Solicitation_W58RGZ-19-R-0050.pdf
PDF 165 KB Posted
- Attached to
- Solicitation for the Overhaul/Repair of the UH-60 Tail Rotor Blade with Pitch Horn Replacement
- Solicitation number
- W58RGZ-19-R-0050
About this file
Solicitation Document No. W58RGZ-19-R-0050
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
Offeror To Complete Block 12, 17, 23, 24, & 30
1. Requisition Number Page Of
2. Contract No. 3. Award/Effective Date 4. Order Number 5. Solicitation Number 6. Solicitation Issue Date
7. For Solicitation Information Call:
A. Name B. Telephone Number (No Collect Calls) 8. Offer Due Date/Local Time
9. Issued By Code 10. This Acquisition is Unrestricted OR Set Aside: % For:
Small Business Women-Owned Small Business (WOSB) Eligible Under the Women-Owned Small Business Program
Hubzone Small Business EDWOSB
Service-Disabled Veteran-Owned Small Business NAICS:
Email: 8(A) Size Standard:
11. Delivery For FOB Destination Unless Block Is Marked
12. Discount Terms 13a. This Contract Is A Rated Order Under DPAS (15 CFR 700) 13b. Rating
See Schedule 14. Method Of Solicitation RFQ IFB RFP
15. Deliver To Code 16. Administered By Code
Telephone No.
17a. Contractor/Offeror Code Facility 18a. Payment Will Be Made By Code
Telephone No.
17b. Check If Remittance Is Different And Put Such Address In Offer
18b. Submit Invoices To Address Shown In Block 18a Unless Block Below Is Checked See Addendum
19.
Item No.
20.
Schedule Of Supplies/Services
21.
Quantity
22.
Unit
23.
Unit Price
24.
Amount
(Use Reverse and/or Attach Additional Sheets As Necessary)
25. Accounting And Appropriation Data 26. Total Award Amount (For Govt. Use Only)
27a.Solicitation Incorporates By Reference FAR 52.212-1, 52.212-4. FAR 52.212-3 And 52.212-5 Are Attached. Addenda Are Are Not Attached.
27b.Contract/Purchase Order Incorporates By Reference FAR 52.212-4. FAR 52.212-5 Is Attached. Addenda Are Are Not Attached.
28. Contractor Is Required To Sign This Document And Return _________ 29. Award Of Contract: Ref. Offer Copies to Issuing Office. Contractor Agrees To Furnish And Deliver All Items Set Forth Or Otherwise Identified Above And On Any Additional Sheets Subject To The Terms And Conditions Specified.
Dated . Your Offer On Solicitation (Block 5), Including Any Additions Or Changes Which Are Set Forth Herein, Is Accepted As To Items:
30a. Signature Of Offeror/Contractor 31a. United States Of America (Signature Of Contracting Officer)
30b. Name And Title Of Signer (Type Or Print) 30c. Date Signed 31b. Name Of Contracting Officer (Type Or Print) 31c. Date Signed
Authorized For Local Reproduction Previous Edition Is Not Usable
Standard Form 1449 (Rev. 2/2012) Prescribed By GSA-FAR (48 CFR) 53.212
W58RGZ-19-R-0050 2018DEC04
ELEANOR BADER (256)313-3082
ELEANOR.L.BADER.CIV@MAIL.MIL
2019JAN04 11:59pm
W58RGZ
ARMY CONTRACTING COMMAND-REDSTONE
REDSTONE ARSENAL AL 35898-5280
336413
X
X DOA1
X
SEE SCHEDULE
SEE SCHEDULE
X X
X 1
1 79
19.
Item No.
20.
Schedule Of Supplies/Services
21.
Quantity
22.
Unit
23.
Unit Price
24.
Amount
32a. Quantity In Column 21 Has Been
Received Inspected Accepted, And Conforms To The Contract, Except As Noted: _________________________________________________
32b. Signature Of Authorized Government Representative 32c. Date 32d. Printed Name and Title of Authorized Government Representative
32e. Mailing Address of Authorized Government Representative 32f. Telephone Number of Authorized Government Representative
32g. E-Mail of Authorized Government Representative
33. Ship Number 34. Voucher Number 35. Amount Verified 36. Payment 37. Check Number Correct For Partial Final Complete Partial Final
38. S/R Account No. 39. S/R Voucher Number 40. Paid By
41a. I Certify This Account Is Correct And Proper For Payment 42a. Received By (Print) 41b. Signature And Title Of Certifying Officer 41c. Date 42b. Received At (Location)
42c. Date Rec’d (YY/MM/DD) 42d. Total Containers
Standard Form 1449 (Rev. 2/2012) Back
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SUPPLEMENTAL INFORMATION
Buyer Name: ELEANOR BADER
Buyer Office Symbol/Telephone Number: CCAM-ALB/(256)313-3082
Type of Contract 1: Firm Fixed Price
Kind of Contract: Maintenance Contracts
*** End of Narrative A0000 ***
Title_____ Date______
A-1 NOTICE TO OFFERORS - FLIGHT SAFETY PARTS FEB/1996
REQUIRING ENGINEERING TESTING
(a) The parts being procured under this solicitation are identified as flight safety parts requiring engineering testing. In accordance with the Army policy pertaining to such parts, this procurement is limited to only those sources (1) who have been approved in accordance with AMCOM (previously ATCOM) source approval procedures and (2) whose part has successfully completed all required engineering testing. Notwithstanding the fact that the technical data package may list sources who have not been tested, only those sources listed in Section B are eligible for award.
(b) By submitting an offer/bid/quote, the contractor certifies that (1) parts representative of the parts it will deliver have previously been subjected to and have passed all requisite engineering testing and (2) the critical manufacturing processes that will be used to produce the parts are either unchanged since the representative parts were tested or that changes in critical manufacturing processes have been approved by the Government in accordance with QE-STD-1 or other Government approved standard. The contractor agrees to provide any and all pertinent documentation which the Government deems necessary to show compliance with the foregoing requirements.
*** END OF NARRATIVE A0001 ***
1. This item is a Critical Safety Item (CSI). _________________________________________
2. This is a five (5) year Firm-Fixed-Price (FFP) Indefinite Delivery Indefinite Quantity (IDIQ) contract pursuant to FAR 52.216-22
3. Depot Maintenance Work Requirement (DMWR) number DMWR-1-1615-287, Revision Date: 12/30/2011, No Change #, is adequate for the
Overhaul/Repair of the UH-60 Tail Rotor Blade with Pitch Horn Replacement. Sikorsky Aircraft Corporation, CAGE Code: 78286 is the only approved source. No other sources have the capabilities in place to accomplish this overhaul/repair effort.
4. When Applicable, the contractor is reminded to complete the Foreign Military Sales (FMS) Customer DA FORM 2410 (Component Removal and Repair Overhaul Record), submitted with the item for repair, in accordance with DA Pamphlet 738-751 and TB-1500-341-01. Upon completion of repair, if authorized, the contractor is reminded to fill out U.S. Army DA Form 2410 and return it to the FMS customer with the repaired asset(s), along with the FMS customer version of the DA Form 2410.
5. The FMS Customer and geographical location(s) for deliveries, inspection and acceptance points are unknown at this time.
6. Subject to the availability of funds, any quantities ordered will be priced at the unit price established for the ordering period in which they are ordered. Funds shall be obligated by issuance of Delivery Orders and not by the contract itself.
7. The minimum quantity set forth herein shall be obligated on Delivery Order (DO) 0001, to be issued simultaneously with the award of the contract. Any additional quantities ordered will be priced at the firm fixed price in effect during the ordering period in which they are ordered.
8. The Government will not be required to obtain the contractor's signature prior to the issuance of an order.
9. Reserved.
10. The Government has segregated the estimated quantities into five ordering periods. However, this does not preclude exercising the
Government's right under FAR 52.216-19 by ordering the maximum quantity specified in FAR 52.216-19(b)(1) at any time during the five year ordering period.
Ordering Period 1 will be from date of contract award through 365 days after contract award (DACA).
Ordering Period 2 will be from 366 DACA through 730 DACA.
Ordering Period 3 will be from 731 DACA through 1,095 DACA.
2 79
W58RGZ-19-R-0050
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
Ordering Period 4 will be from 1,096 DACA through 1,460 DACA.
Ordering Period 5 will be from 1,461 DACA through 1,825 DACA.
11. Please insert your firm fixed unit prices for the 1st, 2nd, 3rd, 4th, and 5th ordering periods in the spaces provided under each
CLIN/SubCLIN.
12. For purposes of Block 12 on page 1, the offer acceptance period is 120 days from the date for receipt of offers specified in Block
9, unless a different period is inserted by the offeror in the blank in Block 12.
13. No Government Furnished Materials (GFM), other than the reparable assets and reusable containers, will be provided.
14. Offers shall be submitted in accordance with FAR Clause 52.215-1. Facsimile and electronic submissions are not authorized.
Proposals shall be mailed to:
Army Contracting Command - Redstone
ATTN: Eleanor L. Bader, CCAM-ALB
Bldg. 5303, 2nd Floor
Redstone Arsenal, AL 35898-5280
15. If any offeror chooses to hand carry their proposal, the offeror must reach the appointed location (identified as building 5300, 5300 Martin Road, Redstone Arsenal, AL 35898, Foyer) by the date and time as stated in block 9 on page 1 of the solicitation. Please be advised that Redstone Arsenal is a restricted facility and should an offeror choose to hand carry a proposal, a minimum of 72 hours notice to the Contracting Officer is required in order to ensure access by the closing date/time of the solicitation. Any unauthorized entity must be identified as having a need, as validated by the Contracting Officer, in order to gain access to the post. The contracting office must notify the Gate personnel, who monitor post access, a minimum of 48 hours prior to an entity gaining entrance to the restricted post. Please note that any proposals delivered late as a result of failure to comply with the procedure will not be accepted, IAW FAR 52.215-1 entitled "Instructions to Offerors-Competitive Acquisition".
16. The Contractor is required to submit a Frozen Plan in accordance with CDRL A003 and (IAW) Clause C-3, AFARS 52.209-4012, "Flight _________________________________________________________________________________________________________________________________
Safety Parts Critical Characteristics Maintenance and Overhaul QE-STD-2, Paragraph 6.1.2. The documentation shall be submitted within_______________________________________________________________________________________________________________________________________
30 days after contract award (DACA).____________________________________
17. The Contractor shall flow down the critical characteristics and QE-STD-1 to all suppliers of Critical Safety Items (CSI).
18. The contractor shall provide with their proposal a response that addresses the contractor's plan to meet all government special tooling and test equipment requirements with either:
1. Physical possession of the required tools, 2. Confirmed requisitions for the required tools, 3. Confirmed arrangements for subcontracting the processes requiring the special tools, or 4. Specific plans describing their technical approach to develop equivalent tools.
19. Reserved.
20. The contractor is instructed to put the following words in the remarks column of the DD 250/WAWF: "Repair and Return Process D6".
21. Access to DLA FedMall (formerly EMALL) is NOT authorized. ___
22. The National Defense Authorization Act for Fiscal Year 1993, Public Law 102-484, Section 326, prohibits use of Other Direct Cost
(ODC) in Department of Defense contracts awarded on or after 1 June 1993, unless appropriate authority is granted.
