Attachment 44 - Design Maturity Self Assessment.xlsx

XLSX spreadsheet 29 KB Posted

Attached to
Mobile Protected Firepower
Solicitation number
W56HZV18R0001
Issued by

About this file

Attachment 44 - Design Maturity Self Assessment

View the file

Other files

File Type Posted
MPF_RFP_W56HZV-18-R-0001_-_Questions_and_Answers_BATCH_8_(Distro_A).pdf PDF
MPF_RFP_W56HZV-18-R-0001_QandA_Batch_7_(Distro_A).pdf PDF
MPF_RFP_W56HZV-18-R-0001_-QandA_Batch_6_(Distro_A).pdf PDF
MPF_RFP_W56HZV-18-R-0001_-_Questions_and_Answers_Batch_5_(Distro_A).pdf PDF
W56HZV-18-R-0001,_Conformed_Copy__(through_Amendment_0002).pdf PDF
MPF_RFP_W56HZV-18-R-0001_-QandA_Batch_4_(Distro_A).pdf PDF
W56HZV-18-R-0001-0002.pdf PDF
MPF_RFP_W56HZV-18-R-0001_-QandA_Batch_3_(Distro_A).pdf PDF
W56HZV-18-R-0001_Conformed_copy_(through_AMD1).pdf PDF
Attachment_28_-_Equipment_Publications_Defects_List.pdf PDF
Attachment_55_-_Technical_Data,_Computer_Software_and_Patent_License_Identification_and_Assertions.xlsx XLSX spreadsheet
W56HZV18R0001-0001.pdf PDF
Attachment_54_-_Force_Structure_Worksheet.xlsx XLSX spreadsheet
Attachment_35_-EMD__Pricing_Spreadsheet.xlsx XLSX spreadsheet
MPF_W56HZV-18-R-0001_-_Questions_and_Answers_-_BATCH_2_(Distro_A).pdf PDF
Attachment_40_-_EMD_VATEP_Adjustment_Spreadsheet.xlsx XLSX spreadsheet
Attachment_51_-_Identification_and_Assertion_of_Restrictions.xlsx XLSX spreadsheet
Attachment_56_-_Special_License_Requirements.pdf PDF
Attachment_36_-_LRIP_Pricing_Spreadsheet.xlsx XLSX spreadsheet
Attachment_01_-_DD254.pdf PDF
Q&A-Batch_1-Distro_A.pdf PDF
Attachment 28 - Equipment Publications Defects List.pdf PDF
Attachment 38 - SBP Workbook Instructions.pdf PDF
Attachment 41 - Logistics Product Data - Packaging Data Requirements.pdf PDF
Attachment 33 - Performance Requirements Worksheet.pdf PDF
Attachment 12 - Vehicle Dynamics Data Sheet.xlsx XLSX spreadsheet
Attachment 02 - IEEE 15288-2 FCA-SVR-PCA Criteria Tailoring.pdf PDF
Attachment 47 - CARC Paint Drawing.pdf PDF
Attachment 11 - Vehicle Propulsion Data Sheet.xlsx XLSX spreadsheet
Attachment 03 - MPF Production Readiness Review Checklist.xlsx XLSX spreadsheet
Attachment 29 - LRC Design Proposal Format.pdf PDF
Attachment 01 - MPF DD Form 254.pdf PDF
W56HZV-18-R-0001.pdf PDF
Attachment 26 - Attribute Selection Sheet.pdf PDF
Attachment 39 - SBP Certification Subcontractor.pdf PDF
Attachment 37 - SBP Workbook.xlsx XLSX spreadsheet
Attachment 19 - Request for Use of Prohibited Materals.pdf PDF
Attachment 51 - Assertions for Tech Data and Computer Software.xlsx XLSX spreadsheet
Attachment 35 - Pricing Spreadsheet.xlsx XLSX spreadsheet
Attachment 27 - Critical Stockage List.pdf PDF
Attachment 10 - ATPD-2407 PDF
Attachment 04 - CSDR Plan.pdf PDF
Attachment 06 - MPF OPSEC Plan.pdf PDF
Attachment 30 - Critical Task List.pdf PDF
Attachment 20 - Production Government Format TDP Requirements.pdf PDF
Attachment 31 - Weld Standards Table 1.pdf PDF
Attachment 42 - Incoming Transaction Format.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Title Page

Attachment 44 Design Maturity Self Assessment

Distribution A

10/24/2017

Maturity Level

System Maturity LevelArtifacts Required to Achieve LevelLocation within Proposal (if provided)
Level 1
Requirements AnalysisRequirements Decomposition Completed
Functional Baseline Completed
Software Requirements Documented
Derived Requirement Development Completed
Interface Identification Completed
Reliability and Maintainability (R&M) Program Plan completed
R&M Allocations Completed
Level 2
Preliminary Design AnalysisAllocated Baseline Completed
Software Requirements Validated
Component Analysis/Selection Completed
Interface Designs Completed
Lessons Learned from previous design generation(s) implemented
Design for Manufacturability Study Completed
R&M Modeling and Prediction Completed
Cybersecurity Architectural Design Trade Study Analysis Completed
Design Failure Mode Effects and Analysis (DFMEA), Fault Tree Analysis (FTA), Critical Items List (CIL) Completed
Level 3
Subsystem Integration, Testing and AnalysisSub Systems Integration/Testing/Analysis on Hull/Structure/Frame Completed
Sub Systems Integration/Testing/Analysis on Running Gear Completed
Sub Systems Integration/Testing/Analysis on Base Vehicle Protection Completed
Sub Systems Integration/Testing/Analysis on Armor Kits Completed
Sub Systems Integration/Testing/Analysis on Interior Force Protection Technologies Completed
Sub Systems Integration/Testing/Analysis on Power Generation and Distribution Completed
Sub Systems Integration/Testing/Analysis on Optics and Sensors Solutions Completed
Sub Systems Integration/Testing/Analysis on Powertrain (to include cooling) Completed
Sub Systems Integration/Testing/Analysis on Vehicle Electronics Architecture/Software Completed
Sub Systems Integration/Testing/Analysis on Fire Control System/Software Completed
Power Generation Architectures Completed
Vetronics/Software Architectures Completed
Requirements Compliance Matrix Completed
Component Qualification Testing Completed
Materials Analyzed for Hull/Structure/Frame/Protection
Software Integration/Testing/Analysis completed
Failure Analysis Completed
R&M system level M&S, Analysis, and sub-system level testing completed
Cybersecurity assessment of subsystem components
R&M modeling and prediction updated with the reduced failure rates
Level 4
System Integration, Testing and AnalysisSystem Demonstrator Fabricated
Integrated System Testing (to current requirements) Completed
Automotive Performance Testing (to current requirements) Completed
Turret Performance Testing (to current requirements) Completed
Optics and Sensors Performance Testing (to current requirements) Completed
Fire Control Performance Testing (to current requirements) Completed
Failure Analysis Completed
Software Integration Schedule Completed
Cybersecurity assessment of integrated system completed
The system level R&M test completed, data collected and analyzed, failure analysis completed, and R&M predictions updated with test results
Level 5
Post-Testing Detailed Design AnalysisDesign Finalized (to current requirements)
CAD Drawings Finalized (to current requirements)
Software Support Plan Finalized
Interface Design Finalized (to current requirements)
Requirements Compliance Finalized
Manufacturing plan finalized
Cybersecurity vulnerability assessment completed
Corrective actions for the failures from system level testing developed and R&M predictions updated with the reduced failure rates (to current requirements)

&"-,Bold"&14Attachment 44

Page &P of &N 24 October 2017

Data Validation

Yes
No