevent standing water in low points to minimize corrosion. [Ref.: 40 CFR 112.8(d)(4); 2015 NFPA 30.21.6.1.2; 29 CFR
1910.106(b)(1)(iii)(a); STI SP001 Para 7.4.3, Annual checklist 4.3; STI SP001 Appendix A Para
2.3.1.4]
5.5. ASTs shall be so installed that the bottom outside surface of the tank is at least 12 inches above ground level to provide visual inspection capabilities and meet the STI SP001 standard Category 1 tank inspection requirements. ASTs may be installed on saddles or support legs directly on concrete foundations, or it may be supported by properly designed metallic structural supports as appropriate.
Tank supports must be designed to minimize abrasion and corrosion and allow for expansion and contraction. [Ref.: 40 CFR 112.8(d)(3); 2015 NFPA 3022.5.2.1; STI SP001]
5.6. Tank supports greater than 12" high shall be constructed with material rated with a 2 hours fire resistance. [Ref.: 40 CFR 112.8(c)(8); 2015 NFPA 30.22.5.2.4; 29 CFR 1910.106(b)(5)(ii); STI
SP001 Para 2]
5.7. Tank openings must be liquidtight, sealed and closed with steel caps and fittings. Low melting point materials including but not limited to aluminum, copper, or brass, plastics or
(Am-0003)
Section 01 57 19 Attachment Page 18 nonductile materials, such as cast iron, shall not be used. [Ref.: 2015 NFPA 30.21.8.4, 2015
NFPA 30.21.8.7, 2015 NFPA 30.27.2.4; 2015 NFPA 30.27.3.2, 2015 NFPA 30.27.4.3, 2015
NFPA 30.27.4.4.2, 2015 NFPA 30.27.5.1.3, 29 CFR 1910.106(b)(4)(iv)(a)]
5.8. An approved means shall be provided to notify the tank filling operator of the pending completion of the tank fill operation at the fill connection. [Ref.: 40 CFR 112.8(c)(8)(i)(ii)(iii);
2015 NFPA 30.21.7.1.6.1]
5.9. An approved means shall be provided to stop delivery of liquid to the tank prior to the complete filling of the tank. [Ref.: 40 CFR 112.8(c)(8)(i)(ii)(iii); 2015 NFPA 30.21.7.1.6.2]
6.0. Tank Location.
6.1. ASTs must be positioned to the nearest building in accordance with applicable NFPA Codes, Uniform Building Code (UBC) and all other applicable local codes and ordinances. The location of the tank must provide Fire Department vehicle access. [Ref.: 2015 NFPA 30.21.6.6.4; 2015 NFPA
30.22.4.1]
6.2. The minimum distance between any two ASTs shall be 3-feet. [Ref.: 2015 NFPA 30.22.4.2.1
Table]
6.3. The minimum distance between an AST with Gasoline or Diesel fuel and a Liquefied Petroleum
Gas (LPG) tank shall be 20-feet (6 m). [Ref.: 2015 NFPA 30.22.4.2.4]
7.0. Security.
7.1. Access to the storage tank shall be protected against tampering or trespassers where necessary.
[Ref.: 40 CFR 112.7(g); 29 CFR 1910.106(d)(6)(iv); 2015 NFPA 30.15.3.6; ]
7.2. Sufficient lighting shall be installed at the facility to prevent acts of vandalism and assist in the discovery of oil discharges. [Ref.: 40 CFR 112.7(g)]
7.3. ASTs and piping shall be protected from collision and impact damage on sides exposed to traffic. Protection against collision can be accomplished by either tank shell design or collision barriers such as steel pipe bollards or precast concrete barriers. [Ref.: 40 CFR 112.8(d)(5); 29 CFR
1910.106(g)(3)(iv)(d); 2015 NFPA 30.22.11.4.7; 2015 NFPA 30.22.15]
8.0. Tank Containment.
8.1. ASTs and their associated external piping aboveground or underground must be secondarily contained. Double wall construction is preferred. [Ref.: 40 CFR 112.8(b)(3); 40 CFR 112.8(c)(2);
40 CFR 112.8(d)(1); 2015 NFPA 30.22.11].
Section 01 57 19 Attachment Page 19
8.2. ASTs shall be double-walled type tanks unless a single wall tank installation is approved by the
DPW. While single wall storage tanks designed with an external sized secondary containment is acceptable under 40 CFR 112.8, preference to double wall tanks will be given, whenever possible, in order to reduce the potential for a catastrophic tank failure and to also reduce the long term maintenance cost of the tank and secondary containment structure. Corrosion damage to tanks in
Hawaii is dramatically accelerated and the tank life expectancy is significantly reduced due to the
Island’s tropical climate which includes a combination of humidity/rain and constant exposure to salt-laden air. While the upfront cost of double wall ASTs is higher, the long-term potential risks to the environment and cost of ownership is significantly reduced and therefore preferred.
8.3. In cases where a single wall tank construction is approved, USAG-HI requires that the external secondary containment/dike be impervious and capable of holding the entire content of the largest container plus an additional ten percent to allow for rain if precipitation can enter the secondary containment. Secondary containment can also serve as overfill spill protection for tank fill ports not equipped with a spill bucket. [Ref.: 40 CFR 112.8(c)(2)]
8.4 The containment drainage shall be equipped with traps or separator if it discharges into public waterways or if it is connected to the public sewers. [Ref.: 29 CFR 1910.106(e)(3)(iv)(b); 29 CFR
1910.106(f)(7); 2015 NFPA 30.9.13.1.1]
9.0. Tank Foundation and Support.
9.1. ASTs shall rest on the ground or on foundations made of concrete, masonry, piling, or steel.
Tank foundations shall be designed to minimize the possibility of uneven settling of the tank and to minimize corrosion in any part of the tank resting on the foundation. The bearing capacity of the foundation for the tank must be designed in accordance with the manufacturer’s recommendations and must be able to support the tank plus the weight of the maximum amount of product the tank will be storing. [Ref.: 2015 NFPA 30.22.5.2.1; 2015 NFPA 30.22.5.2.2]
9.2. The tank must be securely anchored with hold down restraints to resist natural disasters. [Ref.:
2015 NFPA 30 4.2.4.3; 2015 NFPA 30.19.7.3.2.2; 2015 NFPA 30.21.6.3(2); 2015 NFPA 30.22.5.1.3;
29 CFR 1910.106(b)(5)(vii); STI SP001 Para 1.6, Para 10.3]
9.3. The tank foundation design must include provisions for draining surface water away from the tank to minimize corrosion and the risk of fuel accumulation under the tank from an overfill or spill.
[Ref.: 2015 NFPA 30.15.3.5.1; 29 CFR 1910.106(d)(6)(iii)]
10.0. Leak Detection.
10.1 Double wall tanks and piping must be provided with means to detect leaks such as a direct vision leak gauge and/or leak sensor/alarm. Note: Elevated single wall ASTs do not require a release prevention barrier (in addition to secondary containment) to qualify as a Category 1 tank, as leaks from elevated tanks are visible. [Ref.: 40 CFR 112.8(c)(8); 2015 NFPA 30.22.11; STI SP001 Para
7.5.1, 7.5.2]
Section 01 57 19 Attachment Page 20
10.2 The length of the leak gauge sensor must be correctly sized based on the tank height and installed in a complete loop/circuit from the primary sensor to the final annunciation or alarm point. [Ref.: 40 CFR 112.8(c)(8)(i)-(v); STI SP001 Para. 7.1.9.3]
11.0. Liquid Level Equipment.
11.1. ASTs must be provided with means for determining the level of liquid in the tank to prevent overfilling the tank i.e. direct vision level gauge, overfill valve and/or overfill alarm. This method must be accessible to the delivery operator. [Ref.: 40 CFR 112.8(c)(8)(i)-(v); STI SP001 Appendix A
Para 1.2.1.4]
11.2. If the primary tank is equipped with a mechanical/visual level gauge, the liquid level gauge length must be correctly sized for the tank diameter. [Ref.: 40 CFR 112.8(c)(8)(i)-(v); STI SP001
Para. 7.1.9.3]
12.0. Overfill Protection Device (Spill Bucket).
12.1. Fill ports on tanks shall be equipped with spill protection to prevent liquid in ASTs from running over or spilling out of the AST during the filling process (i.e. spill bucket or within a containment system). [Ref.: 40 CFR 112.8(b)(3); 40 CFR 112.8(c)(8)(i-v); 40 CFR 280.30; HAR
11-281; 2015 NFPA 22.11; STI SP001]