23. The following websites are provided for the purpose of obtaining/reviewing various Army publications and technical manuals/bulletins:
A. ://liw.logsa.army.mil/etmapp/#/etm/home - Technical Manuals and Bulletins
B. http://www.apd.army.mil/ - DA Pamphlets and Army Regulations
24. COMPLETE THE FOLLOWING CONTRACTOR POINT OF CONTACT INFORMATION:
NAME: _________________________________________
TELEPHONE NUMBER: _____________________________
FAX NUMBER: ___________________________________
3 79
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
E-MAIL ADDRESS: _______________________________
*** END OF NARRATIVE A0002 ***
4 79
PIIN/SIIN
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
SUPPLIES OR SERVICES AND PRICES/COSTS
0001 TAIL ROTOR BLADE
The Contractor is required to submit a Frozen Plan in accordance with "Flight Safety Parts Critical
Characteristics Maintenance and Overhaul QE-STD-2", Paragraph 6.1.2, Data Item A003, Exhibit C, and
Attachment 0018. The documentation shall be submitted within 30 days after contract award (DACA).
PVA must be approved before overhaul may begin.
(End of narrative A001)
This CLIN represents the Product Verification Audit
(PVA) for the Tail Rotor Blade with Pitch Horn
Replacement, NSN: 1615-01-113-8188, as shown in CLIN
0002AA.
PVA shall be in accordance with narrative in Section
E, entitled "Product Verification Audit (PVA)
Statement of Work".
PVA shall be conducted within 90 days after receipt of reparables. The Contractor shall prepare three
(3) assets for PVA. The Contractor is required to notify the Government Quality Office for scheduling of the PVA by email to the following address:
usarmy.redstone.rdecom-armdec.mbx.qs-contracts@mail.mil
With copy emailed to the Contract Specialist at:
eleanor.l.bader.civ@mail.mil
The Contractor will prepare and forward, through the cognizant Government Quality Element, finalized audit reports within 10 working days after completion of the PVA to the email address above.
NOTE: A copy of the cover letter for the report shall be forwarded to the Contract Specialist at:
U.S. Army Contracting Command - Redstone
ATTN: CCAM-ALB, Eleanor L. Bader
Bldg. 5303, 2nd Floor, Martin Road
Redstone Arsenal, AL 35898-5000
PVA requires approval prior to Government acceptance of contract deliverable assets.
Failure to pass the PVA may lead to Termination for____________________________________________________
Default of the contract.________________________
Payment Instructions: The Contractor will go into____________________
Wide Area Work Flow (WAWF) to receive payment for the
PVA. The Contractor shall use DoDAAC W58H0Z when
5 79
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
submitting the PVA invoice in WAWF.
THIS IS A FIRM-FIXED-PRICE CLIN.
(End of narrative A002)
0001AA PRODUCT VERIFICATION AUDIT (PVA) $ ________________________________ __________________
SERVICE REQUESTED: TAIL ROTOR BLADE
CLIN CONTRACT TYPE:
Firm Fixed Price
Deliveries or Performance _________________________
0002 TAIL ROTOR BLADE (TRB)
NSN: 1615-01-113-8188
Mfr CAGE: 78286
Mfr Part Number: 70101-31000-043
0002AA OVERHAUL/REPAIR OF THE TRB WITH PITCH HORN $ $ __________________________________________ ______________ __________________
COMMODITY NAME: TAIL ROTOR BLADE (TRB)
CLIN CONTRACT TYPE:
Firm Fixed Price
SYSTEM: UH-60
INPUT NSN: 1615-01-113-8188
INPUT PART NUMBER: 70101-31000-043
OUTPUT NSN: 1615-01-113-8188
OUTPUT PART NUMBER: 70101-31000-043
Overhaul/Repair shall be in accordance with
Section C, C-1 entitled 'Statement of
Work/Specifications - Government
Specifications'. This Firm Fixed Price (FFP)
CLIN includes all mandatory and non-mandatory parts, labor charges, preservation, packaging, packing, marking, and data items necessary to return the unit, to a serviceable condition, as stated in section C, Statement of Work.
OFFEROR IS REQUIRED TO FILL IN PROPOSED FIRM
FIXED UNIT PRICE:
ORDERING PERIOD 1 - U/P $_________ (FFP) Min
Qty 50 EA
6 79
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
ORDERING PERIOD 2 - U/P $_________ (FFP) Est
Qty 55 EA
ORDERING PERIOD 3 - U/P $_________ (FFP) Est
Qty 60 EA
ORDERING PERIOD 4 - U/P $_________ (FFP) Est
Qty 65 EA
ORDERING PERIOD 5 - U/P $_________ (FFP) Est
Qty 70 EA
(End of narrative B001)
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
PACKAGING REQUIREMENTS
LOCATION OF PACKAGING/PACKING/SPECS:
ADDENDA: 22
LEVEL PRESERVATION: Military
LEVEL PACKING: A
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
FOB POINT: Origin
0003 TAIL ROTOR BLADE (TRB)
NSN: 1615-01-113-8188
Mfr CAGE: 78286
Mfr Part Number: 70101-31000-043
This CLIN will be used if an FMS customer requires this item. If no FMS customer(s) are identified, the
United States Army requirer may utilize the FMS quantity. The estimated quantities are listed below.
The FMS customer and geographical locations for deliveries, inspection, and acceptance points are unknown at this time. Total FMS quantities cannot exceed 400 each.
(End of narrative A001)
0003AA OVERHAUL/REPAIR OF THE TRB WITH PITCH HORN __________________________________________
REPLACEMENT (FMS) $ $ _________________ ______________ __________________
7 79
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
COMMODITY NAME: TAIL ROTOR BLADE (TRB)
CLIN CONTRACT TYPE:
Firm Fixed Price
SYSTEM: UH-60
INPUT NSN: 1615-01-113-8188
INPUT PART NUMBER: 70101-31000-043
OUTPUT NSN: 1615-01-113-8188
OUTPUT PART NUMBER: 70101-31000-043
Overhaul/Repair shall be in accordance with
Section C, C-1 entitled 'Statement of
Work/Specifications - Government
Specifications'. This Firm Fixed Price (FFP)
CLIN includes all mandatory and non-mandatory parts, labor charges, preservation, packaging, packing, marking, and data items necessary to return the unit, to a serviceable condition, as stated in section C, Statement of Work.
