Attachment_0014_MEO_B2474_W58RGZ-19-R-0050.pdf
PDF 524 KB Posted
- Attached to
- Solicitation for the Overhaul/Repair of the UH-60 Tail Rotor Blade with Pitch Horn Replacement
- Solicitation number
- W58RGZ-19-R-0050
About this file
Attachment 0014_MEO B2474_W58RGZ-19-R-0050.pdf
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MAINTENANCE ENGINEERING ORDER
(AMCOM Reg. 750-2)
MEO NO.
DATE PAGE 1 of
TITLE Tolerances Unless otherwise noted, dimensions are in inches and tolerances are:
Fractional ………………… ± 1/32 Decimal ………………... ± 0.010 Angular ………………… ± ½°
APPLICABILITY CSI Critical Characteristic Affected?
Impact Statement Attached?
REFERENCES FOR RDECOM USE ONLY
DOCUMENT(S) AFFECTED
PURPOSE OR PROBLEM
PROJECT ENGINEER ENGINEERING REVIEW ENGINEERING RELEASE
MED FORM 5-DEC-09 1401-R-E
B 2474
Jul 29, 2016 4
CSI update of Tail Rotor Blade Assembly P/N 70101-11200-044 and 70101-31000-043
Administrative
INTERIM USE OF THIS MEO IS AUTHORIZED
UNTIL AFFECTED DOCUMENT IS UPDATED.
MEO CHANGE TYPE
4) Normal - Can be implemented with normal priorityPRIORITY IMPLEMENTATION CATEGORY
UH60 DAA
TN 162553
DMWR 1-1615-287 dated 30 Dec 2011
DOCUMENT CHANGE IS REQUIRED Verification: Hands-On Table-Top None
To update the CSI boilerplate content.
SOUTH.JEPHRE
Y.LEE.123067790
Digitally signed by
SOUTH.JEPHREY.LEE.1230677901
DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, ou=USA, cn=SOUTH.JEPHREY.LEE.1230677901 Date: 2016.07.28 07:55:09 -05'00'
GUERRA.ROBER
TO.JR.12868780
Digitally signed by
GUERRA.ROBERTO.JR.1286878012
DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, ou=CONTRACTOR, cn=GUERRA.ROBERTO.JR.1286878012 Date: 2016.07.25 14:11:56 -05'00'
Roberto Guerra Jr
HORN.REINHOL
D.J.1087783495
Digitally signed by
HORN.REINHOLD.J.1087783495
DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, ou=USA, cn=HORN.REINHOLD.J.1087783495 Date: 2016.07.28 11:50:33 -05'00'
Jephrey L. South Ron Horn PUBLICATION CHANGE REQUEST: REQUEST THAT THE FOLLOWING DATA BE INCLUDED IN THE NEXT
CHANGE OR REVISION TO THE PUBLICATION IDENTIFIED ABOVE.
WP NO. PAGE
NO.
PARA-
GRAPH
FIGURE/
TABLE
NO.
CHANGES
(EXACT WORDING OF CHANGES MUST BE GIVEN)
2-2 2-7.1.c REPLACE paragraph 2-7.1c with the following:
"c. Table B-6 provides CSIs that have Depot level inspected and verified CCs. Not listed in Table B-6 are additional CSIs and CCs that are specifically applicable to the manufacture of new parts that might be installed during the overhaul process. In order to maintain airworthiness by ensuring that these new parts have Manufacturer CCs inspected and verified, all CSIs must be obtained from RDECOM approved sources.
The listing of CSIs/CCs not shown in Table B-6 may be obtained from the Army Aviation Sustainment Gateway (ARISE) CSI Database, Joint Services Critical Item Data Viewer, contract, or from the Contracting Officer."
Distribution Statement D:- Distribution authorized to Department of Defense and U.S. DoD contractors only to protect critical technology effective as of 26 June 2014. Other requests for this document must be referred to U.S. Army Aviation and Missile Research, Development and Engineering Center, ATTN: RDMR -AEM , Corpus Christi, TX 78419-5211
MED FORM 24 FEB 2016
W58RGZ-17-R-0237
Attachment 0014
Continuation Sheet
MEO NO.
PAGE of
WP NO. PAGE
NO.
PARA-
GRAPH
FIGURE/
TABLE
NO.
CHANGES
(EXACT WORDING OF CHANGES MUST BE GIVEN)
MED FORM 15-DEC-09 1401-R-E
2-3
2-7.1.d.
