W15QKN17R0006-0001.pdf

PDF 94 KB Posted

Attached to
Contractor Logistics Support Federal contract opportunity
Solicitation number
W15QKN-17-R-0006
Issued by
Department of the Army Materiel Command Contracting Command Picatinny Arsenal

About this file

Amendment 0001 to solicitation W15QKN-17-R-0006

View the file

Other files for this federal contract opportunity

Other files attached to Contractor Logistics Support, newest first.
File Type Posted
W15QKN17R0006-0003.pdf PDF
W15QKN17R0006-0002.pdf PDF
dd1423-1_-_A007_Report,_Record_of_Meeting_Minutes_rev2signed.pdf PDF
ATT_0016_PAST_PERFORMANCE_QUESTIONNAIRE.pdf PDF
Task_Order_0001_Performance_Work_Statement_(PWS)_FOR_INFORMATIONAL_PURPOSES_ONLY.pdf PDF
dd1423-1_-_F001_Funds_and_Man-Hour_Expenditure_Report_rev2signed.pdf PDF
ATT_0062_CLS_PRICING_WORKBOOK.xlsx XLSX spreadsheet
ATT_0063_TASK_ORDER_0001_PERFORMANCE_WORK_STATEMENT_(PWS)-_FOR_INFORMATIONAL_PURPOSES_ONLY.pdf PDF
ATT_0015_DD_254,_DEPARTMENT_OF_DEFENSE_CONTRACT_SECURITY_CLASSIFICATION_SPECIFICATION.pdf PDF
ATT_0003_Labor_Category_Definitions.pdf PDF
ATT_0016_PAST_PERFORMANCE_QUESTIONNAIRE.pdf PDF
ATT_0001_PM_CCS_Systems.pdf PDF
ATT_0022_PHRASELATOR_P2_TSP.pdf PDF
ATT_0003_LABOR_CATEGORY_DEFINITIONS.pdf PDF
ATT_0011_DD2345,_MILITARILY_CRITICAL_TECHNICAL_DATA_AGREEMENT.pdf PDF
ATT_0062_CLS_PRICING_WORKBOOK.xlsx XLSX spreadsheet
ATT_0024_VLAD_TSP.pdf PDF
ATT_0009_PROCEDURES_TO_DESIGNATE_A_US_INVITED_CONTRACTOR_UNDER_THE_US_ROK_SOFA.pdf PDF
ATT_0025_MAGNUM_SPIKE_STRIP_TSP.pdf PDF
ATT_0006_SAMPLE_FORMAT_FOR_FIELD_SERVICE_REPRESENTATIVE_(FSR)_EVENT_TRACKER.pdf PDF
ATT_0023_EPVK_TSP.pdf PDF
ATT_0029_MAGNUM_SPIKE_STRIP_Draft_TM_5-5340-101-10_-_20_Sep_2010.pdf PDF
ATT_0028_VLAD_TM_5-4240-536-10_-_30_Jun_2005.pdf PDF
ATT_0019_HAND_HELD_METAL_DETECTOR_Draft_TM_5-6350-312-10_-_20_Sep_2010.pdf PDF
ATT_0021_AHD_(MAD)_Draft_TM_5-5965-1934-10_-_20_Sep_2010.pdf PDF
ATT_0004_TSP_TMS_INSTALL_DEINSTALL_INSTRUCTIONS_AND_POI.pdf PDF
ATT_0015_DD_254,_DEPARTMENT_OF_DEFENSE_CONTRACT_SECURITY_CLASSIFICATION_SPECIFICATION.pdf PDF
ATT_0014_INME-PIC-IM_Form_3002,_CLEARANCE_OF_TECHNICAL_INFORMATION_FOR_PUBLIC_RELEASE.pdf PDF
ATT_0013_STANDARD_FORM_LLL,_DISCLOSURE_OF_LOBBYING_ACTIVITIES.pdf PDF
ATT_0063_TASK_ORDER_0001_PWS.pdf PDF
ATT_0007_SITE_LANE_PREPARATION.pdf PDF
ATT_0010_NON_DISCLOSURE_AND_NON_USE_AGREEMENT_for_W15QKN-17-R-0006.pdf PDF
ATT_0002_GOVERNMENT_LOCATIONS.pdf PDF
ATT_0012_AMSTA-AR_1350_TECHNICAL_DATA_AGREEMENT.pdf PDF
ATT_0020_ACOUSTIC_HAILING_DEVICE_(MAD)_TSP.pdf PDF
ATT_0008_QUALITY_ASSURANCE_SURVEILLANCE_PLAN_(QASP).pdf PDF
ATT_61_Tech_Manual_TM_9-2330-392-14&P.pdf PDF
W15QKN-17-R-0006.pdf PDF
ATT_0017_MISSION_ESSENTIAL_CONTRACTORS.pdf PDF
DD_1423_CDRLs.pdf PDF
ATT_0018_HAND_HELD_METAL_DETECTOR_TSP.pdf PDF
ATT_0027_EPVK_Draft_TM_5-2590-536-10_-_20_Sep_2010.pdf PDF
ATT_0026_PHRASELATOR_Draft_TM_5-5805-901-13.pdf PDF
ATT_0005_GOVERNMENT_FURNISHED_PROPERTY.pdf PDF
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of

2. Amendment/Modification No.

3. Effective Date

4. Requisition/Purchase Req No.

5. Project No. (If applicable)

6. Issued By Code 7. Administered By (If other than Item 6) Code

8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)

9A. Amendment Of Solicitation No.

9B. Dated (See Item 11)

10A. Modification Of Contract/Order No.

10B. Dated (See Item 13) Code Facility Code

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting And Appropriation Data (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS

It Modifies The Contract/Order No. As Described In Item 14.

A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In

The Contract/Order No. In Item 10A.

B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set

Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).