OFFEROR IS REQUIRED TO FILL IN PROPOSED FIRM
FIXED UNIT PRICE:
ORDERING PERIOD 1 - U/P $_________ (FFP) Est
Qty 0 EA
ORDERING PERIOD 2 - U/P $_________ (FFP) Est
Qty 15 EA
ORDERING PERIOD 3 - U/P $_________ (FFP) Est
Qty 15 EA
ORDERING PERIOD 4 - U/P $_________ (FFP) Est
Qty 15 EA
ORDERING PERIOD 5 - U/P $_________ (FFP) Est
Qty 15 EA
(End of narrative B001)
Packaging and Marking _____________________
Deliveries or Performance _________________________
FOB POINT:
0004 SCRAP
8 79
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
0004AA SCRAP OF TAIL ROTOR BLADE $ _________________________ __________________
SERVICE REQUESTED: SCRAP
CLIN CONTRACT TYPE:
Firm Fixed Price
THE GOVERNMENT'S ESTIMATED QUANTITY PER
ORDERING PERIOD IS 24 EACH FOR PROPOSAL
EVALUATION PURPOSES ONLY.
Offeror is required to fill in the proposed firm-fixed-unit prices for ordering periods 1 to 5:
ORDERING PERIOD 1 - U/P $_______________ Est
Qty 10 EA
ORDERING PERIOD 2 - U/P $_______________ Est
Qty 10 EA
ORDERING PERIOD 3 - U/P $_______________ Est
Qty 10 EA
ORDERING PERIOD 4 - U/P $_______________ Est
Qty 10 EA
ORDERING PERIOD 5 - U/P $_______________ Est
Qty 10 EA
Scrap assets from CLINs 0002AA and 0003AA shall be in accordance with Section C, C-1 entitled Statement of Work/Specifications -
Government Specifications.
Units authorized to be scrapped in accordance with Section C shall be reflected as an increase in CLIN 0004AA with a corresponding decrease in quantity and funds in CLINs 0002AA and/or 0003AA.
In the event the Procuring Contracting Officer
(PCO) determines that certain items should be scrapped, the contractor shall scrap such items at the fixed-unit price in Section B hereof and make disposition in accordance with the contractor's approved Government property procedures.
The Government may, at its discretion, replace any items scrapped by input of additional assets and said scrap quantities will not count as part of the total maximum quantity.
Scrap requires authorization by the PCO via formal modification. In no event shall the contractor scrap an item prior to receiving a contractual modification for a unit.
THIS IS A FIRM-FIXED-PRICE CLIN.
9 79
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
(End of narrative B001)
Deliveries or Performance _________________________
0005 CONTAINERS
0005AA CONTRACTOR FURNISHED CONTAINERS $ _______________________________ __________________
SERVICE REQUESTED: CONTAINERS
CLIN CONTRACT TYPE:
Firm Fixed Price
THE GOVERNMENT'S ESTIMATED QUANTITY PER ORDERING
PERIOD IS 10 EACH FOR PROPOSAL EVALUATOIN
PURPOSES ONLY.
Offeror is required to fill in proposed firm fixed unit prices for ordering periods 1 to 5:
ORDERING PERIOD 1 - U/P $____________ Est Qty 10
EA
ORDERING PERIOD 2 - U/P $____________ Est Qty 10
EA
ORDERING PERIOD 3 - U/P $____________ Est Qty 10
EA
ORDERING PERIOD 4 - U/P $____________ Est Qty 10
EA
ORDERING PERIOD 5 - U/P $____________ Est Qty 10
EA
The contractor shall provide the container in accordance with Section C, C-1 entitled
Statement of Work/Specifications - Government
Specifications and Section J, Attachment 0022
Packaging Requirements.
The Government cannot determine at the time of contract award, how many of the assets to be overhauled will be received by the Contractor in unserviceable containers or received without containers.
The Contractor, IAW Section C Statement of Work, should submit a Report of Discrepancy (ROD) SF
Form 364 through the Defense Contract Management
Agency (DCMA) Quality Assurance Representative
(QAR) for verification within 7 working days to the address shown on Exhibit B, Data Item A002.
10 79
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
When assets are received in unserviceable containers or without containers, approval of the PCO is required before replacement containers are purchased.
This CLIN covers containers for CLINs 0002AA and
0003AA.
THIS IS A FIRM-FIXED-PRICE CLIN.
(End of narrative B001)
Deliveries or Performance _________________________
0006 CONTRACT DATA REQUIREMENTS LIST (CDRLS) _______________________________________
Pricing for Data Items shall be included in the applicable unit price of CLINs 0002AA and
0003AA.
The Contractor shall provide Data Items A001-
A006, in accordance with CDRLS, DD Form 1423, Section J, Exhibits A-F.
