ATT_04b_Safety_Plan_Checklist_IAW_USACE_EM_385_1_Appendix_A.pdf

PDF 674 KB Posted

Attached to
Fort Knox, Ky Consolidated Construction Multiple Award Task Order Contract (MATOC)/Job Order Contract (JOC)
Solicitation number
W9124D20R0034
Issued by

About this file

This document contains a safety plan checklist for a construction project at Fort Knox, Kentucky as well as details of an upcoming solicitation for a Job Order Contract and Multiple Award Task Order Contract to support maintenance, repair, and minor construction at Fort Knox. The safety plan checklist outlines requirements for contractor safety plans, including background information on the project and contractor, safety policies and responsibilities, training, inspections, compliance, incident reporting, and hazard analyses. It provides a list of specific safety programs and plans required by the US Army Corps of Engineers Safety Manual. The solicitation will be issued on June 22, 2020 by the Mission and Installation Contracting Command at Fort Knox in support of the Directorate of Public Works. The combined Indefinite Delivery/Indefinite Quantity contract will be used for a broad range of facility services at Fort Knox.

View the file

Other files

File Type Posted
W9124D20R0034_Amendment_0002.pdf PDF
ATT_00c_Seed_Project_GD_Highway_KY20200038_8-14-20_Amdt_0002.pdf PDF
ATT_00b_Seed_Project_Drawings_Stithton_Traffic_Circle_Rev_8-18-20_Amdt_0002.pdf PDF
ATT_12_JOC_Bid_Form_Templates.pdf PDF
ATT_00_DPW_Construction_JOC-MATOC_SOW_Rev_8-18-20_ Amdt_0002.pdf PDF
ATT_05_FK_EnvironmentaL_Handbook_2020_Edition.pdf PDF
ATT_Pre-Proposal Conference-Site_Visit_Attendees.pdf PDF
ATT_05a_Environmental_Contract_Language.pdf PDF
ATT_00b_ Seed_Project_Drawings_Stithton_Traffic_Circle_Rev.Amdt_0001.pdf PDF
W9124D20R0034_Amendment_0001.pdf PDF
ATT_00a_Seed_Project_Specifications_Rev.Amdt_0001.pdf PDF
ATT_02a_Division_11_Equipment.pdf PDF
ATT_02d_Fort_Knox_Sprinkler_Systems_Initial_Acceptance_Test_Fm_9 Jul_2009.pdf PDF
ATT_02a_Division_01_General_Requirements.pdf PDF
ATT_11_Performance_Assessment_Questionnaire.pdf PDF
ATT_02a_Division_13_Special_Construction.pdf PDF
ATT_06_Contractor_Row_Map.pdf PDF
ATT_02a_Division_09_Finishes.pdf PDF
ATT_02a_Table_of_Contents.pdf PDF
ATT_00b_ Seed_Project_Drawings__Stithton_Traffic_Circle.pdf PDF
ATT_02a_Division_08_Doors_and_Windows.pdf PDF
W9124D20R0034_Consolidated_JOC_MATOC.pdf PDF
ATT_02a_Division_32_Exterior_Improvements.pdf PDF
ATT_01_JOC_Guide_2003_Version.pdf PDF
ATT_03_JOC_Software_Specifications.pdf PDF
ATT_00_DPW_Construction_JOC-MATOC_SOW.pdf PDF
ATT_00c_Seed_Project_GD_KY20200038.pdf PDF
ATT_02c_FKFD_Fire_Alarm_Fire_Suppression_Check_List.pdf PDF
ATT_02a_Division_23_HVAC.pdf PDF
ATT_02a_Division_02_Existing_Conditions.pdf PDF
ATT_02a_Division_26_Electrical.pdf PDF
ATT_02a_Division_12_Furnishings.pdf PDF
ATT_02a_Division_10_Specialties.pdf PDF
ATT_02a_Division_31_Earthwork.pdf PDF
ATT_02a_Division_04_Masonry.pdf PDF
ATT_02a_Division_05_Metals.pdf PDF
ATT_02a_Division_03_Concrete.pdf PDF
ATT_07_Sign_Template.pdf PDF
ATT_02a_Division_22_Plumbing.pdf PDF
ATT_09a_Instructions_for_DD_FORM_1354.pdf PDF
ATT_10_FT_Knox_Locates_Revised_25_Mar_2019.pdf PDF
ATT_02a_Division_14_Conveying_Systems.pdf PDF
ATT_00a_Seed_Project_Specifications_21_Jul_2020.pdf PDF
ATT_04a_EM385_1_1_APP_AFINAL.pdf PDF
ATT_02a_Divisioin_00_Procurement_and_Contracting_Requirements.pdf PDF
ATT_02a_Division_06_Woods_and_Plastics.pdf PDF
ATT_02a_Division_33_Utilities.pdf PDF
ATT_02b_Fort_Knox_Fire_Department_Requirements_5_30_19.pdf PDF
ATT_09b_DD1354_Template_May_2014.pdf PDF
ATT_08_Fort_Knox_CADD_Contract_Requirements_(25_Mar_2019)_V1_1.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 4b

