This document contains a safety plan checklist for a construction project at Fort Knox, Kentucky as well as details of an upcoming solicitation for a Job Order Contract and Multiple Award Task Order Contract to support maintenance, repair, and minor construction at Fort Knox. The safety plan checklist outlines requirements for contractor safety plans, including background information on the project and contractor, safety policies and responsibilities, training, inspections, compliance, incident reporting, and hazard analyses. It provides a list of specific safety programs and plans required by the US Army Corps of Engineers Safety Manual. The solicitation will be issued on June 22, 2020 by the Mission and Installation Contracting Command at Fort Knox in support of the Directorate of Public Works. The combined Indefinite Delivery/Indefinite Quantity contract will be used for a broad range of facility services at Fort Knox.
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 4b
FORT KNOX INSTALLATION SAFETY CONTRACTOR
REVIEW CHECKLIST
ITEM DESCRIPTION YES NO N/A Comments
a. Includes the name, signature, and title of the Plan Preparer (Qualified person, i.e. corporate safety staff person, QC)
b. Includes the name, signature, and title of the Plan Approver (e.g.
owner, company president, regional vice president) (HTRW activities require approval of a Certified Industrial Hygienist, a Certified Safety Professional may approve the plan for operations involving UST removal where contaminants are known to be petroleum, oils, or lubricants).
c. Includes the name(s), signature(s), and title(s) for Plan Concurrence (provide concurrence of other applicable corporate and project personnel (contractor)) (e.g. Chief of Operations, Corporate Chief of Safety, Corporate Industrial Hygienist, project manager or superintendent, project safety professional, project
QC.)
2. Background information
a. Includes the Contractor Name.
b. Includes the Contract Number.
c. Includes the Project Name.
d. Includes the Brief Project Description.
e. Includes the Location of the Project (map).
f. Includes the Contractor Accident Experience (Copy of OSHA 300 Forms, or equivalent documentation).
g. Includes the Listing of Phases of Work and Hazardous Activities Requiring an Activity Hazard Analyses (AHA).
3. Statement of Safety and Health Policy. Includes a copy of the corporate safety policy. (In addition to the corporate policy statement,a copy of the corporate safety program may provide a portion of the information required by the accident prevention plan.)
4. Responsibilities and Lines of Authorities
a. Includes the identification and job responsibilities of personnel responsible for safety - at both corporate and project level – including their resumes.
b. Includes the lines of authority.
DATE:
CONTRACT NUMBER
CONTRACTING OFFICER / PHONE
COMPANY
GOVERNMENT ORGANIZATION POC AND
PHONE NUMBER:
SAFETY OFFICE REVIEWER: Brian Wood / 624-4407 / brian.r.wood3.civ@mail.mil mailto:brian.r.wood3.civ@mail.mil
ITEMS DESCRIPTION YES NO N/A Comments
5. Training
a. Includes the list of subjects to be discussed with employees at safety indoctrination.
b. Includes the list of mandatory training and certifications applicable to this project (e.g., explosive actuated tools, confined space entry, crane operator, diver, vehicle operator, HAZWOPER training and certification, PPE) and any requirements for periodic retraining / recertification.
c. Includes the identity requirements for emergency response training.
d. Includes the outline requirements (who attends, when given, who will conduct, etc.) for supervisory and employee safety meetings.
6. Safety and Health Inspections
a. Includes the name(s) of individual(s) responsible for conducting safety inspections. (e.g., PM, safety professional, QC, supervisors, employees)
b. Includes proof of inspector's training / qualifications.
c. Indicates when inspections will be conducted.
d. Furnished sample forms upon which inspections will be recorded.
e. Indicates deficiency tracking system and follow-up procedures.
f. Includes the names of competent and / or qualified person(s) and proof of competency / qualification to meet specific OSHA competent / qualified person(s) requirements.
g. Includes any external inspections / certifications which may be required. (e.g., US Coast Guard)
7. Safety and Health Expectations, Incentive Programs, and Compliance
a. Includes the company's written safety program goals, objectives, and accident experience goals.
b. Includes a brief description of the company's safety incentive programs (if any).
c. Includes the policies and procedures regarding noncompliance with safety requirements (to include disciplinary actions for violation of safety requirements).
d. Includes the written company procedures for holding managers and supervisors accountable for safety.
8. Mishap Reporting
a. The plan identifies how, when, and who shall complete the Exposure data (man-hours worked).
b. The plan identifies how, when, and who shall complete mishap investigations, reports, and logs.
c. The plan identifies how, when, and who shall make immediate notification of major mishaps.
9. Plans (Programs, Procedures) required by the Safety Manual
a. Fatigue Management Plan (01.A.20)
b. Emergency response plans:
(1) Procedures & Test (01.E.01)
(2) Spill Plans (01.E.01, 06.A.02)
(3) Fire Fighting Plan (01.E.01; 19.A)
(4) Posting of Emergency Telephone Numbers (01.E.05)
(5) Man overboard/abandon ship (19.A.04) ITEM DESCRIPTION YES NO N/A Comments
(6) Medical Support. Outline on-site medical support and off-site medical arrangements including rescue and medical duties for those employees who are to perform them, and the name(s) of on-site Contractor personnel trained in first aid and CPR. A minimum of two employees shall be certified in CPR and first-aid per shift/site (Section 03.A; 03.D)
c. Plan for prevention of alcohol and drug abuse (01.C.02)
d. Site Sanitation Plan (Section 02.B)
e. Medical Support Plan, (03.A.01; 03.A.06; 03.D)
f. Bloodborne Pathogen Plan (03.A.05)
g. Exposure Control Plan (03.A.05)
h. Site Layout Plan (04.A)
i. Access/Haul road Plan (04.B)
j. Hearing Conservation Program (05.C)
k. Respiratory Protection Plan (05.G)
l. Health Hazard Control Program (06.A)
m. Process Safety Management Plan (06.B.04)
n. Lead Abatement Plan (06.C & Specs)
o. Asbestos Abatement Plan (06.C & Specs)
p. Radiation Safety Program (06.F)
q. Abrasive Blasting Plan (06.I)
r. Heat/Cold Stress Monitoring Plan (06.J)
s. Indoor Air Quality Management Plan (06.L)
t. Mole Remediation Plan (06.L.04)
u. Chromium (VI) Exposure Evaluation (06.M)
v. Crystalline Silica Assessment (06.N)
w. Lighting Evaluation (07.A)
x. Lighting Plan for Night Operations (07.A.09)
y. Traffic Control Plan (08.C.05)
z. Fire Prevention Plan (09.A.01)
aa. Wild Land Fire Management Plan (09.L)
bb. Arc Flash Hazard Analysis (11.B)
cc. Assured Equipment Grounding Control Program (AEGCP), (11.D.05, App D)
dd. Hazardous Energy Control Plan, (12.A.01)
ee. Standard Pre-Lift Plan (LHE) (16.A.03, 16.L.15)
ff. Critical Lift Plan – LHE (16.H)
gg. Naval Architectural Analysis (16.L)
hh. Contingency Plan for Severe Weather (19.A.03)
ii. Man Overboard/Abandon Ship (19.A.04)
jj. Float Plan (19.F.04)
kk. Fall Protection Program, (21.D);
ll. Demolition/Renovation Plan (to include engineering survey), (23.A.02)
mm. Rope Access Program, (24.H.02)
nn. Excavation/Trenching Plan, (25.A.01)
oo. Underground construction fire prevention and protection Plan ITEM DESCRIPTION YES NO N/A Comments
pp. Compressed Air Plan, (26.I.01)
qq. Formwork and Shoring Erection and Removal plan, (27.C)
rr. PreCast Concrete Plan, (27.D) ss Lift. slab plans, (27.E)
tt. Masonry Bracing Plan, (27.F.01)
uu. Steel Erection Plan, (28.B)
vv. Explosives Safety Site Plan (ESSP) (29.A)
ww. Blasting Plan, (29.A; 26.J)
yy. Tree Felling/Maintenance Program, (31.A)
zz. Aircraft/Airfield Construction Safety & Phasing Plan, (32.A.02) aaa. Site Safety and Health Plan (HTRW), (33.B) bbb. Confined Space Entry Program, (34.A.06, 07)
10. Risk Management Processes. Detailed project-specific hazards shall be identified and controls provided via Activity Hazard Analysis (01.A.14 & 01.A.15) for each major phase/activity of work.