(End of narrative A001)
A001 TAMMS-A $ ** NSP ** _______ __________________
SERVICE REQUESTED: DATA ITEM A001
DATA ITEM A001 - DI-SESS-81758A - THE ARMY
MAINTENANCE MANAGEMENT SYSTEM - AVIAION (TAMMS-A) -
AS REQUIRED
(End of narrative B001)
Deliveries or Performance _________________________
A002 REPORT OF SHIPPING (ITEM) AND PACKAGING _______________________________________
DISCREPANCY (ROD) $ ** NSP ** _________________ __________________
SERVICE REQUESTED: DATA ITEM A002
11 79
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
DATA ITEM A002 - DI-MGMT-80503 - REPORT OF SHIPPING
(ITEM) AND PACKAGING DISCREPANCY (ROD) - AS REQUIRED
(End of narrative B001)
Deliveries or Performance _________________________
A003 FROZEN PLAN (PROCESS PLAN) $ ** NSP ** __________________________ __________________
SERVICE REQUESTED: DATA ITEM A003
DATA ITEM A003 - DI-MISC-80508B - FROZEN PLAN
(TECHNICAL REPORT - STUDY/SERVICES - PROCESS PLAN) -
SUBMIT 30 DAYS AFTER CONTRACT (DAC) AWARD
(End of narrative B001)
Deliveries or Performance _________________________
A004 DD FORM 1348-1A $ ** NSP ** _______________ __________________
SERVICE REQUESTED: DATA ITEM A004
DATA ITEM A004 - DI-MISC-80508B - DD FORM 1348-1A - 5
WORKING DAYS AFTER RECEIPT OF REPARABLES
(End of narrative B001)
Deliveries or Performance _________________________
A005 QUALITY DEFICIENCY REPORT (QDR) $ ** NSP ** _______________________________ __________________
SERVICE REQUESTED: DATA ITEM A005
DATA ITEM A005 - DI-QCIC-80736 - QUALITY DEFICIENCY
REPORT (QDR) - AS REQUIRED
(End of narrative B001)
12 79
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
Deliveries or Performance _________________________
A006 CONTRACT DEPOT MAINTENANCE (CDM) PRODUCTION REPORT $ ** NSP ** __________________________________________________ __________________
SERVICE REQUESTED: DATA ITEM A006
DATA ITEM A006 - Di-PSSS-81995 - CONTRACT DEPOT
MAINTENANCE (CDM) PRODUCTION REPORT - AS REQUIRED
(End of narrative B001)
Deliveries or Performance _________________________
13 79
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
__ TITLE_______ DATE____
C-1 STATEMENT OF WORK/SPECIFICATIONS - GOVERNMENT OCT/2000
SPECIFICATIONS
a. The Contractor, as an independent Contractor, and not as an agent or employee of the Government, shall furnish all services, facilities, labor, parts, materials, equipment, tools and data necessary to accomplish the inspection and Overhaul/Repair required to return the items as specified in Section B, to condition code A as defined by Army Regulation 725-50. The input/output configuration shall be as defined in Section B herein . Upon completion of the Overhaul/Repair, as applicable, the items shall be packaged as defined in Section D and Attachment 0022 of this contract and shipped to the destination(s) specified in each individual delivery order.
b. Prior to commencement of Overhaul/Repair, the Contractor shall disassemble and inspect the item to the extent necessary to determine if the total cost of such Overhaul/Repair including labor, services, parts and materials. The Contractor shall continue the overhaul/repair process on all end items when the total cost to overhaul/repair does not exceed $64,025.00. The overhaul/repair shown in
Section B for CLINs 0002AA and 0003AA are Firm-Fixed-Price (FFP). The Contractor will be required to complete the overhaul/repair at the
FFP on all end items regardless of the damage as long as the total cost to overhaul/repair does not exceed $64,025.00. The Contractor will be required to provide other than certified cost and pricing data and a Report of Discrepancy (ROD) signed by the DCMA QAR to the
Procuring Contracting Officer (PCO) to confirm that the total cost to overhaul/repair will exceed $64,025.00. This data will include at minimum material cost (65% of material cost will be supported by current vendor quotes), labor hours, labor rates, overheads, G&A(s), and profit rate. More information to support the Contractor's price may be requested by the Government. In no event will any asset be scrapped prior to an approved modification by the PCO. No additional funding except for missing parts will be provided to the Contractor to complete the overhaul/repair of the end item. The Government cannot guarantee the condition or configuration of the assets sent to the Contractor for overhaul/repair.
c. In the event that the total contractor cost to overhaul/repair is determined (approved by PCO) to exceed $64,025.00, the Contractor shall scrap such items at the fixed unit price in Section B hereof and make disposition in accordance with (IAW) the Contractor's approved Government property procedures. Such scrapped items shall count toward the quantities ordered hereunder. The Government may, at its discretion, replace any items scrapped by input of additional assets, and said scrap quantities will not count as part of the total maximum quantity.
d. Overhaul/Repair of the Tail Rotor Blade shall be accomplished IAW Depot Maintenance Work Requirement (DMWR) DMWR-1-1615-287, dated 30
December 2011 (Section J, Attachment 0001). The DMWR does not cover the replacement of the Pitch Horn.
In conjunction with the DMWR, the following Maintenance Engineering Order(s) (MEOs) will be used, B1295, B1389, B1576A, B1586, B1613, B1739A, B1754A, B1887, B2033, B2059, B2142, B2469, B2474, B2481; and T1356D (Section J, Attachments 0002 - 0017).
e. The Overhaul shall comply with the critical characteristics identified as an attachment to the Solicitation/Contract, see Section J, Attachment 0023.
f. Upon receipt of the reparables, containers shall be reviewed for serviceability. Containers shall be considered serviceable unless one or more of the following conditions exist: (1) containers are structurally damaged to include functional damage to the suspension system, cracks or holes to the container hull, hull deformity to the extent the container cannot be closed (or sealed where required), or dents that will interfere with the item envelope; (2) corrosion has progressed to the point where fit, function or the life of the container is affected. Items received without containers or containers determined to be unserviceable shall be processed IAW the
Contractor's locally approved Government Property procedures. Components received improperly packaged, damaged with corrosion/deterioration or those with shipping discrepancies shall be reported IAW Data Item A002, Exhibit B.
g. Any Contractor paint facility which is used in the performance of this contract shall comply with the Environmental Protection Agency and Occupational Safety and Health Administration standards for painting as implemented by TM 55-1500-345-23, with change 12, Painting and Marking of Army Aircraft.
h. Data and reports shall be submitted IAW the Contract Data Requirements List, DD Form 1423, Exhibits A-F. Data shall be packaged, packed and marked as necessary to assure safe delivery to the addressees indicated on the DD Form(s) 1423. All RODs shall be reviewed/signed by the DCMA QAR prior to submission to the PCO.
i. Product Verification Audit (PVA) shall be conducted IAW CLIN 0001AA and the Product Verification Audit (PVA) Statement of Work, as specified in Section E of the Solicitation/Contract. The Frozen Plan must be prepared IAW DI-MISC-80508, QESTD-2, Data Item A003, Exhibit C, and the Frozen Plan Description and Guidance Instructions, Attachment 0018, and approved before the PVA may be conducted.
j. The Army Maintenance Management System - Aviation (TAMMS-A): The Contractor shall prepare TAMMS data IAW DI-SESS-81758 and the TAMMS instructions as specified in Data Item A001, Exhibit A. The Contractor shall complete the forms and records as specified in DA PAM 738-
751, TB 1-1500-341-01, TM 1-1500-328-23.
