ISS 15R0001 USAYPG - Technical Exhibit 7 - Electrical Substations.docx

DOCX document 34 KB Posted

Attached to
Installation Support Services for Yuma Proving Ground, AZ Federal contract opportunity
Solicitation number
W9124R-15-R-0001
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Joint Base Lewis-McChord

About this file

TE 7

View the file

Other files for this federal contract opportunity

Other files attached to Installation Support Services for Yuma Proving Ground, AZ, newest first.
File Type Posted
W9124R-15-R-0001-0005_conformed.pdf PDF
W9124R-15-R-0001-0005.pdf PDF
Attachment_1_PWS_15R0001_YPG-ISS_-_5-19-17_v7L.pdf PDF
W9124R-15-R-0001-0004.pdf PDF
Attachment_1_PWS_15R0001_YPG-ISS_-_5-18-17_v5L.pdf PDF
Attachment_1_PWS_15R0001_YPG-ISS_-_5-9-17_v6L.pdf PDF
revised_Technical_Exhibit_3_-_Performance_Requirements_Summary_-_20170504.pdf PDF
W9124R-15-R-0001-0003.pdf PDF
Response_to_Vendor_Questions__8_5-10-17_.pdf PDF
Response_to_Vendor_Questions__7_5-4-17_.pdf PDF
Attachment_1_PWS_15R0001_YPG-ISS_-_4-27-17_v1L.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_1_-_Real_Property_Inventory_-_20170426.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_2_-_Workload_History_-_20170426.docx DOCX document
Attach__6_YPG_CBA_2015_2020.pdf PDF
Response_to_Vendor_Questions__4_posted_4-25-17.docx DOCX document
Response_to_Vendor_Questions__3-_Yuma_PG_ISS_4-21-17.pdf PDF
Response_to_Vendor_Questions__2.pdf PDF
Attach_L_-_3_SKtr_Consent_for_Release.docx DOCX document
ISS 15R0001 USAYPG - Technical Exhibit 22 - Government Furnished Property.docx DOCX document
ISS 15R0001 USAYPG - Technical Exhibit 13 - Water Pumping Booster Stations.docx DOCX document
Attachment_5_YPG_Price_Breakdown_-_for_evaluation.xlsx XLSX spreadsheet
ISS 15R0001 USAYPG - Technical Exhibit 17 - POL Facilities Locations and Equipment.docx DOCX document
ISS 15R0001 USAYPG - Technical Exhibit 16 - Roads and Test Courses.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_3_-_Performance_Requirements_Summary_-_20170327_v2L.pdf PDF
Attachment_3_Vehicle_list.xlsx XLSX spreadsheet
W9124R-15-R-0001.pdf PDF
ISS 15R0001 USAYPG - Technical Exhibit 15 - Grounds Inventory.docx DOCX document
ISS 15R0001 USAYPG - Technical Exhibit 5 - Equipment In Place.docx DOCX document
Attachment_1_PWS_15R0001_YPG-ISS_-_3-30-17_v5L.pdf PDF
ISS_15T0001_USAYPG_-_Technical_Exhibit_23.pdf PDF
ISS 15R0001 USAYPG - Technical Exhibit 19 - Cathodic Protection System Locations.docx DOCX document
ISS 15R0001 USAYPG - Technical Exhibit 4 - Contractor Occupied Facilities.docx DOCX document
Attachment_4_-_DD254.pdf PDF
Attachment_2_WD_3-30-17.docx DOCX document
ISS 15R0001 USAYPG - Technical Exhibit 21 - Labor Categories .docx DOCX document
ISS 15R0001 USAYPG - Technical Exhibit 8 - ICE PM Checklist.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_5_-_Equipment_In_Place.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_18_-_POL_Facilities_Bi-Monthly_Checklist.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_3_-_Performance_Requirements_Summary_-_20161005.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_7_-_Electrical_Substations.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_20_-_Cathodic_Protection_System_PM_Checklist.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_2_-_Workload_History.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_6_-_Deliverables_20161011.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_16_-_Roads_and_Test_Courses.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_1_-_Real_Property_Inventory.docx DOCX document
PWS_-_ISS_15R0001_USAYPG_-_3-2-17.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_9_-_ICE_Visible_Emisions_Inspection_Checklist.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_10_-_Boiler_Tune-Up_Form.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_13_-_Water_Pumping_Booster_Stations.docx DOCX document
ISS_15R0001_USAYPG_-_Technical_Exhibit_17_-_POL_Facilities_Locations_and_Equipment.docx DOCX document
Show all 50

Installation Support Services for Yuma Proving Ground, AZ has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL EXHIBIT 7

ELECTRICAL SUBSTATIONS

SUBSTATION NUMBER
FACILITY NUMBER
KVA RATING & VOLTAGE IN/ VOLTAGE OUT
SERVICE AREA
YEAR BUILT
BACK-UP SUBSTATION
A
708
7000 @ 69000 12470
HCA
1948
B
B
2007
7000 @ 69000 12470
WCA LAAF & DYNO COURSE
2006
A
C
3540
7000 @ 69000 12470
KFR MAIN AREA/95
1995
G
D
6009
7000 @ 34500 12470
CDH,CDA, BP, AEROSTAT
1960
C, G
E
3540
14000 @ 69000 34500
KOFA & CIBOLA RANGE AREA
1995
L
F
7005
3750 @ 34500 12470
CIBOLA RANGE
1970
NONE
G
3540
7000 @ 69000 12470
KFR MAIN AREA
1995
C
I
SS486
1288 @ 34500 12470
EAST KFR RANGE
1995
NONE
L
3540
14000 @ 69000 34500
KOFA & CIBOLA RANGE AREAS
2002
E
H
SS319
20000 @ 161000 69000
ALL YPG
1995
ARMY TAP
MFF
NA
7000 @ 69000 12470
MILITARY FREEFALL TRAINING CENTER
2014
B
ARMY TAP
1508
24000 @ 69000 (SWITCH)
ALL YPG
1970
K
WMIDD SOUTH CIBOLA RANGE FEED
N/A
34500 & 12470
BIG GUNS & SOUTH CIBOLA RANGE
1952
NONE
APS NORTH CIBOLA FEED MILE POST 82
N/A
12000/12000
NORTH CIBOLA RANGE
1990
NONE
APS NORTH CIBOLA FEED MILE POST 89
N/A
12000/12000
NORTH CIBOLA RANGE
2004
NONE