FORT KNOX INSTALLATION SAFETY CONTRACTOR

REVIEW CHECKLIST

ITEM DESCRIPTION YES NO N/A Comments

a. Includes the name, signature, and title of the Plan Preparer (Qualified person, i.e. corporate safety staff person, QC)

b. Includes the name, signature, and title of the Plan Approver (e.g.

owner, company president, regional vice president) (HTRW activities require approval of a Certified Industrial Hygienist, a Certified Safety Professional may approve the plan for operations involving UST removal where contaminants are known to be petroleum, oils, or lubricants).

c. Includes the name(s), signature(s), and title(s) for Plan Concurrence (provide concurrence of other applicable corporate and project personnel (contractor)) (e.g. Chief of Operations, Corporate Chief of Safety, Corporate Industrial Hygienist, project manager or superintendent, project safety professional, project

QC.)

2. Background information

a. Includes the Contractor Name.

b. Includes the Contract Number.

c. Includes the Project Name.

d. Includes the Brief Project Description.

e. Includes the Location of the Project (map).

f. Includes the Contractor Accident Experience (Copy of OSHA 300 Forms, or equivalent documentation).

g. Includes the Listing of Phases of Work and Hazardous Activities Requiring an Activity Hazard Analyses (AHA).

3. Statement of Safety and Health Policy. Includes a copy of the corporate safety policy. (In addition to the corporate policy statement,a copy of the corporate safety program may provide a portion of the information required by the accident prevention plan.)

4. Responsibilities and Lines of Authorities

a. Includes the identification and job responsibilities of personnel responsible for safety - at both corporate and project level – including their resumes.

b. Includes the lines of authority.

DATE:

CONTRACT NUMBER

CONTRACTING OFFICER / PHONE

COMPANY

GOVERNMENT ORGANIZATION POC AND

PHONE NUMBER:

SAFETY OFFICE REVIEWER: Brian Wood / 624-4407 / brian.r.wood3.civ@mail.mil mailto:brian.r.wood3.civ@mail.mil

ITEMS DESCRIPTION YES NO N/A Comments

5. Training

a. Includes the list of subjects to be discussed with employees at safety indoctrination.

b. Includes the list of mandatory training and certifications applicable to this project (e.g., explosive actuated tools, confined space entry, crane operator, diver, vehicle operator, HAZWOPER training and certification, PPE) and any requirements for periodic retraining / recertification.

c. Includes the identity requirements for emergency response training.

d. Includes the outline requirements (who attends, when given, who will conduct, etc.) for supervisory and employee safety meetings.

6. Safety and Health Inspections

a. Includes the name(s) of individual(s) responsible for conducting safety inspections. (e.g., PM, safety professional, QC, supervisors, employees)

b. Includes proof of inspector's training / qualifications.

c. Indicates when inspections will be conducted.

d. Furnished sample forms upon which inspections will be recorded.

e. Indicates deficiency tracking system and follow-up procedures.

f. Includes the names of competent and / or qualified person(s) and proof of competency / qualification to meet specific OSHA competent / qualified person(s) requirements.

g. Includes any external inspections / certifications which may be required. (e.g., US Coast Guard)

7. Safety and Health Expectations, Incentive Programs, and Compliance

a. Includes the company's written safety program goals, objectives, and accident experience goals.

b. Includes a brief description of the company's safety incentive programs (if any).

c. Includes the policies and procedures regarding noncompliance with safety requirements (to include disciplinary actions for violation of safety requirements).

d. Includes the written company procedures for holding managers and supervisors accountable for safety.