14 79
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
k. Reserved.
l. Reserved.
m. Reserved.
n. Inventory Transactions - The Contractor shall prepare the following reports:
1. The contractor shall prepare a Depot Maintenance Production Report IAW DI-PSSS-81995, Data Item A006, Exhibit F and Attachment
0020.
2. The contractor shall complete and maintain the DD Form 1348-1A receipt for reparables on all shipments IAW DI-MISC-80508 and DD
Form 1348-1A IAW Data Item A004, Exhibit D. The contractor shall complete the DD Form 1348-1A, Block 10 (indicates the quantity received), along with Block 22 (signature), and Block 23 (date). Printed names, name/date stamps, and initials shall not be acceptable. If a DD Form 1348-1A is not delivered with the shipment, a DD Form 1348-1A is located at:
http://www.acq.osd.mil/dpap/ccap/cc/jcchb/files/formspubsregs/dod_funding_documents/dd13481a.pdf
The contractor shall prepare this data to include the following corresponding receipt information:
A. National Stock Number (NSN) - (Positions 8-22)
B. Condition Code - (Position 71)
C. Unit Price - (Positions 74-80)
D. Total Price - (Block 1)
E. Actual Quantity Received - (Block 10)
F. Nomenclature - (Block 17)
G. Signature and Date - (Blocks 22 and 23)
An example of a 1348-1A filled out correctly is attached (See Attachment 0019).
If there are any questions with the above information please contact: usarmy.redstone.usamc.mbx.immc-smb-ammo@mail.mil
o. Reserved.
p. Reserved.
q. The Government reserves the right to replace any items scrapped.
r. Reserved.
s. The Contractor shall prepare the Quality Deficiency Report IAW DI-QCIC-80736, Data Item A005, Exhibit E
t. The Contractor shall prepare the Process Plan Report (Frozen Plan) IAW DI-MISC-80508, QE-STD-2, Data Item A003, Exhibit C, and the
Frozen Plan Description and Guidance Instructions, Attachment 0018. Also see http://amcomdmz.redstone.army.mil/casl_cmo/casldba.casl_cmo_samsar and select AMCOM Maintenance and Overhaul (M&O) SAR."
u. Shipping Containers, See Drawing SPD70101-002, Wood Packaging must be ISPM-15 Compliant. Packaging requirements IAW instructions attached to the Solicitation/Contract, see Attachment 0022. The Contract must use a method of shipment that provides a procedure so that the package can be tracked in case the shipment is not received by AMCOM.
*** END OF NARRATIVE C0001 ***
TITLE_____ DATE____
C-2 FLIGHT SAFETY PARTS CRITICAL CHARACTERISTICS JUL/2002
MAINTENANCE AND OVERHAUL
QE-STD-2
QE-STD-2
REVISION A
4 OCT 96
FLIGHT SAFETY PARTS
15 79
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
CRITICAL CHARACTERISTICS
MAINTENANCE & OVERHAUL
QE-STD 2
Paragraph
Purpose--------------------------------------- 1.0
Scope----------------------------------------- 2.0
References------------------------------------ 3.0
Definitions----------------------------------- 4.0
Policy---------------------------------------- 5.0
Requirements---------------------------------- 6.0
Planning-------------------------------------- 6.1
Plan Content---------------------------------- 6.1.1
Frozen Planning Requirements------------------ 6.1.2
Changes to Frozen Planning-------------------- 6.1.3
Audits---------------------------------------- 6.2
Critical Characteristics---------------------- 6.3
Inspection of Critical Characteristics-------- 6.3.1
Nonconforming Critical Characteristics-------- 6.3.2
Contradictory Critical Characteristics-------- 6.3.3
Delivered Nonconformances--------------------- 6.3.4
Records--------------------------------------- 6.4
Traceability of Records----------------------- 6.4.1
Purchasing Records---------------------------- 6.4.2
Retention of Records-------------------------- 6.4.3
Certification of Personnel-------------------- 6.5
Measurement & Test Equipment------------------ 6.6
Calibration----------------------------------- 6.6.1
Tolerance------------------------------------- 6.6.2
Government Furnished Material----------------- 6.7
1.0 PURPOSE: To establish the minimum level of activity that is required for the Maintenance and Overhaul (M&O) for Flight Safety Parts _______
(FSPs) wherein the M&O affects or involves the Critical Characteristics (CCs) associated with the FSP. Requirements established herein are intended to establish and maintain the integrity of the CCs throughout the M&O process.
2.0 SCOPE: This document is intended to be used in conjunction with other contractually specified quality requirements. This document _____ shall apply to all FSP.