C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:

D. Other (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.

14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. Name And Title Of Signer (Type or print)

16A. Name And Title Of Contracting Officer (Type or print)

15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed

By (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITIONS UNUSABLE

30-105-02 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

SEE SCHEDULE

X

Firm Fixed Price

0001 2017MAR03

W15QKN

ARMY CONTRACTING COMMAND - NJ

PICATINNY ARSENAL, NJ 07806-5000

TIFFANY NOSTI

EMAIL: TIFFANY.N.NOSTI.CIV@MAIL.MIL

W15QKN-17-R-0006

2017FEB23

X

X

2 signed

SEE SECOND PAGE FOR DESCRIPTION

1 31

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION A - SUPPLEMENTAL INFORMATION

Buyer Name: TIFFANY NOSTI

Buyer Office Symbol/Telephone Number: ACC-NJ-CC/(973)724-7364

Type of Contract 1: Firm Fixed Price

Type of Contract 2: Cost No Fee

Kind of Contract: Service Contracts

*** End of Narrative A0000 ***

The purpose of Amendment 0001 to Solicitation W15QKN-17-R-0006 is to:

1. Update Section A, to include the response date and time, which remains unchanged from the date/time shown on FedBizOpps of 24 March

2017 2:00 PM EST.

2. Update Section A to include an alternate Point of Contact (POC), Tina G. Gopon Contracting Officer tina.g.gopon.civ@mail.mil. All correspondence should include both POCs.

3. Update Section C, Performance Work Statement (PWS) paragraph 5.1.1 by deleting the following statement: "The Contractor may occupy office space within the Fort Leonard Wood Army Installation if coordinated with and approved by the COR and KO."

4. Change Section H , FROM: "The Performance Work Statement for Task Order 0001 is provided for informational purposes only to facilitate the award of the first task order. The Government intends to award the first task order within two (2) weeks of contract award."

TO: The Performance Work Statement for Task Order 0001 (Attachment 0063) is provided for informational purposes only to facilitate the award of the first task order. The Government intends to award the first task order within two (2) weeks of contract award."

5. Update Section L, paragraph 3.3.1.c. FROM: "As a requirement under the CLS solicitation, all Offerors must submit Reps/Certs data into the System for Award Management (S.A.M.) at https://www.sam.gov/ and provide one (1) hard copy and one (1) previously submitted with the proposal."

TO: "As a requirement under the CLS solicitation, all Offerors must submit Reps/Certs data into the System for Award Management (SAM) at https://www.sam.gov/ and provide one (1) hard copy and one (1) electronic copy (on CD) submitted as an.XPS file. Any Offeror that has previously submitted Reps/Certs data into SAM is reminded to update the data prior to submitting with the proposal."

6. Update Section L, paragraph 5.2.2 FROM: "Offerors shall submit a list of all recent Government contracts (prime and major subcontracts) in performance or awarded to the Offeror and any of its major subcontractors within the past three (3) years, or awarded earlier than three (3) years ago, but for which deliveries/performance occurred or were scheduled to occur within the past three (3) years, which are relevant to the effort required by the solicitation."

TO: Offerors shall submit a list of all recent Government contracts (prime and major subcontracts) in performance or awarded to the

Offeror and any of its major subcontractors within the past five (5) years, or awarded earlier than five (5) years ago, but for which deliveries/performance occurred or were scheduled to occur within the past five (5) years, which are relevant to the effort required by the solicitation."

7. Update Section L, paragraph 5.1.1(d) FROM: "The Offeror shall provide descriptions of their Management ability to recruit, hire, and retain skilled qualified CENTCOM Field Service Representatives (FSR) as it relates to the activities, documentation, and timing cited in

Attachment 0002 of the PWS. The Offerors ability to provide uninterrupted high quality personnel coverage for CONUS & OCONUS, and

Theater work, including their ability to quickly deploy personnel for unplanned Theater requirements and maintain continuity of services in the midst of personnel disruptions such as sickness, leave, and terminations."

TO: "The Offeror shall provide description of their Managements ability to recruit, hire and retain skilled qualified personnel to ensure a stable workforce especially as it relates to the activities, documents and timing to process a Field Service Representative

(FSR) for deployment to each CENTCOM AOR country cited in Attachment 0002 of the PWS. The Offerors shall provide descriptions of their ability to provide uninterrupted high quality personnel coverage for CONUS & OCONUS, and Theater work, including their ability to quickly deploy personnel for unplanned Theater requirements and maintain continuity of services in the midst of personnel disruptions such as sickness, leave, and terminations."

8. Update Section L, paragraph 5.2.2(5)FROM: "The POCs shall be instructed to electronically complete Part II of the questionnaire and e-mail the entire questionnaire to the Contracting Officer and Contract Specialist within thirty (30) calendar days of the release of the RFP, to tina.g.gopon.civ@mail.mil and tiffany.n.nosti.civ@mail.mil."

TO: "The POCs shall be instructed to electronically complete Part II of the questionnaire and e-mail the entire questionnaire to the

2 31

W15QKN-17-R-0006 0001

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

Contracting Officer and Contract Specialist no later than the closing of the solicitation, 24 March 2017 at 2:00 pm EST, to tina.g.gopon.civ@mail.mil and tiffany.n.nosti.civ@mail.mil."

9. Update Section M, paragraph C.3.2. FROM: "For the purpose of evaluating proposals, recent is defined as occurring within the following time standards: 1) occurring within the past three (3) years, or 2) awarded earlier than three (3) year ago, but for which deliveries/performance occurred or were scheduled to occur within the past three (3) years."

TO: "For the purpose of evaluating proposals, recent is defined as occurring within the following time standards: 1) occurring within the past five (5) years, or 2) awarded earlier than five (5) years ago, but for which deliveries/performance occurred or were scheduled to occur within the past five (5) years."

