ATT_00a_Seed_Project_Specifications_Rev.Amdt_0001.pdf

PDF 814 KB Posted

Attached to
Fort Knox, Ky Consolidated Construction Multiple Award Task Order Contract (MATOC)/Job Order Contract (JOC)
Solicitation number
W9124D20R0034
Issued by

About this file

This document package outlines specifications for a roadway repair and traffic pattern change project at Fort Knox, Kentucky. The project involves removing and replacing concrete sidewalks, curbs, and gutters; constructing concrete header curbs and mountable islands; removing and replacing asphalt and concrete surfaces; reconfiguring South Knox Street; and regrading areas for drainage at Stithton Circle and South Knox Street. Bids are due by 24 July 2020 for work to be completed within 120 calendar days of notice to proceed. The contractor will coordinate traffic control and maintain access for base users throughout construction. The Mission and Installation Contracting Command at Fort Knox intends to solicit offers for a combined Job Order Contract and Multiple Award Task Order Contract to support maintenance, repair, and minor construction requirements at the base, with an anticipated solicitation date of 22 June 2020.

View the file

Other files

File Type Posted
W9124D20R0034_Amendment_0002.pdf PDF
ATT_00c_Seed_Project_GD_Highway_KY20200038_8-14-20_Amdt_0002.pdf PDF
ATT_00b_Seed_Project_Drawings_Stithton_Traffic_Circle_Rev_8-18-20_Amdt_0002.pdf PDF
ATT_12_JOC_Bid_Form_Templates.pdf PDF
ATT_00_DPW_Construction_JOC-MATOC_SOW_Rev_8-18-20_ Amdt_0002.pdf PDF
ATT_05_FK_EnvironmentaL_Handbook_2020_Edition.pdf PDF
ATT_Pre-Proposal Conference-Site_Visit_Attendees.pdf PDF
ATT_05a_Environmental_Contract_Language.pdf PDF
ATT_00b_ Seed_Project_Drawings_Stithton_Traffic_Circle_Rev.Amdt_0001.pdf PDF
W9124D20R0034_Amendment_0001.pdf PDF
ATT_02a_Division_11_Equipment.pdf PDF
ATT_02d_Fort_Knox_Sprinkler_Systems_Initial_Acceptance_Test_Fm_9 Jul_2009.pdf PDF
ATT_02a_Division_01_General_Requirements.pdf PDF
ATT_11_Performance_Assessment_Questionnaire.pdf PDF
ATT_02a_Division_13_Special_Construction.pdf PDF
ATT_06_Contractor_Row_Map.pdf PDF
ATT_02a_Division_09_Finishes.pdf PDF
ATT_02a_Table_of_Contents.pdf PDF
ATT_00b_ Seed_Project_Drawings__Stithton_Traffic_Circle.pdf PDF
ATT_02a_Division_08_Doors_and_Windows.pdf PDF
W9124D20R0034_Consolidated_JOC_MATOC.pdf PDF
ATT_02a_Division_32_Exterior_Improvements.pdf PDF
ATT_01_JOC_Guide_2003_Version.pdf PDF
ATT_03_JOC_Software_Specifications.pdf PDF
ATT_00_DPW_Construction_JOC-MATOC_SOW.pdf PDF
ATT_00c_Seed_Project_GD_KY20200038.pdf PDF
ATT_04b_Safety_Plan_Checklist_IAW_USACE_EM_385_1_Appendix_A.pdf PDF
ATT_02c_FKFD_Fire_Alarm_Fire_Suppression_Check_List.pdf PDF
ATT_02a_Division_23_HVAC.pdf PDF
ATT_02a_Division_02_Existing_Conditions.pdf PDF
ATT_02a_Division_26_Electrical.pdf PDF
ATT_02a_Division_12_Furnishings.pdf PDF
ATT_02a_Division_10_Specialties.pdf PDF
ATT_02a_Division_31_Earthwork.pdf PDF
ATT_02a_Division_04_Masonry.pdf PDF
ATT_02a_Division_05_Metals.pdf PDF
ATT_02a_Division_03_Concrete.pdf PDF
ATT_07_Sign_Template.pdf PDF
ATT_02a_Division_22_Plumbing.pdf PDF
ATT_09a_Instructions_for_DD_FORM_1354.pdf PDF
ATT_10_FT_Knox_Locates_Revised_25_Mar_2019.pdf PDF
ATT_02a_Division_14_Conveying_Systems.pdf PDF
ATT_00a_Seed_Project_Specifications_21_Jul_2020.pdf PDF
ATT_04a_EM385_1_1_APP_AFINAL.pdf PDF
ATT_02a_Divisioin_00_Procurement_and_Contracting_Requirements.pdf PDF
ATT_02a_Division_06_Woods_and_Plastics.pdf PDF
ATT_02a_Division_33_Utilities.pdf PDF
ATT_02b_Fort_Knox_Fire_Department_Requirements_5_30_19.pdf PDF
ATT_09b_DD1354_Template_May_2014.pdf PDF
ATT_08_Fort_Knox_CADD_Contract_Requirements_(25_Mar_2019)_V1_1.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT SPECIFICATION