13.0. Venting Requirements.
13.1. Atmospheric shop fabricated storage tanks shall be adequately vented to prevent the development of vacuum or pressure exceeding the design pressure due to filling or emptying and the atmospheric temperature changes. The interstitial space (annulus) of a double wall tank shall also be equipped with an emergency vent. [Ref.: 2015 NFPA 30.21.4.3.3; 2015 NFPA 30.22.7.1.1.1]
13.2. Single wall ASTs must have one normal atmospheric vent and one emergency vent or other acceptable form of construction or device that will relieve excessive internal pressure caused by exposure to fires. This requirement also applies to each compartment of a compartmented tank and tanks with closed top dike construction. Double wall ASTs must have an emergency vent for the interstitial space in addition to the normal and emergency vents required for the primary tank. [Ref.:
2015 NFPA 30.21.4.3.3.1 through 30.21.4.3.3.12; 2015 NFPA 30.22.7.1.1.1]
13.3. Emergency venting device for secondary containment (interstice) is not required on Convault tank per the manufacturer’s tank form of construction and design. Acceptable under 2015 NFPA
30.22.7.1.1. [Ref.: 2015 NFPA 30.21.4.3.4; 2015 NFPA 30.22.7.1.1.1]
13.4. Normal/primary vents shall be sized in accordance with either API Standard 2000, Venting
Atmospheric and Low-Pressure Storage Tanks, or another approved standard. Alternatively, the normal vent shall be at least as large as the largest filling or withdrawal connection, but in no case shall it be less than 1.25 in. (32 mm) nominal inside diameter. [Ref.: 2015 NFPA 30.21.4.3.3; STI
SP001 Storage Tank Venting Compendium]
(Am-0003)
Section 01 57 19 Attachment Page 21
13.5. If any tank or pressure vessel has more than one fill or withdrawal connection and simultaneous filling or withdrawal can be made, the vent size shall be based on the maximum anticipated simultaneous flow. [Ref.: 2015 NFPA 30.21.4.3.6]
13.6. Where vent pipe outlets are adjacent to building or public ways, they shall be located so that the vapors are released at a safe point outside of buildings and not less than 12 ft. above the adjacent ground level. In order to aid their dispersion, vapors shall be discharged upward or horizontally away from closely adjacent walls. Vent outlets shall be located so eaves will not trap the flammable vapors or other obstructions and shall be at least 5 ft. from building openings and at least 15 ft. (4.5 m) from powered ventilation air intake devices. [Ref.: 2015 NFPA 30.27.8.1.1 through NFPA 30.27.8.1.3]
13.7. Manifolding of vent piping shall be prohibited except where required for special purposes such as vapor recovery, vapor conservation, or air pollution control. [Ref.: 2015 NFPA 30.27.8.1.4]
14.0. Corrosion Prevention.
14.1. Tank and piping both aboveground and underground, where subject to external corrosion, must be painted or otherwise protected against corrosion. [Ref.: 2015 NFPA 27.6.4; 29 CFR
1910.106(c)(5)]
15.0. Aboveground Fuel Lines.
15.1 Double wall aboveground instead of underground fuel lines for use with AST systems shall be installed, whenever feasible, to minimize environmental risks and simplify compliance with the inspection and maintenance requirements.
15.2 All materials for piping, valves, or fittings shall be made of steel, nodular iron, or malleable iron. Galvanized piping shall not be used for diesel, kerosene and jet fuel. [Ref.: 2015 NFPA
30.27.4.3; 29 CFR 1910.106(c)(2)(i)]
15.3 Unless otherwise determined to not be practical, all piping connections to the tank shall be made above the normal maximum liquid level with fill lines sloped toward the tank. [Ref. :
2015 NFP 30.22.3.8, 2015 NFPA30.22.11.4.2; 29 CFR 1910.106(b)(3)(v)(c)]
15.4. Anti-siphon valve must be provided to prevent a release from the tank by siphon flow where the liquid level in the tank is higher than the elevation of the dispenser thereby producing gravity head on the dispending unit or any of the product piping. Such a valve must be positioned in the tank’s discharge pipe, downstream from the block valve that is located just outside the tank shell and so adjusted that liquid cannot flow by gravity from the tank in case of piping or hose failure. Anti-siphon valves must be designed to remain in a closed position, thus preventing the flow of liquid except when some positive action, such as turning on the pump, is taken. An anti-siphon valve may operate on the solenoid principle. Others are spring-loaded check valves. Both shall be designed to open only when the pump is operating. [40 CFR 112.8(d)(4); 2015 NFPA 30.22.13.1; 2015
(Am-0003)
Section 01 57 19 Attachment Page 22
22.11.4.3; 2015 NFPA 30.27.6.6.1; 2015 NFPA 30.27.6.6.2; 29 CFR 1910.106(g)(4)(ii)(d), STI
SP001]
15.5. All piping whether aboveground or underground shall be secondarily contained. [Ref.: 40
CFR 112.8(b)(3); 2015 NFPA 30.22.11.3.13]
15.6. Exception to underground piping secondary containment requirements shall apply for airport hydrant fuel distribution system. In accordance with 40 CFR 280, Subpart K - UST Systems with
Field-Constructed Tanks and Airport Hydrant Fuel Distribution Systems, the Hawaii Administrative
Rules (HAR) 11-281-01 and UFC 3-460-01, underground hydrant systems that meet the definition of an “Airport hydrant fuel distribution system” as per 40 CFR 280.50 are exempt from secondary containment requirements.