10. Update Section M, paragraph C.3.4 FROM: "Based on the Offerors previous and current experience and performance on same or similar services (maximum three (3) years), including the frequency of cost growth and schedule delays, the Government will assess those risks associated with the Offerors past performance."

TO: "Based on the Offerors previous and current experience and performance on same or similar services (maximum five (5) years), including the frequency of cost growth and schedule delays, the Government will assess those risks associated with the Offerors past performance."

11. Update Section M, paragraph C.2.2.d FROM: "The Government will evaluate the adequacy and completeness of the description of

Managements ability to recruit, hire and retain skilled qualified CENTCOM Field Service Representative (FSR) as it relates to the activities, documentation and timing cited in Attachment 0002 of the PWS. The Offerors ability to provide uninterrupted high quality personnel coverage for CONUS & OCONUS and Theater work, including their ability to quickly deploy personnel for unplanned Theater requirements and maintain continuity of services in the midst of personnel disruptions such as sickness, leave and terminations."

TO: "The Government will evaluate the adequacy and completeness of the description of their Managements ability to recruit, hire and retain skilled qualified personnel to ensure a stable workforce especially as it relates to the activities, documents and timing to process a Field Service Representative (FSR) for deployment to each CENTCOM AOR country cited in Attachment 0002 of the PWS. The

Offerors shall provide descriptions of their ability to provide uninterrupted high quality personnel coverage for CONUS & OCONUS, and

Theater work, including their ability to quickly deploy personnel for unplanned Theater requirements and maintain continuity of services in the midst of personnel disruptions such as sickness, leave, and terminations."

12. Update Section J, replacing "Attachment 0003 LABOR CATEGORY DEFINITIONS", "Attachment 0015 DD 254, DEPARTMENT OF DEFENSE CONTRACT

SECURITY CLASSIFICATION SPECIFICATION", "Attachment 0062 CLS PRICING WORKBOOK" and "Attachment 0063 Task Order 0001 Performance Work

Statement (PWS) - For Informational Purposes Only" in their entirety.

13. Answer the following questions from industry:

Solicitation Section A:________________________

Q1. What is the due date/time of this solicitation.

A1. The solicitation is due by 24 March 2017 at 2:00 pm EST. See #1 above. The due date/time has been added to Section A of the

Solicitation as well.

Solicitation Section B:________________________

Q2. Will the Contractor be required to complete and price the CLIN's contained in Section "B" of the solicitation for the 60 month period of the basic IDIQ contract?

A2. As stated in Section B, "Offerors are not required to complete Section B of this RFP. Offerors shall submit their proposed fully loaded direct labor rates and indirect rates in Attachment 0062, CLS Pricing Workbook. The labor categories and respective loaded FFP labor rates and indirect rate(s) for Material, Other Direct Costs (ODCs), and Travel will be contractually binding upon contract award and are to be used in pricing task order proposals under the resultant contract." Attachment 0062, CLS Pricing Workbook, includes areas for labor rates to be entered for all five years of the IDIQ contract.

Q3. Recommend including Phase-In and Phase-Out CLINs.

A3. The Government appreciates this recommendation, however, the Government does not anticipate the need for these CLINs. The Offerors are required to provide a Transition Plan which accounts for any "phase in" period for the Awardee.

Q4. Recommend utilizing monthly support CLINs vs. current CLIN structure as PWS states that the Awardee is required to support all systems.

A4. Yes, the Awardee must support all systems, however, historically the funding has been allocated separately by the various programs

3 31

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

and due to the limitations of DFARS PGI 204.7108 Uniform Contract Line Item Numbering System, this is the best way to ensure proper payment.

Q5. Recommend a CLIN for repairs.

A5. The Government is responsible for furnishing the Contractor with any/all resupply actions when available spare parts are depleted.

Therefore, the repairs being completed are minimal as the equipment has recently been fielded and the Contractor is not responsible for supplying any spare parts. Furthermore, the Contractor personnel under this requirement are paid for a specific period of performance with duties including repair, maintenance, training, and logistics of the PM CCS systems and are not paid/reimbursed for each repair, training, or supply action. This is a Firm-Fixed Price with Cost No Fee CLINs, not a Firm Fixed Price Level of Effort, nor a Time-And -

Material effort type contract. The Government has CDRL reports in place for tracking purposes.

Solicitation Section C:________________________

Q6. Is it the Government's intention to include the Transition Plan referenced in 4.2.1 in the proposal directly into the contract?

A6. Yes, as stated in Section L, paragraph 5.1.2 Subfactor 2 Transition Plan, "This Transition Plan shall be incorporated into the contract by reference upon contract award."

Q7. The RFP includes Section C Performance Work Statement (PWS) and Attachment 0063 "Task Order 0001 Performance Work Statement (PWS)-

For Informational Purposes Only". These two documents appear to be a near mirror image with the exception of the information provided in paragraph 1.1. What is the Governments intent in submitting both Section C and Attachment 0063? Which document takes precedence in our response and subsequent Government evaluation?

A7. As stated in Section H, "The Performance Work Statement for Task Order 0001 is provided for informational purposes only to facilitate the award of the first task order. The Government intends to award the first task order within two (2) weeks of contract award." Attachment 0063 is the PWS for Task Order 0001 and is provided for informational purposes only and should not be utilized in developing a response to this Solicitation.

Q8. Would the Army consider allowing the vendor to store Fort Leonard Wood (FLW) Government Furnished Property (GFP) and provide a program management office at the contractors DSS-approved facility located outside the state?

A8. The Government's requirement is for the primary operating/supply locations mentioned in the Solicitation. As such, the Government will not consider relocating the GFP to a location outside FLW.

Q9. Does the Army have historical data on the number of training events per year?

A9. Historical data doesn't necessarily predict future schedules. The base contract projects an average of 3-4 training events per month to include about 8 site lane preparations per year. Task orders will be tailored to reflect anticipated training events by location for the associated period of performance.

