This document outlines a pre-bid conference for a federal solicitation seeking offers to add and alter a small air terminal building. Key details include: the solicitation number and project name; a firm fixed price contract will be awarded under FAR Part 14 procedures for a 450-day period of performance; a site visit will follow the conference; questions are due by a specified date and will be answered and posted anonymously; the bid package must include pricing for all line items, representations and certifications, acknowledgement of amendments, and a bid bond; the bid opening location and time are specified; and the apparent low bidder must submit documents to establish responsibility prior to award.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2 June 2021
Pre-Bid Conference/Site Visit
Solicitation Number W50S87-21-B-5005
Add/Alter Small Air Terminal
Agenda
• Introduction
• Administrative Items
• Process for Questions and Answers
• Project Overview
• Solicitation, Plans, Specifications and Amendments
• Invitation for Bid Basics and Bid Requirements
• Break – approx. 10 min
• Site Visit to follow conference
Introduction
• SMSgt Bryant K Alexander– Contracting Officer
• Lt Col Lemuel Rios – Contracting Officer’s Representative (COR)
• Maj James Eaton – COR
• Mr. Hanson Pedersen – COR
Administrative items- Attendance Roster
• Ensure you sign in on the attendance roster
• We will post this roster to www.sam.gov in order to facilitate communication between potential subs and prime contractors
• A site visit will follow this presentation
• Any questions you have during the site visit should be sent in writing for an official response in accordance with the solicitation.
• Submit questions to SMSgt Bryant K Alexander. See Section 00100 for instructions.
• Questions and official answers will be posted on a non-attribution basis with solicitation information at www.sam.gov
• Submit questions NLT 7 business days prior to bid opening.
Do not contact the A/E or any Gov engineering personnel directly.
• Amendments will be only issued only if there is a change in the solicitation, specifications, or plans 5
Process for Questions and Answers
Project Overview
• A Firm Fixed Price contract will be awarded
• Invitation for Bid Procedures (FAR Part 14)
• Small Business Set-Aside
• NAICS: 236220
• Period of Performance: 450 calendar days after Notice to
Proceed (NTP) is issued. Important – Several phases
• NTP will be issued after approval of Performance and
Payment Bonds and all required pre-construction submittals
Project Overview
• Brand name requirements:
– Alerton: DDC
– Best: Door hardware
– Interior and exterior finishes
– Monaco: Fire alarm transceiver
– Sika Sarnafil: PVC Roof membrane
– Paradry – Parachute Lift System
Solicitation, Plans, Specifications and Amendments
• Located on the Contract Opportunities portion of the www.sam.gov website
• The Government is not liable for information furnished by any other source
• Amendments (SF30) will be posted to www.sam.gov. It is the offerors responsibility to check the website periodically for any amendments to the solicitation.
Bid Requirements
What you must submit (see Section 00010)
• SF 1442, (Blocks 14-20c)
– Do not enter less than 90 days in Block 17
• Section 00010, Bid Schedule- all items must be priced
– IAW Clause 252.236-7008, Contract Prices- Bidding Schedules. The prices shown in the Bidding Schedule must reflect ALL costs involved in performing the work, as described in the plans, specifications, and statement of work.
• Section 00600, Reps and Certs
– In addition, the offeror must have entered current and complete data within the past year in Online Representations and Certifications at www.sam.gov.
Provisions at 52.204-26 and 252.204-7016. If answer is “does,” need to fill out provisions at 52.204-24 and 252.204-7017. Recommend updating in SAM registration.
• Acknowledge all Amendments (SF 30)
• Bid Bond (Standard Form 24, 20%) and Power of Attorney
• The bid opening will occur at the time and date specified in Block 13 of the SF1442 at 4930 Minuteman Way, Charlotte, NC 28208 (map included in solicitation attachments).
• Hand Carried Bids - must be deposited in the repository prior to the time established for opening of bids.
• Mailed bids - must be received at the location specified in block 7 of the SF1442 prior to the time established for opening of bids.
• Repository and Mailing Address: 4930 Minuteman Way, Charlotte, NC 28208. Attention: Contracting Office, SMSgt Bryant K Alexander
• Late receipt of bids due to entry delays may not be deemed excusable and the Contracting Officer may declare the bid “late” in accordance with FAR
14.304 and in accordance with clause 52.214-7.
Bid Requirements- Bid Submission
Invitation for Bids Procedures What to expect at the Bid Opening
• Bid opening officer (BOO) will announce exact time bids are due and that no more bids will be accepted
• Bids are opened and read out loud with no discussion or comment on responsiveness (FAR 14.301) of bids, and recorded
• BOO opens Government estimate, records
• Abstract will be certified and posted to www.sam.gov as soon as practical.
Invitation for Bids Procedures Determination of Responsibility
IMPORTANT: Refer to the solicitation and FAR Part 9 for details
• A bidder is determined to be responsible in accordance with FAR
9.104
• After bids are publicly opened, an award will be made with reasonable promptness to that responsible bidder whose bid, conforming to the invitation for bids, will be most advantageous to the Government, considering only price.
• To establish its responsibility, the apparent low bidder will be requested by the Government prior to award, to submit a statement/documents regarding his previous experience in performing comparable work, his business and technical organization, financial and bonding resources and plant available to be used in performing the work.