15.7. Non-metallic piping and flex-piping must be listed specifically for their intended use
(aboveground or underground). If approved by the DPW, buried piping must be double wall with leak detection, protectively wrapped and/or coated to prevent corrosion, cathodically protected and periodically tested, and UL 971 listed, Standard for Nonmetallic Underground Piping for Flammable
Liquids. [Ref.: 40 CFR 112.8(d)(1)(4); 2015 NFPA 23.3.5; 2015 NFPA 27.4.6.2; 2015 NFPA
27.6.4]
15.8. Pipe joints shall be made liquidtight and shall be welded, flanged, threaded, or mechanically attached. [Ref.: 2015 NFPA 27.5.1.1]
15.9. Threaded joints shall be made with a suitable non combustible thread sealant or lubricant.
[Ref.: 40 CFR 112.8(d)(4); 2015 NFPA 27.5.1.3]
15.10. Fill pipes that enter the top of a tank shall terminate within 6 in. (150 mm) of the bottom of the tank. Fill pipes shall be installed or arranged so that vibration is minimized. [Ref.: 2015 NFPA
21.4.4]
15.11. Aboveground fuel lines shall be installed a minimum of 6 inches off the ground to facilitate visual inspections and be supported every 3-feet with approved noncombustible support materials meeting industry and manufacturer standard. [Ref.: 2015 NFPA 27.6.1]
15.12. Aboveground piping shall be protected from collision and impact damage on sides exposed to traffic. [Ref.: 40 CFR 112.8(d)(5); 29 CFR 1910.106(g)(3)(iv)(d); 2015 NFPA 30.22.11.4.7; 2015
NFPA 30.22.15]
15.13. ASTs fill caps shall have an approved means of locking when not being refueled. [Ref.: 29
CFR 1910.106(b)(5)(vi)(t), 2015 NFPA 30.21.7.2.2; STI SP001]
16.0. Bonding and Grounding.
Section 01 57 19 Attachment Page 23
16.1. ASTs and piping must be properly bonded and grounded to prevent electrostatic ignition.
[Ref.: 2015 NFPA 30.6.5.4.2, 2015 NFPA 30.6.5.4.3, 2015 NFPA 30.27.9, NFPA 780 4.13; STI
SP001]
17.0. Testing Requirements for Tanks and Piping.
17.1 The tank system, interstitial space, piping and connections must be tightness tested before they are placed in service, and is some cases after repair, in accordance with the requirements of the code under which they were built. Testing requirements shall be stipulated in the design specifications of the construction project. [Ref.: 40 CFR 112.8(c)(6); 2015 NFPA 30.21.5.1]
18.0. Identification and Markings.
18.1. ASTs and associated piping must be marked in accordance with NFPA 704 requirements and the signage must be readily visible to emergency responders. [Ref.: 2015 NFPA 30.21.7.2.1; IFC
Section 3404.2.3.1; IFC Section 3404.2.3.2; 29 CFR 1910.106(f)(6)(g)(8)].
18.2 Fuel loading and unloading risers, supply and return lines shall be properly identified. [Ref.:
2015 NFPA 30.22.13.4.2, 2015 NFPA 30.27.10]
19.0. Generator Base Tanks.
19.1. Generator base tanks shall conform to the AST requirements described in paragraphs above in addition to NFPA 37 – Standard for the Installation and Use of Stationary Combustion Engines and Gas Turbines and NFPA 110 – Standard for Emergency and Standby Power Systems. [Ref.:
2018 NFPA 37.6.2.2; NFPA 37.6.3.3; 2016 NFPA 110.7.9.1.1;]
19.2. New non-tactical portable gensets must be purchased with a double wall fuel storage tank and a spill bucket installed at the fill point as applicable. Whenever feasible and allowed per MILSPEC standards, new tactical gensets must also be purchased with a double wall storage tank and a spill bucket installed at the fill point as applicable. [Ref.: 40 CFR 112.7(c); 40 CFR 112.8(c)(2); USAG-
HI SPCC Plan].
19.3. Fuel piping shall be of compatible metal to minimize electrolysis and shall be properly sized, with vent and fill pipes located to prevent entry of groundwater or rain into the tank. [Ref.:
2016 NFPA 110.7.9.3]
19.4. Galvanized fuel lines shall not be used. [Ref.: 2016 NFPA 110.7.9.3.1]
19.5. Approved flexible fuel lines shall be used between the prime power and the fuel piping.
[Ref.: 2016 NFPA 110.7.9.3.2]
19.6. A minimum clearance of 0.9m (36 in.) shall be maintained on all sides of the generator fuel base tank. [Ref.: 2016 NFPA 110.7.9.12.1]
Section 01 57 19 Attachment Page 24
19.7. Automatically actuated valves shall not be permitted in the fuel oil supply or fuel oil return lines. [Ref.: 2016 NFPA 110.7.9.13]
19.8. Alarms, float-controlled valves, or mechanical or remote-reading level gauges or protected sight glass gauges shall be installed to aid personnel in properly operating the fuel system. [Ref.:
2018 NFPA 37.6.5.2]