Stithton Circle & South Knox Street

Pavement & Drainage Repair and Traffic Pattern Change

Ft. Knox, Kentucky

Prepared By:

Directorate of Public Works

Engineering & Services Division

Bldg. 1110

125 6th Avenue

Ft. Knox, Kentucky 40121

24 July 2020

1 Section 00110- Bid Form

SECTION 00110- Bid Form

FROM: BIDDER _______________________________________________

ADDRESS _______________________________________________

DATE OF BID: _______________________________________, 20_____

The purpose of the Bid Form is to work in conjunction with formal Contract Documents the Contractor may enter into with Mission and Installation Contracting Command, MICC, Fort Knox, KY.

The Bidder hereby signifies that it is _________ (his/their) intention and purpose to enter into a formal Contract with Mission and Installation Contracting Command, MICC, Fort

Knox, KY, to furnish all labor; materials, tools, equipment, apparatus, supplies, etc., required and to do all the Work necessary for and because of the construction, erection, and/or installation of the proposed

Stithton Circle Pavement & Drainage Repair and Traffic Pattern Change work in accordance with the Contract Documents.

Base Bid with Addendum– Stithton Circle & South Knox Street Pavement & Drainage

Repair and Traffic Pattern Change:

________________________________________________________for the lump sum of

_________________________________________________________________ Dollars

($______________). We further agree to complete the Work in 120 calendar days after receipt of Notice to Proceed.

2 Section 00110- Bid Form

NAME OF SIGNER: ______________________________________________________

(Please Print or Type)

TITLE OF SIGNER: ______________________________________________________

SIGNITURE: ____________________________________________________________

DATE: _________________________________________________________________

End of Section- 00100

ATTACHMENT 1

SCOPE OF WORK

STITHTON CIRCLE & SOUTH KNOX STREET

PAVEMENT & DRAINAGE REPAIR

AND TRAFFIC PATTERN CHANGE

FORT KNOX, KENTUCKY

Stithton Circle & South Knox Street

Pavement & Drainage Repair and Traffic Pattern Change

Scope of Work

PRELIMINARY SCOPE OF WORK

Stithton Circle & South Knox Street Repair & Traffic Pattern Change

All work associated with project will be performed in accordance with all applicable Kentucky State Codes and

Regulations, and latest edition of Fort Knox and UFC Standards. Also, workmanship and materials will conform to latest edition of Kentucky Transportation Cabinet Standard Specifications for Road and Bridge Construction.

Project involves the roadway repair and traffic pattern change of Stithton Circle and South Knox Street. Major design features are as follows:

Remove existing concrete sidewalk and curbs and construct new sidewalks and curb and gutter as shown.

Remove existing concrete curb, asphalt and concrete and construct new concrete header curb around the center island. Remove the tank pads and construct new pads as shown. Raise landscape area, pole and monument and regrade area to drain.

Remove existing asphalt and concrete and construct mountable concrete islands as shown.

Concrete test cylinders are required per the specifications.

Mill existing asphalt or remove asphalt and concrete, then place asphalt base/wedging and asphalt surface or construct road according to the pavement design.

Remove South Knox Street from Stithton Traffic Circle to Pershing Drive and restore the area as shown on the plans.

