RFI_14.pdf

PDF 79 KB Posted

Attached to
REPLACE FIRE STATION Federal contract opportunity
Solicitation number
W50S8R-20-B-0001
Issued by
Department of the Army Ohio Army National Guard

About this file

This solicitation notice is for the replacement of a fire station at Mansfield Air National Guard Base in Mansfield, Ohio. The project includes construction of a new aircraft rescue and firefighting station to provide emergency response services related to the airfield and installation aircraft. Optional items to be included are concrete paving to the flightline in either a minimum or full width, four-fold apparatus doors, and a 5-ton bridge crane. The estimated construction duration is 660 calendar days with a contract value between $10-20 million. The solicitation is set aside for small businesses with a NAICS code of 236220 and size standard of $39.5 million average annual revenue. The pre-bid conference is scheduled for November 5, 2019 and bids must be submitted by November 26, 2019. The soliciting agency is the Department of the Army Ohio Army National Guard and any questions should be directed to the specified contracting officer.

View the file

Other files for this federal contract opportunity

Other files attached to REPLACE FIRE STATION, newest first.
File Type Posted
Abstract_FIRE_pg3.pdf PDF
Abstract_FIRE_signed.pdf PDF
bid opening attendees.pdf PDF
RFI_17.pdf PDF
RFI_20.pdf PDF
RFI_21.pdf PDF
RFI_21_attachment.pdf PDF
A-602 - INTERIOR FINISH-COLOR SCHEDULE.pdf PDF
RFI_18.pdf PDF
RFI_13.pdf PDF
RFI_16.pdf PDF
RFI_12.pdf PDF
RFI_08 attach.pdf PDF
RFI_07 attach.pdf PDF
RFI_09.pdf PDF
RFI_10_attachment.pdf PDF
RFI_10.pdf PDF
RFI_11.pdf PDF
RFI_06.pdf PDF
RFI_3_attachment.pdf PDF
RFI_2.pdf PDF
Attach6_Civil_6a.pdf PDF
Attach6_Civil_8a.pdf PDF
Attach6_Civil_5d.pdf PDF
Attach6_Civil_9.pdf PDF
Attach6_Civil_8b.pdf PDF
Attach6_Telecommunications.pdf PDF
Attach2_Vol_2_Specifications.pdf PDF
Attach6_General.pdf PDF
Attach6_Electrical.pdf PDF
Attach6_Fire_Alarm.pdf PDF
Attach6_Civil_4a.pdf PDF
Attach6_Civil_4b.pdf PDF
Attach6_Structural.pdf PDF
Attach6_Civil_3.pdf PDF
Attach7_Geotechnical_Report.pdf PDF
Attach4_Vol_4_Specifications.pdf PDF
Attach1_Vol_1_BOD.pdf PDF
Attach8_RFI_template.doc DOC document
Attach6_Civil_1b.pdf PDF
Attach6_Civil_1a.pdf PDF
EXHIBIT_A-Communications_Equipment.xlsx XLSX spreadsheet
EXHIBIT_B_Sealed_Bid_Reminders.pdf PDF
Attach3_Vol_3_Specifications.pdf PDF
Attach5_Vol_5_Specifications.pdf PDF
Attach6_Civil_5a.pdf PDF
Attach6_Civil_2.pdf PDF
Attach6_Civil_5c.pdf PDF
Attach6_Fire_Protection.pdf PDF
W50S8R-20-B-0001.pdf PDF
Show all 50

REPLACE FIRE STATION has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION

R E

Q U

E S

T O

R S

E C

T

IO

N

From:

Date:

11-19-2019

To: Contracting Officer

Gordon Strom

1. Solicitation Number:

W50S8R-20-B-0001

2. Location of Project:

Fire Station - Mansfield Ohio ANG

3. Information Requested: (Include Specification Section and/or Drawing Number and Page if inquiring about a discrepancy)

1. Section A on DWG S-301 shows a section 7/S-512, however section 7 on S-512 does not look like the section. Is there a section for the truss bearing detail?

2. Dwg C-503 Detail 4 calls for a Bicycle Rack. Is there a specification for the Bicycle Racks?

3. Dwg C-521, Detail 11 calls for a Horizontal Fall Protection, however I cannot find it on the Roof Plan, can you advise where it is to be located. Also, I could not find a specification for the Fall Protection. Can you provide?

4. Drawing A-111, Room 119 EOC, Note 10 calls for an Operable Partition. Please provide Specification for this item.

5. Drawings A-201 Note 16 and A-202 Note 14 call for Sun Control Devices. Please provide

Specification for this item. (Drawing A-310, Note 20 calls this out as a concrete-filled bollard).

6. Dwg A-111, per Note 10, calls for an Operable Partition, however I cannot find a specification for it. Also, the ceiling plans do not show the ceiling is to accommodate the operable partition. Please provide more information.

7. Dwg A-150, detail 1 shows a snow rail. However, I cannot find a specification or manufacturer, can a specification or manufacturer be provided?

8. Dwg S-521, shows a structural man door canopy, however several Architectural drawings A- 201, 202, 203 indicate a pre-finished man door canopy. Architectural drawing A-311 Detail 5 indicates a structural canopy but does not show any finishes. We cannot find a specification for the prefinished canopy. Can you provide more information?

9. Dwg A-201, Note 16 & A-202, Note 14 indicate a Sun Control, however we cannot find a specification or detail, can you provide more information?

Attachments:

Date Response Required:

By:

Title:

Requestor's FAX Number:

Requestor's Telephone Number:

R E

S P

O N

S E

To:

Date:

Response:

1. 7/S-512 should be revised to 3/S-522.

2. Commercial standard double-sided bicycle rack, that will fit within the allotted dimensions of drawing/specs, will meet this requirement.

3. There is no specification for this. This particular requirement is noted in specifications as a “Delegated Design”, meaning contractor shall provide solution to meet the requirement, that meets applicable fall protection-applicable standards/regulations/guidance (i.e. ANSI, OSHA, etc.)

4. Provide ModernFold Acousti-Seal 932 or similar product that meets the salient characteristics of this product.

5. Sun Control Devices shall be YKKAP ThermaShade with Square Outrigger, 3-5/8” airfoil and 3-1/2” fascia or equal. Drawing

A-310, Note 20 shall be changed to read “Sun Control Device”

6. Provide ModernFold Acousti-Seal 932 or similar product that meets the salient characteristics of this product, with manufacturers standard details for header installation

7. Provide S-5! with 2 snow rails or approved similar product that meets the salient characteristics of this product.

8. All man door canopies shall be installed per structural. The canopies shall be epoxy painted, color to match doors.

9. Sun Control Devices shall be YKKAP ThermaShade with Square

Outrigger, 3-5/8” airfoil and 3-1/2” fascia or equal.

This information is a clarification of the solicitation/contract and does not change the contract terms or conditions.

This information is a proposed change to the solicitation/contract. An amendment will be issued.

Contracting Officer: