07_ITEM 01.2-7_ADD 02_Section 07 27 26.pdf

PDF 33 KB Posted

Attached to
F-35 THREE BAY SPECIALIZED HANGAR Federal contract opportunity
Solicitation number
W50S9F-22-B-0001
Issued by
Department of the Army National Guard

About this file

This is a summary of an invitation for bid solicitation and related federal contract opportunity. The solicitation is for the construction of a new three-bay specialized hangar at Dane County Regional Airport - Truax Field in Madison, Wisconsin to support F-35 mission operations. Services required include demolishing an existing 19,875 square foot building and constructing a new 31,000 square foot three-bay hangar with administrative and shop spaces. The hangar bays must provide pre-conditioned aircraft air, 270VDC aircraft power, fire suppression, and HVAC. The contract also includes options for a paint/mix addition and aircraft rated pavement. The North American Industry Classification code is 236220 and size standard is $39.5 million. The contract duration is 550 days from notice to proceed. The solicitation is unrestricted with HubZone preference and requires a small business subcontracting plan from the apparent low bidder. The bid opening will be conducted according to FAR Subpart 14.4 and DFARS Subpart 214.4. Interested contractors must register in SAM and check the site periodically for amendments. The solicitation and documents are available on SAM.gov only.

View the file

Other files for this federal contract opportunity

Other files attached to F-35 THREE BAY SPECIALIZED HANGAR, newest first.
File Type Posted
Questions and Answers 4.pdf PDF
08_ITEM 01.2-8_ADD 04_Section 11 94 10.pdf PDF
13_ITEM 01.3-3_ADD 04_02700C-601.pdf PDF
21_ITEM 01.3-11_ADD 04_02700A-501.pdf PDF
FSB2020-270-00 - WI-ANG - 3-Bay Hangar - Addendum 004 COMBINED DRAWINGS.pdf PDF
22_ITEM 01.3-12_ADD 04_02700A-502.pdf PDF
Questions and Answers 3.pdf PDF
W50S9F22B0001 Solicitation - Amend 0003.pdf PDF
08_ITEM 01.2-8_ADD 03_Section 21 13 18.pdf PDF
10_ITEM 01.2-10_ADD 03_Section 26 08 00.pdf PDF
12_ITEM 01.3-2_ADD 03_02700C-100.pdf PDF
25_ITEM 01.3-15_ADD 03_02700A-505.pdf PDF
27_ITEM 01.3-17_ADD 03_02700A-511.pdf PDF
32_ITEM 01.3-22_ADD 03_02700A-702.pdf PDF
35_ITEM 01.3-25_ADD 03_02700FA101.pdf PDF
01_ITEM 01.2-1_ADD 03_Section 02 65 00.pdf PDF
07_ITEM 01.2-7_ADD 03_Section 21 13 13.pdf PDF
Questions and Answers 2.pdf PDF
00_FSB2020-270-00_WI-ANG_3-Bay_ADD NO. 03_2022.06.14_Narrative.pdf PDF
04_ITEM 01.2-4_ADD 03_Section 05 51 33.pdf PDF
05_ITEM 01.2-5_ADD 03_Section 08 71 00.pdf PDF
17_ITEM 01.3-7_ADD 03_02700SF102.pdf PDF
21_ITEM 01.3-11_ADD 03_02700A-306.pdf PDF
22_ITEM 01.3-12_ADD 03_02700A-307.pdf PDF
26_ITEM 01.3-16_ADD 03_02700A-510.pdf PDF
29_ITEM 01.3-19_ADD 03_02700A-601.pdf PDF
Bid Opening Directions.pdf PDF
02_ITEM 01.2-1_ADD 02_PROJECT TOC.pdf PDF
08_ITEM 01.2-9_ADD 02_Section 08 87 35.pdf PDF
17_ITEM 01.3-3_ADD 02_02700C-301.pdf PDF
27_ITEM 01.3-13_ADD 02_02700SF106.pdf PDF
39_ITEM 01.3-25_ADD 02_02700FA101.pdf PDF
40_ITEM 01.3-26_ADD 02_02700FA102.pdf PDF
41_ITEM 01.3-27_ADD 02_02700FA601.pdf PDF
47_ITEM 01.3-33_ADD 02_02700EP701.pdf PDF
31_ITEM 01.3-17_ADD 02_02700A-103.pdf PDF
03_ITEM 01.2-2_ADD 02_Section 01 50 00.pdf PDF
11_ITEM 01.2-12_ADD 02_Section 26 42 13.pdf PDF
18_ITEM 01.3-4_ADD 02_02700C-401.pdf PDF
22_ITEM 01.3-8_ADD 02_02700SF101.pdf PDF
26_ITEM 01.3-12_ADD 02_02700SF105.pdf PDF
34_ITEM 01.3-20_ADD 02_02700A-202.pdf PDF
44_ITEM 01.3-30_ADD 02_02700EG601.pdf PDF
46_ITEM 01.3-32_ADD 02_02700EP601.pdf PDF
B.07.Pre-Proposal Slides - F-35 3-Bay Hangar.pdf PDF
ATTACHMENT 7 - 20220208 Single Source Determination - Monaco - Redacted.pdf PDF
W50S9F22B0001 Solicitation - F-35 3-Bay Hangar.pdf PDF
ATTACHMENT 4 - 20220208 Single Source Determination - Advantor - Redacted.pdf PDF
ATTACHMENT 8 - SFS Form 12 - Template.xls XLS spreadsheet
ATTACHMENT 9 - Volume 6 - WI ANG F-35 3-Bay GBCI ADD 01.pdf PDF
Show all 50