Re-align South Knox Street at Pershing Drive to Dixie Street to meet the street profile and grading shown on the plans along with the proposed storm drainage shown.

Re-construct the entrance to Abound from the new South Knox Street.

Re-construct the entrance to Pershing Drive to the west from the new South Knox Street.

Paint all asphalt surfaces as required.

All work to be completed according to all applicable codes and Fort Knox standards

1 Section 00115- List of Drawings

SECTION 00115- LIST OF DRAWINGS

Cover Sheet: Abbreviations, Sheet Index, General Notes, Drawing Symbols, Material

Legend

Sheet 1: Stithton Circle Site Layout Plan with Imagery

Sheet 2: South Knox Street Site Layout Plan with Imagery

End of Section- 00115

1 Section 00211- Phasing and Project Description

SECTION 00211- PHASING & PROJECT DESCRIPTION

General: All work associated with project will be performed in accordance with all applicable Kentucky State Codes and Regulations, and latest edition of Fort Knox and

UFC Standards. Also, workmanship and materials will conform to latest edition of

Kentucky Transportation Cabinet Standard Specifications for Road and Bridge

Construction.

Scope of Work is as Follows:

Stithton Circle & South Knox Street Repair & Traffic Pattern Change

Project involves the roadway repair and traffic pattern change of Stithton Circle and

South Knox Street. Major design features are as follows:

Remove existing concrete sidewalk and curbs and construct new sidewalks and curb and gutter as shown.

Remove existing concrete curb, asphalt and concrete and construct new concrete header curb around the center island. Remove the tank pads and construct new pads as shown. Raise landscape area, pole and monument and regrade area to drain.

Remove existing asphalt and concrete and construct mountable concrete islands as shown.

Concrete test cylinders are required per the specifications.

Mill existing asphalt or remove asphalt and concrete, then place asphalt base/wedging and asphalt surface or construct road according to the pavement design.

Remove South Knox Street from Stithton Traffic Circle to Pershing Drive and restore the area as shown on the plans.

Re-align South Knox Street at Pershing Drive to Dixie Street to meet the street profile and grading shown on the plans along with the proposed storm drainage shown.

Re-construct the entrance to Abound from the new South Knox Street.

Re-construct the entrance to Pershing Drive to the west from the new South Knox

Street.

Paint all asphalt surfaces as required.

All work to be completed according to all applicable codes and Fort Knox standards

1 Section 00311- Preliminary Schedule

SECTION 00311- PRELIMINARY SCHEDULE

Anticipate that Contractor will receive Contract for Stithton Circle & South Knox Street

Pavement & Drainage Repair and Traffic Pattern Change no later than 30 August 2020.

Anticipated that Contractor will complete all work within 120 calendar days. Contractor must schedule work hours as necessary to meet the required completion date.

End of Section- 00311

1 Section 00312- Existing Conditions Information

SECTION 00312- EXISTING CONDITIONS INFORMATION

Existing concrete is anticipated under the asphalt pavement and is likely 6-8” thick with little to no rock under it. Contractor shall submit a traffic plan along with schedule on how all work will be completed. The contractor shall coordinate with DPW during construction of all changes to the schedule, this is a heavily traveled area and the movement of traffic during construction is essential. Contract will coordinate with Abound to ensure the entrance is accessible for users and employees throughout construction. Contractor will provide traffic control devices, signage and flag persons as necessary to meet all KYTC safety regulations for traffic control in construction areas throughout construction.

End of Section- 00312

ATT_00a_Seed_Project_Specifications_Revised,Amdt_0001.pdf
Cover Page 24 July 2020.pdf
Section 00110- Bid Form 24 July 2020.pdf
ATTACHMENT 1 Cover Sheet 24 July 2020.pdf
ATTACHMENT 1 Stithton Circle Repair - SOW 24 July 2020.pdf
Section 00115- List of Drawings 24 July 2020.pdf
Section 00211- Phasing and Project Description 24 July 2020.pdf
Section 00311- Preliminary Schedule 24 July 2020.pdf
Section 00312- Existing Conditions Information 24 July 2020.pdf

Section 00110- Bid Form 4 Aug 2020.pdf