Q10. Does the Army have historical data on repairs for each system?

A10. Spider maintenance site visits would depend on available funding. However, the Government forecasts at least 2 site visits per month at CONUS and OCONUS installations. Maintenance actions for Spider are averaging an additional 2-3 per month for equipment sent to the FSRs or telephone/email support to unit maintainers. For HHI detector equipment, most CONUS/OCONUS units initially coordinate repair actions with the CLS team via telephone or email. As a last resort, equipment is shipped to the FSRs for evaluation/repair and returned to user, accordingly. On average, 3-4 repair actions a month may be anticipated for HHI support. Periodically, at the request of a customer, an FSR mobile team may conduct a site visit to an installation to perform a technical inspection of all their HHI equipment. Refer to Attachment 0006, Sample Format for Field Service Representative (FSR) Event Tracker, for guidance on candidate HHI locations that have been historically supported in this manner.

Q11. Is training completed on a scheduled recurring basis or is it associated with unit deployment schedules? Are there other criteria used to determine training frequency?

A11. Training schedule is determined by equipment fielding schedule. Refer to Government response to Question 9 herein for guidance.

Q12. Are units trained in a single training event or does training require multiple visits to a single location?

A12. Training events are typically a one-time activity but may involve several trips to each installation due to unit schedules.

Q13. Is the vendor required to include equipment that is located at the CONUS/OCONUS units on the equipment inventory for this contract?

A13. No. Equipment that has been issued to the CONUS/OCONUS units is not considered Government Furnished Property (GFP) and therefore

4 31

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

is not identified on the Program Management (PM) inventory.

Q14. What is the square footage of the FLW facility that is storing the GFP?

A14. Storage space is Government furnished and is adequate to support the mission of CLS support to PM CCS equipment. The storage space can be changed based on the introduction of additional conexes as each program arranges for more storage space.

Q15. The Contractor may occupy office space within the Fort Leonard Wood Army Installation if coordinated with and approved by the COR and KO. Will the Government clarify this? Does the COR and KO have access to office space on Fort Leonard Wood that the Government prefer the Offeror occupy or office space that would be beneficial to the Government and cost effective?

A15. The Government intends for the Offeror to be located in the vicinity of Fort Leonard Wood and not specifically on base. As such, this statement has been removed from the PWS as noted above. See #3.

Q16. Paragraph 5.2.1 states that "the Contractor shall be responsible for round trip travel costs for individuals that are not cleared for deployment by CRC". Will the Government please explain the round trip travel costs to which they are referring?

A16. Should a Contractor employee not pass inprocessing at CRC and/or are declared ineligible for Theater deployment, the Contractor shall be responsible for the associated round trip travel costs between home of record and CRC. These costs may consist of but are not limited to the airfare/costs associated with getting to CRC, and the airfare/costs associated with their return home from CRC. These costs shall not be passed on to the Government and will not be reimbursed.

Q17. Paragraph 5.3.1 requires Contractors to use Government provided air transportation. Does this mean that the Contractor does not schedule airline travel from CRC to OCONUS locations? Is the Contractor allowed to use commercial airlines for travel to and from

Theater for vacation, emergency, or other circumstances?

A17. Government provided air transportation shall be utilized for personnel deploying and redeploying to/from Theater. Once in

Theater, Contractor may use commercial air for travel associated with approved leave or emergency leave at the Contractor's expense

(refer to PWS para 6.12). There is a distinction between OCONUS and Theater, therefore subject to COR approval, commercial air travel may be utilized by the Contractor to travel to OCONUS locations (e.g., Germany, Alaska, etc.).

Q18. Paragraph 6.7, references "...the entire family of PM CCS systems". Will the Government list the entire family of PM CCS systems or is this referring to Attachment 0001?

A18. Yes this is referring to the systems identified in Attachment 0001, as well as the systems listed in Section C 1.1.

Q19. Paragraph 6.9 states, "The Contractor shall be licensed IAW local standards..." Will the Government please define "local" as the word is used in this paragraph?

A19. "Local" refers to the location at which the equipment (e.g., material handling equipment) is being operated. It could be installation, state, country or Combatant Commander standards, as applicable. The Contractor should apply due diligence in knowing applicable standards prior to operating equipment.

Q20. Will the Government provide a notional (one-year schedule to include proposed training dates) for each of the 40 locations noted in PWS paragraph C.2.2.

A20. Training dates and locations are not currently available. The Government estimates up to 8 AN/PSS-14 lane preparations per year and up to 30 AN/PSS-14 trailing events per year (with multiple training events occurring at given locations). Each task order will be tailored to reflect anticipated training events by location for the associated period of performance. All training/maintenance events under the subsequent task orders are subject to available funding.

Solicitation Section L:_______________________

Q21. Paragraph 3.3.1(b) states, "two (2) electronic CD Copies of the proposal volumes shall be compiled... submitted on a single-write

CD ROM. Does the Government want two (2) separate CD ROMs with a single copy of each volume?

A21. The Government requires two (2) separate CD ROMs for each volume of the Proposal. The CD ROMs utilized shall be single-write to prevent any accidental erasure of the data.

Q22. Paragraph 3.3.1(c) seems to indicate we are only required to provide one (1) hard copy of Volume IV. How many original and hard copies does the Government require for Volume I? How many original and hard copies does the Government require for Volume II? How many original and hard copies does the Government require for Volume III? How many original and hard copies does the Government require for

Volume IV?

A22. Offerors shall include:

5 31

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

Original- (1) signed and completed all-inclusive copy of the proposal

Volume I Technical Factor - five (5) paper copies, 2 CD copies

Volume II Past Performance Factor - five (5) paper copies, 2 CD copies

Volume III Price Factor - five (5) paper copies, 2 CD copies

Volume IV Solicitation, Offer, Award, Representation, and Certification Documents - one (1) paper copy, 1 CD copy

Q23. RFP Section L, Paragraph 4.1 states "the offerors proposal shall be submitted in severable volumes..." For clarification, did the

Government mean to write several or severable?