3.0 REFERENCES: __________
a. ANSI/ASQC B1,B2,B3-1996
b. ISO 10012-1
c. Competition Advocate's Shopping List(CASL)
d. AMCOM Regulation 702-7 (Flight Safety Parts/New Source Testing Program Management)
4.0 DEFINITIONS: ___________
a. Flight Safety Part, (Aircraft and Components): Any part, assembly, or installation containing a critical characteristic(CC) _____________________________________________ whose failure, malfunction, or absence could cause loss of or serious damage to the aircraft, and/or serious injury or death to the occupants.
b. Flight Safety Part, (Engine): Any part, assembly, or installation containing a CC whose failure, malfunction, or ____________________________ ab sence could cause an uncommanded engine shut down, and/or an uncontained engine failure resulting in loss of, or serious damage to the aircraft and/or serious injury or death to the occupants.
c. Critical Characteristic: Any feature throughout the life cycle of a FSP, such as dimension, finish, material or assembly, _______________________ manufacturing or inspection process, installation, operation, field maintenance, or depot overhaul requirement which if nonconforming, missing or degraded could cause the failure or malfunction of the FSP.
d. Approved Source: A manufacturer or vendor who has satisfied, prior to contract award, all AMCOM source approval requirements _______________ as set forth in the CASL to include, if applicable, engineering testing requirements (fatigue, endurance, and/or interchangeability).
16 79
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
e. Contractor: Any company or Government owned and operated depot performing M&O for AMCOM. __________
5.0 POLICY: To maintain the integrity and quality of FSP, components, sub-assemblies, and assemblies undergoing M&O, contractors ______ providing such services are required to adhere to the requirements of this document in its entirety. If a contractor has difficulty in maintaining process control as evident through such things as internal management audits, customer audits, the receipt of quality deficiency reports for parts previously supplied to AMCOM et. al., this will require immediate corrective action for the current contract and could affect the award of future contracts to that contractor.
6.0 REQUIREMENTS: All requirements of this document (para 6.1 - 6.7) shall be complied with by a contractor receiving a contract for M&O ____________ of FSP. If a process or processes that involve a CC is subcontracted, this document must be imposed, in its entirety, on the subcontractor performing the work. If, during M&O replacement parts are required that are not identified on the repair parts lists, the contractor will contact the PCO for instructions on how to procure these parts.
6.1 PLANNING: ________
6.1.1 PLAN CONTENT: Each M&O process affecting a FSP critical characteristic as identified in the Depot Maintenance Work Requirements ____________
(DMWR) or other AMCOM authorized M&O procedure must be controlled by detailed procedures outlining each step or parameter of the process along with any required materials, tooling, equipment, or operator certification. All procedures shall be clearly defined and the values of characteristics recorded as applicable. Plans shall clearly define sequence of operation, machine type, and accept/reject limits for the specific process or operation. Critical processes not easily verified shall clearly define process operating parameters with tolerances. Plans shall clearly identify all CCs.
6.1.2 FROZEN PLANNING REQUIREMENTS: The contractor is responsible for developing M&O planning. Review and control of these plans will be ____________________________ the responsibility of the Contractor Control Board (CCB) consisting of qualified personnel equipped with adequate resources to assure development of complete, reliable, and traceable documentation. Parts maintained and overhauled utilizing these plans shall meet all contractual requirements. Plans developed for the M&O of FSP shall be frozen at the time the Product Verification Audit (PVA) is approved by the Government, or when a PVA is not required, prior to induction of the first M&O asset.
Once frozen, plans shall remain frozen throughout the existing contract and all subsequent contracts for M&O of the item unless changes to the planning are made in accordance with this standard. In addition all plans shall be made available to the Government at any time upon request. For future contracts, verification of the currency of this planning will also be required at the time of bid submission if specified in the solicitation.
6.1.3 CHANGES TO FROZEN PLANNING: Frozen M&O planning pertaining to a CC shall not be changed without prior CCB recommendation, __________________________ justification to AMCOM and receipt of approval by the Procuring Contracting Officer (PCO) except changes occurring as the result of an
AMCOM approved Engineering Change Proposal (ECP), or AMCOM Engineering Directive (AED) requires CCB approval only. All changes to frozen planning affecting CCs will be submitted to AMCOM for approval. When the item, CC, or process is accomplished by a subcontractor, the planning shall be reviewed and approved by the contractor, and be subject to the same restrictions as above. Changes to frozen planning not effecting CCs require only CCB approval.
6.2 AUDITS: Contractors are to perform self-audits of their frozen planning when that planning applies to CCs produced or verified in ______ house. At a minimum, audits will be performed at the start of each M&O contract, annually, and when process changes occur. It is incumbent upon the contractor to assure that subcontractors accomplish self-audits, and maintain records verifying their vendors are in full compliance with the audit requirement. All audit findings will be recorded and corrective action will be documented.
6.3 CRITICAL CHARACTERISTICS: ________________________
6.3.1 INSPECTION OF CRITICAL CHARACTERISTICS: All CCs which can be nondestructively inspected/tested shall be subjected to 100 percent ______________________________________ inspection by the contractor or subcontractor; however, assemblies containing CCs need only be disassembled to the extent required by the statement of work to return the assemblies to a serviceable condition, in these cases inspection of CCs is not necessary. CCs which require destructive testing are to be tested on a lot or batch basis, with no skip lots allowed. All completed work instructions shall identify the FSP part number, serial or lot number, and characteristic inspected. Critical characteristics shall be identified on the work instructions in such a manner as to draw attention to them. Work instructions shall reflect the exact readings or dimensions, date of inspection, identity of inspector, and any required inspection certification. These requirements are in addition to other contractual requirements.
6.3.2 NONCONFORMING CRITICAL CHARACTERISTICS: Nonconformances of CCs shall not be dispositioned "use as is" or "repair" through ______________________________________ contractor actions. Rework to DMWR or other AMCOM approved procedures are acceptable. Waivers or deviations may be requested as specified in the contract. Request for waivers/deviations of CCs shall be classified as critical and will be forwarded to AMCOM for approval/disapproval.
6.3.3 CONTRADICTORY CRITICAL CHARACTERISTICS: Contradictions between the DMWR or other AMCOM approved procedures shall be brought to the ______________________________________ attention of the PCO immediately and any work pertaining to the CC in question shall be stopped until a written resolution to the contradiction is issued to the contractor from the PCO.