8. Mishap Reporting

a. The plan identifies how, when, and who shall complete the Exposure data (man-hours worked).

b. The plan identifies how, when, and who shall complete mishap investigations, reports, and logs.

c. The plan identifies how, when, and who shall make immediate notification of major mishaps.

9. Plans (Programs, Procedures) required by the Safety Manual

a. Fatigue Management Plan (01.A.20)

b. Emergency response plans:

(1) Procedures & Test (01.E.01)

(2) Spill Plans (01.E.01, 06.A.02)

(3) Fire Fighting Plan (01.E.01; 19.A)

(4) Posting of Emergency Telephone Numbers (01.E.05)

(5) Man overboard/abandon ship (19.A.04) ITEM DESCRIPTION YES NO N/A Comments

(6) Medical Support. Outline on-site medical support and off-site medical arrangements including rescue and medical duties for those employees who are to perform them, and the name(s) of on-site Contractor personnel trained in first aid and CPR. A minimum of two employees shall be certified in CPR and first-aid per shift/site (Section 03.A; 03.D)

c. Plan for prevention of alcohol and drug abuse (01.C.02)

d. Site Sanitation Plan (Section 02.B)

e. Medical Support Plan, (03.A.01; 03.A.06; 03.D)

f. Bloodborne Pathogen Plan (03.A.05)

g. Exposure Control Plan (03.A.05)

h. Site Layout Plan (04.A)

i. Access/Haul road Plan (04.B)

j. Hearing Conservation Program (05.C)

k. Respiratory Protection Plan (05.G)

l. Health Hazard Control Program (06.A)

m. Process Safety Management Plan (06.B.04)

n. Lead Abatement Plan (06.C & Specs)

o. Asbestos Abatement Plan (06.C & Specs)

p. Radiation Safety Program (06.F)

q. Abrasive Blasting Plan (06.I)

r. Heat/Cold Stress Monitoring Plan (06.J)

s. Indoor Air Quality Management Plan (06.L)

t. Mole Remediation Plan (06.L.04)

u. Chromium (VI) Exposure Evaluation (06.M)

v. Crystalline Silica Assessment (06.N)

w. Lighting Evaluation (07.A)

x. Lighting Plan for Night Operations (07.A.09)

y. Traffic Control Plan (08.C.05)

z. Fire Prevention Plan (09.A.01)

aa. Wild Land Fire Management Plan (09.L)

bb. Arc Flash Hazard Analysis (11.B)

cc. Assured Equipment Grounding Control Program (AEGCP), (11.D.05, App D)

dd. Hazardous Energy Control Plan, (12.A.01)

ee. Standard Pre-Lift Plan (LHE) (16.A.03, 16.L.15)

ff. Critical Lift Plan – LHE (16.H)

gg. Naval Architectural Analysis (16.L)

hh. Contingency Plan for Severe Weather (19.A.03)

ii. Man Overboard/Abandon Ship (19.A.04)

jj. Float Plan (19.F.04)

kk. Fall Protection Program, (21.D);

ll. Demolition/Renovation Plan (to include engineering survey), (23.A.02)

mm. Rope Access Program, (24.H.02)

nn. Excavation/Trenching Plan, (25.A.01)

oo. Underground construction fire prevention and protection Plan ITEM DESCRIPTION YES NO N/A Comments

pp. Compressed Air Plan, (26.I.01)

qq. Formwork and Shoring Erection and Removal plan, (27.C)

rr. PreCast Concrete Plan, (27.D) ss Lift. slab plans, (27.E)

tt. Masonry Bracing Plan, (27.F.01)

uu. Steel Erection Plan, (28.B)

vv. Explosives Safety Site Plan (ESSP) (29.A)

ww. Blasting Plan, (29.A; 26.J)

yy. Tree Felling/Maintenance Program, (31.A)

zz. Aircraft/Airfield Construction Safety & Phasing Plan, (32.A.02) aaa. Site Safety and Health Plan (HTRW), (33.B) bbb. Confined Space Entry Program, (34.A.06, 07)

10. Risk Management Processes. Detailed project-specific hazards shall be identified and controls provided via Activity Hazard Analysis (01.A.14 & 01.A.15) for each major phase/activity of work.