A23. The Volumes shall be severable, as in they are separate and can be read/evaluated on their own, independent of other volumes.

Q24. RFP Section L, Paragraph 5.1.1(d) states we are to provide a description of how we intend to recruit, hire, and retain personnel as it relates to the activities, documentation, and timing cited in Attachment 0002. Attachment 0002 provides a list of CONUS and OCONUS

Locations but provides no reference to specific documentation and/or timing. Will the Government please provide the list of documentation and referenced timing?

A24. There was a misprint in this paragraph. See #7 and #11 above for the applicable changes.

Q25. Paragraph 5.1.2 requires the offeror to develop a transition plan to meet the schedule and process requirements of the solicitation. The solicitation only provides locations but no proposed or notional execution schedule (timeline). Will the Government please provide a proposed schedule for the base year and option years so we can best address this requirement?

A25. This requirement is a 5 year Indefinite-Delivery/Indefinite-Quantity (ID/IQ) type contract. The Awardee will have 90 days to

Transition to Theater and 30 days to Transition for CONUS/OCONUS after first task order award. The Offeror is responsible for supplying the Government with their Transition Plan to meet the CLS requirements and shall be incorporated into the contract upon award.

Q26. Paragraph 5.1.2a requires the offeror to assume responsibilities for Theater locations not later than 90 days after first TO award. The VISA process times for travel are often unpredictable and in some cases may take longer than 90 days or within the window for purchasing airline tickets at a reasonable cost. Will the Government address this challenge with a statement in paragraph 5.1.2a that provides clarification? For example: "...not later than 90 days after first Task Order award, and when OCONUS personnel have VISAs for travel. VISA paperwork must be submitted at least 30 days from travel dates".

A26. The Government intends for a 90 day transition for Theater, to include any requirements necessary for performance. This 90 day period shall be addressed in the Offeror's Transition Plan.

Q27. Will the Government consider raising the past performance recency threshold from 3 years to 5 years?

A27. Yes, please see change addressed in #6, #9, and #10.

Q28. Paragraph 5.2.2 uses the term Major Subcontractors In reference to this solicitation. Will the Government please define Major

Subcontractor?

A28. As defined in Section L paragraph 5.2.2(3)Subcontracts, a Major subcontractor is one who will be "providing critical hardware/services or whose subcontract is for more than 25% of the total proposed price."

Q29. This paragraph states the past performance questionnaires are due within 30 calendar days of the release of the RFP. Does the 30 days begin on Friday 17 February and end on Saturday 18 March? Will the Government extend this date to occur at the same date and time the final proposals are due to the Government? Will the Government please provide a no later than date for the submission of the past performance questionnaires?

A29. Yes, paragraph 5.2.2(5) has been updated to reflect a Past Performance Questionnaire response date of 24 March 2017 2:00 pm EST

(see #8 above).

Solicitation Section J______________________

Exhibit A, CDRL A006____________________

Q30. Certification on remaining PM CCS systems supported by the task order shall be achieved within 90 days of award, new personnel hiring action or introduction of new PM CCS systems, as applicable. Will the Government clarify "introduction of new PM CCS systems ?

Does this mean systems other than stated in Attachment 0001?

A30. All current PM CCS systems are listed in Attachment 0001. New PM CCS systems not listed in Attachment 0001 may be added to the contract in the future via a bilateral modification.

6 31

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

Attachment 0003, Labor Category Definitions___________________________________________

Q31. Will the Government accept a Program Manager with one successful tour of duty as a Company Commander O-3 or higher?

A31. The Government is willing to change the Qualifications listed on Attachment 0003 for the Program Manager from "O-4" to "O-3". See

#10 above.

Q32. Will the Government include consideration for former Senior Enlisted Personnel? For example: one successful tour as a First

Sergeant or Sergeant Major (E-8 or higher)?

A32. The Government is not willing to consider the substitution due to the nature of this requirement.

Q33. Will the Government include consideration or trade-off for Civilian education? For example: Master of Business Administration, or

Doctorate in [Training] Education?

A33. The Government is not willing to consider the substitution due to the nature of this requirement.

Q34. This attachment requires the Program Manager, Logistician, Site Manager/Trainer and Maintenance Technician, and Trainer and

Maintenance Technician be able to meet CRC Deployment Requirements. Does this apply to all contractor personnel or only those that are deployed in Theatre?

A34. This requirement is for all Contractor personnel due to the requirement for CONUS/OCONUS personnel to be cross-trained on all systems and required travel to Theater training/maintenance needs.

Attachment 0063, Task Order 0001 Performance Work Statement (PWS)- For Informational Purposes Only__________________________________________________________________________________________________

Q35. Is it the Government's intent to make this task the first SOW/PWS required for execution under the new IDIQ contract?

A35. Yes, as stated in Section H, "The Performance Work Statement for Task Order 0001 is provided for informational purposes only to facilitate the award of the first task order. The Government intends to award the first task order within two (2) weeks of contract award."

*** END OF NARRATIVE A0002 ***

Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________

A-1 CHANGED 52.215-4006 GENERAL INFORMATION TO OFFERORS OR QUOTERS (AS6042) MAR/2012

1. Responses must set forth full, accurate and complete information as required by this solicitation (including attachments). Fill-ins are provided on Standard Form 18, Standard Form 33, and other solicitation documents. Examine the entire solicitation carefully. The penalty for making false statements is prescribed in 18 U.S.C. 1001.

2. Responses must be plainly marked with the Solicitation Number and the date and local time set forth for bid opening or receipt of proposals in the solicitation document.

3. Information regarding the timeliness of response is addressed in the provision of the solicitation entitled either Late Submission, Modification and Withdrawal of Bid or Instructions to Offerors Competitive Acquisitions.

4. Procurement Information

This Procurement is 100% set-aside for Small Business Firms.

The applicable SIC/NAICS codes are: 811219, Other Electronic and Precision Equipment Repair and Maintenance with a Size Standard of $20.5M.

5. Issuing Office

U.S. Army Contracting Command - New Jersey

ATTN: Tiffany Nosti

Office Symbol: ACC-NJ-CC

Picatinny Arsenal, NJ 07806-5000

7 31

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

Email: tiffany.n.nosti.civ@mail.mil

6. Additional Information: Not Applicable

7. Point of Contact for Information:

Name: Tiffany Nosti

Title: Contract Specialist

Email: tiffany.n.nosti.civ@mail.mil

Phone: (973) 724-7364

Fax: (973) 724-6542

Alternate Point of Contact Information:

Name: Tina G. Gopon

Title: Contracting Officer

Email: tina.g.gopon.civ@mail.mil

Phone: (973) 724-3516

Fax: (973) 724-6542

This requirement is for Contractor Logistics Support (CLS) services for the entire family of Project Manager (PM) Close Combat Systems

(CCS) program equipment issued to U.S. Forces, including equipment lent to North Atlantic Treaty Organization (NATO) and its support forces.

Proposal Submission___________________

All proposals are to be submitted in accordance with the instructions in Section L of the Solicitation. No proposals submitted via email or the Army Single Face to Industry (ASFI) website will be accepted. All proposals shall be received no later than 24 March 2017

2:00 pm EST.

Contract Type, Minimum Ordering Obligation, and Contract Maximum________________________________________________________________

This is an Indefinite-Delivery, Indefinite-Quantity (ID/IQ) type contract with Firm-Fixed-Price (FFP) and Cost No Fee Task Orders. The following guarantee and maximum obligation amount are for the services being procured under this contract, which has a period of performance of five (5) years.

Minimum Guarantee: $2,000,000.00

Maximum Contract Value: $36,000,000.00

Contract Years______________

This contract will include five (5) one (1) year ordering periods. The ordering periods are as follows:

The Ordering Period for Year 1 shall be for a period of 12 months from the date of contract award.

The Ordering Period for Year 2 shall be for a period of 12 months following Year 1.

The Ordering Period for Year 3 shall be for a period of 12 months following Year 2.

The Ordering Period for Year 4 shall be for a period of 12 months following Year 3.

The Ordering Period for Year 5 shall be for a period of 12 months following Year 4.

With each ordering period, the Government may issue task orders with periods of performance of 3, 6, 9, or 12 months. Prior to issuance each task order will be negotiated separately.

Task Order Procedures_____________________

The Contracting Officer on the prescribed Government forms will issue task orders consecutively numbered and will indicate:

a. Date of task order

b. Contract Number and Order Number

c. Contract Line Item Number (CLIN) and Description

d. Period of Performance

8 31

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

e. Place of Performance

f. Accounting and Appropriation Data

g. Payment Office

The Contracting Officer is the only Government representative with the authority to issue task orders against this contract.

Task orders will be transmitted and received via fax and/or e-mail.

Also see contract clauses entitled:

252.216-7006 Ordering (MAY 2011)

52.216-19 Ordering Limitations (OCT 1995)

52.216-22 Indefinite Quantity (OCT 1995)

Limited Distribution Data Information Instructions:___________________________________________________

Note: The highest Distribution Level for this procurement is "Distribution D".

This solicitation includes documents with limited distribution data. Documents with limited distribution data are identified by title in Section J and will be made available to interested offerors upon request.

DISTRIBUTION A: Approved for public release. Distribution is unlimited.

DISTRIBUTION C: Distribution is authorized to U.S. Government Agencies and their contractors only for administrative or operation use.

Other request for this document shall be the DoD Organizations listed in each individual document.

DISTRIBUTION D: Distribution is authorized to the Department of Defense and U.S. DoD Contractors only because the document contains sensitive information. Other requests shall be the DoD Organizations listed on each individual document.

DOD DIRECTIVE 5230-25: Disseminate in accordance with provisions of DoD Directive 5230-25. This also applies to all subcontractors at entry level. In the event that a potential offeror is a foreign company, they must comply with and obtain any necessary licenses required by the Arms Export Control Act and implementing regulations, prior to obtaining the referenced drawing.

EXPORT CONTROL WARNING: This document contains technical data whose export is restricted by the Arms Export control Act (Title 22, U.S.C., Sec 2751, et. seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C., App. 2401 et. seq. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230-25.

DESTRUCTION NOTICE: For classified documents, follow the procedures in DoD 5220.22-M, Industrial Security Manual, Section 11-19 or DoD

5200.1-R, Information Security Program Regulation, Chapter IX. For unclassified, limited documents, destroy by any method that will prevent disclosure of contents or reconstruction of the document.

*NOTE: The highest classification level for this requirement is SECRET. Contractor prersonnel shall be able to obtain a SECRET or above security clearance with the apppropriate background investigation as identified in Section C.

DISCLOSURE NOTICE: This information is furnished upon the condition that it will not be released to another nation without the specific authority of the Department of the Army of the United States, that it will be used for military purposes only, that individual or corporate rights originating in the information, whether patented or not, will be respected, that the recipient will report promptly to the United States, any known or suspected compromise, and that the information will be provided substantially the same degree of security afforded it by the Department of Defense of the United States. Also, regardless of any other markings on the document, it will not be downgraded or declassified without written approval of the originating United States agency.

To request limited distribution documents (documents labelled Distribution C and D), interested parties must submit the following:

1- A signed and approved DD Form 2345 Military Critical Technologies Data Agreement (Attachment 0011)

2- A completed AMSTA-AR Form 1350 Technical Data Questionnaire (Attachment 0012)

3- A completed and signed Non-Disclosure Agreement/Non-Use Agreement (Attachment 0010)

4- A copy of their applicable license issued by the Department of State if the offeror is a non-U.S. company.