17 79
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
6.3.4 DELIVERED NONCONFORMANCES: Contractors shall notify the PCO immediately of any discovered Nonconformances that may exist in _________________________ previously delivered FSP. Notification is required whether the characteristic in question has been classified as a CC or not.
Notification shall include a description of the suspected nonconformance, contract number, part number, and affected serial numbers, or lot number (when applicable).
6.4 RECORDS: _______
6.4.1 TRACEABILITY OF RECORDS: All records relating to FSP shall be traceable to the date and place of M&O. Records shall provide the _______________________ degree of traceability required to enable subsequent verification of all aspects of material, manufacture, special process, personnel certification, variability control charts (if applicable), assembly and inspection of CCs. Special processes include but are not limited to heat treat, shotpeening, and nondestructive testing.
6.4.2 PURCHASING RECORDS: All purchase orders for subcontracted products or processes that contain CCs must clearly identify the CC and __________________ reference this STD and if applicable QE-STD 1 for compliance. All documents and referenced data for FSP shall be available for review by the Government to determine compliance.
6.4.3 RETENTION OF RECORDS: The contractor shall retain copies of all records generated pursuant to this standard and make these records ____________________ available to the Government upon request. Records shall be retained for a period of five years past after the contractor ceases the M&O process of the part for which this standard applies. At the end of this period or in the event of relocation or shutdown, all records shall be offered to the PCO prior to disposal.
6.5 CERTIFICATION OF PERSONNEL: Contractor personnel performing work or having inspection responsibilities pertaining to CCs, shall be __________________________ certified to the appropriate professional level as outlined in the applicable national standards, best commercial practices, or as contractually required. A system for tracking personnel certification shall be an element in the contractor internal audit program to assure all certifications are maintained in a current status.
6.6 MEASUREMENT & TEST EQUIPMENT (M&TE): ___________________________________
6.6.1 CALIBRATION: Calibration of inspection equipment shall be in accordance with contractual requirements. All aspects of the ___________ supplier's calibration confirmation system shall be subject to Government verification at unscheduled intervals. The supplier's M&TE shall be made available for use by the Government, as needed. All measuring equipment that is used to measure CCs shall be monitored for effectiveness and reproducibility. A recommended method is provided in ISO 10012-1.
6.6.2 TOLERANCE: Measurement and Test Equipment (M&TE) used to inspect FSPs must be discriminate to within 10 percent of the total _________ tolerance for the feature being inspected except as follows. For tolerances less than .001, M&TE must be discriminate to 20 percent.
6.7 GOVERNMENT FURNISHED MATERIAL: When material is furnished by the Government, the contractor's procedures shall include, as a _____________________________ minimum, the following:
a. Examination upon receipt to detect damage in transit.
b. Inspection for completeness and proper type.
c. Periodic inspection and precautions to assure adequate storage conditions are maintained, and to guard against damage from handling and deterioration during storage.
d. Functional testing, either prior to or after installation, or both, as required by contract to determine satisfactory operation.
e. Identification and protection from improper use or disposition.
f. Verification of quantity.
g. Damaged/nonconforming Government Furnished Material shall be identified as such and is to be segregated in a secure controlled area pending Government disposition instructions.
*** END OF NARRATIVE C0002 ***
18 79
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
PACKAGING AND MARKING
TITLE_____ DATE____
D-1 BAR CODE MARKING JUN/2003
Bar Code Markings are required in accordance with the latest revision of MIL-STD-129 and ISO/IEC 16388 - Information Technology -
Automatic Identification and Data Capture Techniques - Bar Code Symbology Specification - Code 39.Automatic Identification and Data
Capture Techniques - Bar Code Symbology Specification - Code 39.
*** END OF NARRATIVE D0001 ***
19 79
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
INSPECTION AND ACCEPTANCE
This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:
http://farsite.hill.af.mil/ or https://www.acquisition.gov/
If the clause requires additional or unique information, then that information is provided immediately after the clause title.
Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________
1 52.246-2 INSPECTION OF SUPPLIES--FIXED-PRICE AUG/1996
2 52.246-4 INSPECTION OF SERVICES--FIXED-PRICE AUG/1996
3 52.246-16 RESPONSIBILITY FOR SUPPLIES APR/1984
4 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT DEC/2014
(a) The contractor shall comply with the higher-level quality standard(s) listed below.
ISO 9001:2000 or Equivalent; any equivalent must be approved prior to award.
Sikorsky Aircraft Company's Flight Safety Parts Source Approval, Quality, and Test Requirements Document SS9211, Revision 11, dated 10
April 2015 has been approved by the US Army Aviation and Missile Research, Development, and Engineering (AMRDEC) Aviation Engineering
Directorate (AED) from an airworthiness, engineering, and CSI policy viewpoint as meeting the intent of QE-STD-1 and QE-STD-2 and is incorporated and enforced herein. This approval is valid until 31 October 2018.
(b) The contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts in--
(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or
(2) When the technical requirements of a subcontract require--
(i) Control of such things as design, work operations, in-process control, testing and inspection; or
(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.
(End of clause)
TITLE_____ DATE____
E-5 PRODUCT VERIFICATION AUDIT (PVA) STATEMENT DEC/2006
OF WORK
Purpose: The purpose of this PVA SOW is to provide guidance to the contractor in the preparation for and execution of the PVA. The primary concept of the PVA is to validate that the contractor's overhaul processes and procedures comply with contract technical requirements. The PVA candidate(s) are used to evaluate that the contractor processes and procedures are adequate to ensure component integrity.
(a) The Contractor shall perform overhaul and present for acceptance THREE units of Lot/Item 0001AA as specified in this contract. This clause does not supersede instructions contained in depot overhaul work requirements, commercial overhaul manuals, or other applicable documents. It does not relieve the contractor from maintaining a quality system that will assure overhauled items conform to contractual requirements. Contractors may request to delay scheduled PVAs in frequency or waive PVA requirements of selected items in cases where accumulated objective evidence indicates that a consistent quality item is being delivered.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.