F-35 THREE BAY SPECIALIZED HANGAR has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ANG/WI - F-35: 3-Bay Specialized Hangar 20202700F353BAY Addendum No. 02 8 June 2022

SECTION 07 27 26

FLUID-APPLIED MEMBRANE AIR BARRIERS

05/17

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AIR BARRIER ASSOCIATION OF AMERICA (ABAA)

ABAA Accreditation Accreditation

ABAA QAP Quality Assurance Program

ASTM INTERNATIONAL (ASTM)

ASTM C836/C836M (2015) High Solids Content, Cold Liquid-Applied Elastomeric Waterproofing Membrane for Use With Separate Wearing Course

ASTM D412 (2016) Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension

ASTM D4263 (1983; R 2018) Standard Test Method for Indicating Moisture in Concrete by the Plastic Sheet Method

ASTM D4541 (2017) Standard Test Method for Pull-Off Strength of Coatings Using Portable Adhesion Testers

ASTM D5590 (2000; R 2010; E 2012) Standard Test Method for Determining the Resistance of Paint Films and Related Coatings to Fungal Defacement by Accelerated Four-Week Agar Plate Assay

ASTM E84 (2020) Standard Test Method for Surface Burning Characteristics of Building Materials

ASTM E96/E96M (2016) Standard Test Methods for Water Vapor Transmission of Materials

ASTM E283 (2019) Standard Test Method for Determining the Rate of Air Leakage Through Exterior Windows, Curtain Walls, and Doors Under Specified Pressure Differences Across the Specimen

ASTM E331 (2000; R 2016) Standard Test Method for

SECTION 07 27 26 Page 1

Water Penetration of Exterior Windows, Skylights, Doors, and Curtain Walls by Uniform Static Air Pressure Difference

ASTM E2178 (2013) Standard Test Method for Air Permeance of Building Materials

ASTM E2357 (2017) Standard Test Method for Determining Air Leakage of Air Barrier Assemblies

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 285 (2012) Standard Fire Test Method for Evaluation of Fire Propagation Characteristics of Exterior Non-Load-Bearing Wall Assemblies Containing Combustible Components

1.2 RELATED REQUIREMENTS

Coordinate the requirements of Section 07 27 10.00 10 BUILDING AIR BARRIER SYSTEM, Section 07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS, and other building enclosure sections to provide a complete building air barrier system. Submit all materials, components and assemblies of the air barrier system together as one complete submittal package.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Qualifications of Manufacturer ; G

Qualifications of Installer ; G

SD-02 Shop Drawings

Fluid-Applied Membrane Air Barrier ; G

SD-03 Product Data

Fluid-Applied Membrane Air Barrier ; G

Transition Membrane ; G

Primers, Adhesives, and Mastics ; G

Reinforcement ; G

Safety Data Sheets ; G

SECTION 07 27 26 Page 2

SD-04 Samples

Fluid-Applied Membrane Air Barrier Mockup; G

SD-06 Test Reports

Capillary Moisture Test ; G

Field Peel Adhesion Test ; G

Flame Propagation of Wall Assemblies ; G

Flame Spread and Smoke Developed Index Ratings ; G

Site Inspections Reports; G

SD-07 Certificates

Fluid-Applied Membrane Air Barrier ; G

Transition Membrane ; G

SD-08 Manufacturer's Instructions

Fluid-Applied Membrane Air Barrier ; G

Transition Membrane ; G

Primers, Adhesives, and Mastics ; G

1.4 MISCELLANEOUS REQUIREMENTS

For fluid-applied membrane air barrier s provide the following:

1.4.1 Shop Drawings

Submit fluid-applied membrane air barrier shop drawings showing locations and extent of barrier assemblies, transition membranes, details of all typical conditions, intersections with other envelope assemblies and materials, and membrane counterflashings. Show details for bridging of gaps in construction, treatment of inside and outside corners, expansion joints, methods of attachment of materials covering the self-adhered barrier without compromising the barrier. Indicate how miscellaneous penetrations such as conduit, pipes, electric boxes, brick ties, and similar items will be sealed.

1.4.2 Product Data

Submit manufacturer's technical data indicating compliance with performance and environmental requirements, manufacturer's printed instructions for evaluating, preparing, and treating substrates, temperature and other limitations of installation conditions, safety requirements for installation, and Safety Data Sheets . Indicate flame and smoke spread ratings for all products.

1.4.3 Mockup

Provide a mockup of the fluid-applied membrane air barrier. Apply product in an area designated by the Contracting Officer. Apply an area of not

SECTION 07 27 26 Page 3 less than 54 square feet . Include all components specified as representative of the complete system. Notify the Contracting Officer a minimum of 48 hours prior to the test application. Select a test area representative of conditions to be covered including window or door openings, wall to ceiling transitions, flashings, and penetrations, as applicable.

1.4.4 Test Reports

Submit test reports indicating that capillary moisture tests and field peel adhesion test s on all substrate materials have been performed and the changes made, if required, in order to achieve successful and lasting adhesion. Submit test reports for flame propagation of wall assemblies tested in accordance with NFPA 285 . Submit test reports for flame spread and smoke developed index ratings of barrier materials tested in accordance with ASTM E84.

1.5 DELIVERY, STORAGE, AND HANDLING

1.5.1 Delivery

Deliver and store materials in sufficient quantity to allow for uninterrupted flow of work. Inspect materials delivered to the site for damage and store out of weather. Deliver materials to the jobsite in their original unopened packages, clearly marked with the manufacturer's name, brand designation, description of contents, and shelf life of containerized materials. Store and handle to protect from damage.

1.5.2 Storage

Inspect materials delivered to the site for damage; unload and store out of weather in manufacturer's original packaging. Store only in dry locations, not subject to open flames or sparks, and easily accessible for inspection and handling. Protect stored materials from direct sunlight.

1.6 CAPILLARY MOISTURE TEST

Perform a capillary moisture test by plastic sheet method in accordance with ASTM D4263 on the construction mockup and substrate materials.

Perform test after curing period as recommended by the air barrier manufacturer. Record mode of failure and area which failed in accordance with ASTM D4263. Once the air barrier material manufacturer has established a minimum adhesion or moisture level for the product on the particular substrate, indicate on the inspection report whether this requirement has been met. Where the manufacturer has not declared a minimum adhesion or moisture value for their product and substrate combination, the inspector must record actual values.

1.7 FIELD PEEL ADHESION TEST

Perform a field peel adhesion test on a construction mockup. Test the applied product for adhesion in accordance with manufacturer's recommendations. Perform test after curing period recommended by the manufacturer. Record mode of failure and area which failed in accordance with ASTM D4541. When the manufacturer has established a minimum adhesion level for the product on the particular substrate, the inspection report must indicate whether this requirement has been met. Where the manufacturer has not declared a minimum adhesion value for their product/substrate combination, the inspector must record actual values.

SECTION 07 27 26 Page 4

1.8 AIR BARRIER TESTING

Perform air barrier testing in accordance with Section 07 05 23 PRESSURE

TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS.

1.9 QUALITY ASSURANCE

1.9.1 Qualifications of Manufacturer

Submit documentation verifying that manufacturer of fluid-applied membrane air barrier is currently accredited by the Air Barrier Association of America ( ABAA Accreditation https://www.airbarrier.org/ ).

1.9.2 Qualifications of Installer

Submit documentation verifying that installers of the fluid-applied membrane air barrier are currently certified in accordance with the ABAA QAP Quality Assurance Program ( https://www.airbarrier.org/qap/ ).

1.10 PRECONSTRUCTION MEETING

Conduct a preconstruction meeting a minimum of two weeks prior to commencing work specified in this Section. Agenda must include, at a minimum, construction and testing of construction mock up, sequence of construction, coordination with substrate preparation, materials approved for use, compatibility of materials, coordination with installation of adjacent and covering materials, and details of construction. Attendance is required by representatives of related trades including covering materials, substrate materials, adjacent materials, and materials and components of the fluid-applied membrane air barrier.