All completed forms and requests shall be submitted to:

Army Contracting Command - New Jersey

ACC-NJ-CC

ATTN: Tiffany Nosti

Building 10, Phipps Road

9 31

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

Picatinny Arsenal, NJ 07806-5000 tiffany.n.nosti.civ@mail.mil

Electronic submissions of these documents will be accepted.

*** END OF NARRATIVE A0001 ***

10 31

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

Performance Work Statement

PM CCS Contractor Logistics Support (CLS)

1. Scope

1.1. On behalf of the United States Forces, the Project Manager Close Combat Systems (PM CCS) requires Contractor Logistics Support

(CLS) for the entire family of PM CCS program equipment issued to U.S. Forces including equipment lent to North Atlantic Treaty

Organization (NATO) and its support forces. This equipment includes but is not limited to: Phraselator 2 Translation Device, Magnetic

Audio Device (MAD), Garrett Hand Held Metal Detector, Vehicle Lightweight Arresting Device (VLAD), Entry Point Vehicle Kit - Solid State

(EPVK SS), Magnum Spike System MS-16, Handheld Initiative (HHI) systems (VMC1 (Gizmo), VMR2/2+ (Minehound), Detector Special Purpose

#27 (DSP-27), Ceia Compact Metal Detector (CMD) 2.X and Strider Detector System), Army-Navy/Portable Special Search (AN/PSS)-14 Models B and C, LightGuard Mercury, Family of Spider systems, Acoustic Hailing Device (AHD)(AN/TIC-43), and Multispectral Advance Reconnaissance

Video Imaging Notator (MARVIN).

1.2. Major support areas include system integration/installation, fielding, shipping, transportation, training to include site preparation, documentation updates, customer support, inspection and maintenance (defined as repair, rebuild, parts repair replacement, and troubleshooting) as applied to hardware, software, firmware and logistics support, and the associated support tasks such as program management, administration support, inventory management, quality management. Additional requirements include interfacing with other

Government and Contractor personnel as coordinated by the Contracting Officers Representative (COR).

1.3. The Contractor shall provide supervision and oversight to complete the efforts described in this Performance Work Statement (PWS).

The Contractor shall be responsible for hiring personnel with mechanical and electrical knowledge and skills In Accordance With (IAW)

Attachment 0003, who are capable of installing, maintaining and sustaining the entire family of PM CCS systems. Personnel shall be capable of setting up training lanes, conducting operator training, maintenance training, Train-the-Trainer and key leader level training to include testing each operators proficiency on the equipment using task, condition and standard format.

2. Applicable Documents: The applicable documents may be found at the following websites: http://www.apd.army.mil/, http://armypubs.army.mil/index.html, http://www.dtic.mil/whs/directives/index.html, https://assist.dla.mil/online/start/ or as noted herein.

| Document | Title | Date |

| DODI 5230.24 | Distribution Statements on Technical Documents (Rapid Action Revision Issue Date) | 23 Aug 2012 |

| AR 530-1 | Operations Security (OPSEC) | 26 Sep 2014 |

| AR 750-1 | Army Materiel Maintenance Policy | 12 Sep 2013 |

| N/A | Joint Travel Regulations (JTR) | 01 Oct 2014 |

| DA PAM 750-8 | The Army Maintenance Management System (TAMMS) User's Manual | 22 Aug 2005 |

| DD Form 1149 | Requisition and Invoice/Shipping Document | 01 Jul 2006 |

| N/A | DoD Foreign Clearance Manual/Guide https://www.fcg.pentagon.mil | 03 Jan 2017 |

| N/A | SOP for Fielding and Property Management of PM CCS Equip. | 02 May 2014 |

| AER 715-9 | Contractor Personnel in Germany-Technical Expert, Troop Care, & Analytical Support Personnel | 10 Sep 2009 |

| USFK Reg. 700-19 | The Invited Contractor And Technical Representative Program | 28 Aug 2012 |

| USFK Form 700-19A-R-E | Invited Contractor And Technical Representative Personnel Data Report | 01 Feb 2007 |

| DoD 5220.22-M | National Industrial Security Program Operating Manual (change 2) | 18 May 2016 |

| DD Form 441 | DoD Security Agreement | 01 May 2008 |

| AR 381-12 | Threat Awareness and Reporting Program (TARP) | 04 Oct 2010 |

| N/A | Security Classification Guide (SCG) For AN/PSS-14 Mine Detecting Set (MDS) | 22 Feb 2013 |

| N/A | SCG For Strider | 07 Oct 2013 |

| N/A | SCG For Detector Special Purpose Number 27 (DSP-27) | 08 May 2015 |

| N/A | SCG For Dispensing Set, Munition, Network Command: M7 Spider, M7E1 Spider | 02 Sep 2016 |

| N/A | SCG For Experiment Fix Program (applies to: CEIA Compact Metal Detector, VMC1 and VMR2) | 24 Sep 2010 |

3. List of Government Attachments

All documents listed in this section will be supplied to the Contractor and are also listed in Section J of the contract.

| Document | Title | Date |

| Attachment 0001 | PM CCS Systems | 30 Sep 2016 |

| Attachment 0002 | Government Locations | 30 Sep 2016 |

| Attachment 0003 | Labor Category Definitions | 23 Nov 2016 |

| Attachment 0004 | TSP, TMs/Installation & De-installation Instructions, andPOIs | 30 Sep 2016 |

| Attachment 0005 | Government Furnished Property | 30 Sep 2016 |

| Attachment 0006 | Sample Format for Field Service Representative (FSR) Event Tracker | 1 June 2016 |

| Attachment 0007 | AN/PSS-14 Site Training Lane Preparation Instructions | 8 Nov 2016 |

11 31

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

| Attachment 0008 | Quality Assurance Surveillance Plan (QASP) | 23 Nov 2016 |

| Attachment 0009 | Procedure to Designate a US Invited Contractor under the US-ROK SOFA | 1 June 2016 |

4. Requirements

4.1. General CLS Requirements - The Contractor shall perform the following services for PM CCS systems and equipment listed in

Attachment 0001, at the locations listed in Attachment 0002: training; maintenance; installing equipment, parts, and training lanes;

property inventory; tracking and accounting for property; disassembly; packing and labeling; loading; shipping; transporting (to include interim warehousing and in-transit visibility, as required); unloading; moving to final installed location, unpacking, assembly and operational testing.