2-7.1.d.( 1)
2)
REPLACE paragraph 2-7.1.d. with the following:
"d. All sources including contractors and subcontractors for CSI Maintenance and Overhaul (M&O) services shall be required to comply with QE-STD-2, or an Aviation Engineering Directorate (AED) approved equivalent. Activities performing depot operations shall have a documented and AMCOM/RDECOM approved CSI management program. Specific requirements include, but are not limited to:"
REPLACE paragraph 2-7.1.d.(1) with the following:
"(1) PROCUREMENT: Prior to procurement, all parts should be verified for CSI status. All CSIs must be procured from AMCOM/RDECOM approved sources. The approved sources of all CSIs including those not listed in Table B-2 may be obtained from the ARISE CSI Database, Joint Services Critical Item Data Viewer, contract, or from the Contracting Officer. If the procurement of off the shelf, surplus, or a local purchase of a CSI is necessary, approval must be authorized by the RDECOM Aviation Engineering Directorate prior to any procurement action.
Documentation as an approved source does not constitute prior authorization for off the shelf, surplus, or local purchase. Each procurement action must be individually authorized and purchase orders should contain all clauses, CLINs, and other requirements specified by AED and/or contract. For commercial vendors, local purchase should be IAW contract requirements. New producers must be approved via Source Approval Request (SAR) procedures set forth in the Competition Advocate’s Shopping List (CASL). If during contract M&O, replacement parts are required that are not identified on the repair parts lists, the contractor will contact the Procurement Contracting Officer (PCO) for instructions on how to procure these parts."
REPLACE paragraph 2-7.1.d.(2) with the following:
"(2). MANUFACTURE: Prior to local manufacture, all parts should be verified for CSI status through the ARISE CSI Database, Joint Services Critical Item Data Viewer, contract, or from the Contracting Officer. All Government depot/contractor organizations performing M&O functions with a need to manufacture a CSI must obtain source approval from AMCOM/RDECOM, and they must be manufactured in accordance with
QE-STD-1."
MED FORM 24 FEB 2016
B 2474
Continuation Sheet
MEO NO.
PAGE of
WP NO. PAGE
NO.
PARA-
GRAPH
FIGURE/
TABLE
NO.
CHANGES
(EXACT WORDING OF CHANGES MUST BE GIVEN)
MED FORM 15-DEC-09 1401-R-E
2-3 thru 2-4
3)
4)
5)
6)
7)
REPLACE the last sentence in paragraph 2-7.1.d.(3) with the following:
"Contractors shall notify the PCO within 72 hours of any discovered nonconformances that may exist in previously delivered items, CSI or not."
REPLACE the last two sentence in paragraph 2-7.1.d.(4) with the following:
"A recommended method is provided in ISO10012. M&TE used to inspect and/or measure CSIs must discriminate to within 10 percent of the total tolerance span. For features being inspected for tolerances less than 0.001 inches, M&TE must discriminate to 20 percent of the total tolerance span."
REPLACE paragraph 2-7.1.d.(5) with the following:
"(5). RECORDS: All records relating to CSI shall be traceable to the date and place of M&O. All purchase orders for subcontracted products or processes that contain CCs must clearly identify the CCs and any AED and/or contract-specified requirements for compliance. All documents and referenced data for CSIs shall be available for review by the Government to determine compliance."
REPLACE "assure" with "ensure" in the last sentence of paragraph 2-7.1.d.(6).
REPLACE paragraph 2-7.1.d.(7) subparagraph's with the following:
" (a) An examination and inspection upon receipt to detect damage in transit, completeness and proper type.
(b) Verification of quantity upon receipt.
(c) Periodic inspection and precautions to ensure proper use, storage, handling during storage, and disposition.
(d) Functional testing, either prior to or after installation, or both, as required by contract to determine satisfactory operation.
MED FORM 24 FEB 2016
B 2474
Continuation Sheet
MEO NO.
PAGE of
WP NO. PAGE
NO.
PARA-
GRAPH
FIGURE/
TABLE
NO.
CHANGES
(EXACT WORDING OF CHANGES MUST BE GIVEN)
MED FORM 15-DEC-09 1401-R-E
3-127
B-1
3-13.24
B-1
(e) Identification and protection from improper use or disposition.
(f) Damaged/non-conforming Government Furnished Material shall be identified as such and is to be segregated in a secure controlled area pending Government disposition instructions."
ADD "NOTE" above second bulleted paragraph.
ADD the following paragraphs above paragraph B-1:
"CSI/non-CSI status of all parts shall be verified prior to procurement.
(See the CSI Program Procurement section for details).
Prior to procurement, source-control requirements shall be verified for all parts. All source-controlled parts must be procured from AMCOM-approved sources IAW requirements outlined in the Defense Federal Acquisition Regulation Supplement-Procedures, Guidance and Information DFARS PGI 217.7506. The listing of approved sources for source-controlled parts can be obtained from AMCOM. (See the CSI Program Procurement section for details)."
MED FORM 24 FEB 2016