1.11 ENVIRONMENTAL CONDITIONS

1.11.1 Temperature

Install fluid-applied membrane air barrier within the range of ambient and substrate temperatures as recommended in writing by the fluid-applied membrane air barrier manufacturer. Do not apply fluid-applied membrane air barrier to a damp or wet substrate. Do not apply during inclement weather or when ice, frost, surface moisture, or visible dampness is present on surfaces to be covered, or when precipitation is imminent.

1.11.2 Exposure to Weather

Protect fluid-applied membrane air barrier products from direct exposure to rain, snow, sunlight, mist, and other extreme weather conditions.

Replace, at no additional cost to the government, barrier products that have been exposed to ultraviolet (sun)light longer than allowed by manufacturer's written requirements.

PART 2 PRODUCTS

2.1 FLUID-APPLIED MEMBRANE AIR BARRIER

Provide a fluid-applied, vapor permeable, air barrier. This barrier must exhibit no visible water leakage when tested in accordance with ASTM E331 and must perform as a liquid water drainage plane with thru-wall flashing to discharge incidental condensation and water penetration to the exterior

SECTION 07 27 26 Page 5 of the building enclosure. Provide products suitable for use within temperature ranges specified by manufacturer for the location of the project.

2.1.1 Physical Properties

a. Air Permeance ( ASTM E2178): less than 0.004 CFM per sf at 1.57 psf .

b. Air Leakage ( ASTM E2357, ASTM E283): Less than 0.04 CFM per sf at 1.57 psf at one inch .

c. Water Vapor Permeance (Vapor Permeable Membrane) ( ASTM E96/E96M, desiccant method A): 10.0 perms .

d. Tensile Strength ( ASTM D412): Not less than 138 psi .

e. Elongation ( ASTM D412): Not less than 300 percent.

f. Low temperature Flexibility and Crack Bridging ( ASTM C836/C836M):

Pass at minus 15 degrees F .

g. Solids by Volume: minimum 50 percent.

h. Flame propagation of wall assemblies ( NFPA 285 ): Pass

i. Surface Burning Characteristics ( ASTM E84):

(1) Flame Spread Index Rating not higher than 75 .

(2) Smoke Developed Index Rating not higher than 150 .

j. Resistance to Mold, Mildew and Fungal Growth ( ASTM D5590): 0, No growth.

2.2 PRIMERS, ADHESIVES, AND MASTICS

Provide primers, adhesives, mastics, sealants and other accessories as recommended by manufacturer of fluid-applied membrane air barrier for a complete installation.

2.3 SHEET METAL FLASHING

Provide as specified in Section 07 60 00 FLASHING AND SHEET METAL.

2.4 JOINT SEALANTS

Provide as specified in Section 07 92 00 JOINT SEALANTS.

2.5 REINFORCEMENT

Provide fiberglass mesh tape, or fluid-applied air barrier manufacturer's approved equal product, reinforcement at seams, edges, projections and penetrations. Reinforce all joints exceeding 1/4 inch with fiberglass mesh.

PART 3 EXECUTION

3.1 EXAMINATION

Before installing fluid-applied membrane air barrier, examine substrates, SECTION 07 27 26 Page 6 areas, and conditions under which fluid-applied membrane air barrier assemblies will be applied, with installer present, for compliance with requirements. Ensure the following conditions are met:

a. Surfaces are sound, dry, even, and free of oil, grease, dirt, excess mortar or other contaminants detrimental to the adhesion of the membranes.

b. Masonry surfaces are cured and dry, smooth without large voids, spalled areas or sharp protrusions. Do not proceed with installation until after minimum concrete curing period recommended by fluid-applied membrane air barrier manufacturer.

c. Fill voids, gaps and spalled areas in substrate to provide an even plane. Strike masonry joints full flush.

d. Verify substrate is visibly dry and free of moisture. Test for capillary moisture by plastic sheet method in accordance with ASTM D4263 and take suitable measures until substrate passes moisture test.

e. Verify sealants used in substrates, and in joints between substrates, are compatible with fluid-applied membrane air barrier.

3.2 PREPARATION

Clean, prepare, and treat substrate in accordance with manufacturer's written instructions. Ensure clean, dust-free, and dry substrate for fluid-applied membrane air barrier application.

a. Remove dust, dirt and other contaminants from joints and cracks before coating surfaces.

b. Prepare, treat, and seal vertical and horizontal surfaces at terminations and penetrations through fluid-applied membrane air barrier.

c. At changes in substrate plane, provide transition material (bead of sealant, mastic, extruded silicone sealant, membrane counterflashing or other material recommended by manufacturer) under transition membrane to eliminate all sharp 90 degree inside corners and to make a smooth transition from one plane to another.

d. Provide mechanically fastened non-corrosive metal sheet to span gaps in substrate plane and to make a smooth transition from one plane to the other. Continuously support membrane with substrate.

e. For exterior sheathing substrates, ensure that exterior sheathing is stabilized, with corners and edges fastened with appropriate screws.

Treat all joints in accordance with the air barrier manufacturer's instructions prior to application of air barrier material. Allow sufficient time for joint treatments to fully cure before application of transition membranes and fluid-applied membrane air barrier.

f. For masonry substrates, fill all voids and holes, particularly in mortar joints, with non-shrinking grout.

g. Mask off and cover adjacent surfaces to protect from spillage and overspray.

SECTION 07 27 26 Page 7

3.3 INSTALLATION

3.3.1 Installation of Transition Membrane

Install transition membrane materials in accordance with the details on the drawings and the following:

a. Install transition membrane at all required locations prior to installation of the fluid-applied membrane air barrier.

b. Verify transition membrane is fully adhered to substrate and that its surface is clean, dry and wrinkle free prior to installation of the fluid-applied membrane air barrier.

c. Verify transition membrane completely covers all transition areas and will provide continuity of the finished fluid-applied membrane air barrier without gaps or cracks.

3.3.2 Installation of Flashing

Counterflash upper edge of thru-wall flashing and fluid-applied air barrier. Counter flashing and thru-wall flashing are specified in Section

07 60 00 FLASHING AND SHEET METAL.

3.3.3 Installation of Fluid-Applied Membrane Air Barrier

Install materials in accordance with manufacturer's recommendations and the following:

a. Apply fluid-applied membrane air barrier in single or dual coat application by spray or roller. Apply fluid-applied membrane air barrier within manufacturer's recommended temperature range for application.

b. Apply fluid-applied membrane air barrier in manner and at rate and wet film thickness recommended by manufacturer to yield a finished dry film thickness of not less than 40 mils for smooth surfaces and 60 mils for CMU or as otherwise required by the manufacturer for the application substrate material and surface roughness.

c. Apply fluid-applied membrane air barrier around all penetrations ensuring a complete and continuous air barrier. Lap fluid-applied membrane air barrier a minimum of 3 inch over transition membrane to seal leading edge.

d. Seal membrane terminations, heads of mechanical fasteners, masonry tie fasteners, around penetrations, HVAC assemblies, plumbing and electrical assemblies, doors, windows, louvers, and other assemblies penetrating the fluid-applied membrane air barrier with a termination sealant recommended by the fluid-applied membrane air barrier manufacturer.

e. Notify the Contracting Officer and Testing Agency upon completion of fluid-applied membrane air barrier installation. Air barrier materials and assemblies must remain exposed until tested and inspected by the ABAA.

f. Do not allow materials to come in contact with chemically incompatible

SECTION 07 27 26 Page 8 materials.

3.3.4 Installation of Reinforcement

Install reinforcement at projections, corners, joints, and penetrations where applicable.

3.4 FIELD QUALITY CONTROL

3.4.1 Site Inspections and Testing

Provide site inspections and testing in accordance with ABAA protocol to verify conformance with the manufacturer's instructions, the ABAA QAP Quality Assurance Program ( https://www.airbarrier.org/qap/ ), Section 07 27 10.00 10 BUILDING AIR BARRIER SYSTEM, Section 07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS, and this section.

a. Conduct inspections and testing at 5, 50, and 95 percent completion of this scope of work. Forward written inspection reports to the Contracting Officer within five working days of the inspection and test being performed.

b. If the inspections reveal any defects, promptly remove and replace defective work at no additional expense to the Government.

3.5 PROTECTION AND CLEANING

3.5.1 Protection

Protect fluid-applied membrane air barrier assemblies from damage during application and remainder of construction in accordance with manufacturer's written instructions.

Coordinate installation, testing, and inspection procedures to ensure exposure period does not exceed that recommended by the product manufacturer. Remove and replace, at no additional cost to the government, membrane products that exceed manufacturer's allowed exposure limits.

3.5.2 Cleaning of Adjacent Surfaces

Clean excess product from adjacent construction using cleaning agents and procedures as recommended in writing by the manufacturer of each type of affected construction and as acceptable to same.

3.6 CLEANUP OF SPILLS

Conduct cleanup of uncured product spillage in accordance with manufacturer's written safe handling instructions.

-- End of Section --

SECTION 07 27 26 Page 9

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 07 27 26 Page 10

File details come from the government source that posted it. Updated .