4.1.1. Field Service Representatives (FSRs): The Contractor shall provide all specific logistics support requirements delineated in

Section 4.2 below for all PM-CCS Equipment listed in Attachment 0001.

4.1.2. Place of Performance: The contract management locations shall be in the vicinity of Fort Leonard Wood, MO (for CONUS) and

Afghanistan (for US Central Command (CENTCOM) Area of Responsibility (AOR)). Both locations shall require full time manning of personnel. Additional contract performance locations include, but are not limited to, the locations contained in Attachment 0002.

4.1.3. Post Award Conference. A post award conference shall be held at the contractors facility within 30 days after contract award.

The purpose of this review is for the contractor to review and demonstrate to the Government the management procedures, provide progress assessments, review of technical and other specialty area status, and to establish schedule dates for near term critical meetings/actions. The contractor shall present management, key personnel, and program implementation processes. The contractor shall provide the Government with minutes of the post award conference within seven (7) calendar days following the conference IAW DI-ADMN-

81505 (CDRL A007).

4.2. Specific CLS Requirements

4.2.1. Contractor Transition Planning

The Contractor shall execute the Government approved transition plan. The Government approved Contractors transition plan shall be included as an attachment to the contract. The Contractor shall assume CLS responsibilities and execute all requirements contained within the PWS for Theater locations (Theater is synonymous with US CENTCOM AOR) no later than 90 days after the first task order award.

For CONUS locations, the Contractor shall assume full CLS responsibilities no later than 30 days after first task order award.

4.2.2 Training

4.2.2.1. Training includes: initial, follow-on, remedial, refresher, operators, maintenance, troubleshooting, training lane preparation, installation, de-installation, service items removal/replacement, recovery procedures, New Equipment Training (NET) and

Doctrine, Tactics and Techniques (DTT); IAW the Training Support Package (TSP) (Attachment 0004). Electronic training applications such as, video teleconferencing and computer-based training (CBT), shall be employed to enhance the effectiveness of training materials and courses.

4.2.2.2. AN/PSS-14 Site Training Lane Preparation Support

4.2.2.2.1. In support of the AN/PSS-14 training events, the Contractor shall prepare and setup up to twelve (12) lanes per location (up to a total of forty (40) locations) in accordance with the AN/PSS-14 Site Training Lane Preparation Instructions outlined in Attachment

0007 of the PWS. The Government representative will coordinate lane preparation with respective military installation Range Control

Offices for the Contractor to install, re-install or upgrade the AN/PSS-14 Training lanes. The Contractor shall participate in site surveys with Government representatives at each location to determine the appropriate number of lanes and layout based on available real estate. The site survey shall be used to determine the level of metallic clutter removal and logistics required to successfully prepare lanes. The Government representative will be responsible for obtaining the appropriate environmental or dig permits required prior to the work commencing.

4.2.2.2.2. Based on the lane design and as annotated within Attachment 0007, the Contractor shall purchase material and rent equipment necessary to prepare and setup the lanes for required items that are unavailable and cannot be furnished by the Government.

4.2.2.2.3 Site planning and preparation could be different for each location. The Contractor shall apply specific ground clearance requirements as stated in the lane preparation instructions within Attachment 0007 as applicable to meet the Governments requirements for each potential location, which will be determined in each task order. The Contractor shall follow the layout instructions for building the training lanes. Specific designs will be based on the types of hazards to be identified as well as the specific number of lanes required. The layout of the lanes is critical to achieve maximum training benefit. The Contractor shall adhere to the precise measurements and instruction delineated in Attachment 0007 without deviation unless authorized in writing by the Contracting Officer

(KO). The Contractor shall prepare a Lane Key per lane per site for each completed site training lane preparation and submit the lane keys as part of the After Action Report (AAR) requirement (DI-MISC-80508B) (CDRL A001).

12 31

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

4.2.2.3. The Contractor shall provide training to Soldiers and Instructors and Key Personnel (IKP) on all equipment identified in

Attachment 0001. As authorized by the COR, the Contractor shall provide training at the identified locations (Attachment 0002).

4.2.2.4. Training shall cover equipment operation, operator maintenance, basic Preventative Maintenance Checks and Services (PMCS), troubleshooting, installation of equipment, service items removal/replacement, and recovery procedures.

4.2.2.5. The Contractor shall schedule training based on known and emerging training requests received from the COR. The Government will notify the Contractor a minimum of seven (7) calendar days prior to the start of the training event. The training schedules will be subject to change throughout the period of performance for this effort.

4.2.2.6. The Contractor shall administer the TSP or Program of Instruction (POI) examination at the end of each course. In accordance with the standards in the TSP/POI, the Contractor shall provide remedial training to all Soldiers or IKPs that fail the examination.

All remedial training requests shall be approved by the COR. The Contractor shall submit training records to the COR (DI-MISC-80508B)

(CDRL A001).

4.2.2.7. The Contractor shall provide all attendees that successfully complete the course and pass the end-of-course examination with a training certificate. The standard format of this certificate will be provided by the Government COR. The Contractor shall update the certificate with the appropriate system and attendee information such as, their name, rank, dates of attendance and system name and provide a copy to the COR. Within five (5) days of receipt from the COR, the Contractor shall issue the signed certificates to the attendees.