About this file
This document is a WebAIM Short Form Task Group Instruction (TGI) for the USS John Finn (DDG-113), detailing a maintenance task to replace the peel and stick nonskid system on the forward 02 level deck plating. The work involves replacing 970 square feet of nonskid deck covering on the 02 Level Weather, Frames 193-228 (Port and Starboard), and 487 square feet in the Uptake Engine Room No. One, including vertical surfaces up to 4 inches from the deck. The contractor work is scheduled to start on 4/20/26 and complete by 6/15/26, with the nonskid deck covering required to conform to MIL-PRF-24667, Type XI, Composition PS. SRF-JRMC will provide supporting services including crane rigging, utility services (electrical, air, water, steam), and safety/quality assurance inspections.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
08-AUG-2025 0806
20.15.6.0.9333 (July 2025) ICN: 38BC163406 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 02 PEEL AN STICK AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-113 USS JOHN FINN BC1
CU PHASE TITLE: F/O - REPLACE PEEL AND STICK NONSKID SYSTEM ON FWD 02 LEVEL DECK PLATING
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 3
ES01L021
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
NAKAGAWA, DAICHI 231A 3152430969 11-JUL-2025
APPROVED BY: CODE: PHONE: DATE:
NAKAMURA, YUUJI 231A 3152436041 11-JUL-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
ES01-L021
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
634A1106
1. SCOPE/PURPOSE:
1.1 Title: Peel and Stick Nonskid System on Forward (FWD) 02 Level Deck Plating; replace
1.2 Location of Work:
1.2.1 02 Level Weather, Frames between 193 and 228, Port and Starboard (Stbd)
1.2.2 Uptake Engine Room No. One (02-186-0-Q)
1.3 Identification:
1.3.1 Quantity (970 SF), 02 Level Deck Plating, Frames between 193 and 228, including vertical surface up to height of 4 inches from deck in and around peel and stick nonskid deck covering area, Port and Stbd
1.3.2 Quantity (487 SF), Deck Plating in 02-186-0-Q, including vertical surface up to height of 4 inches from deck in and around peel and stick nonskid deck covering area
TGI Short Form
08-AUG-2025 0806
20.15.6.0.9333 (July 2025) (Continued) ICN: 38BC163406 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 02 PEEL AN STICK AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-113 USS JOHN FINN BC1
CU PHASE TITLE: F/O - REPLACE PEEL AND STICK NONSKID SYSTEM ON FWD 02 LEVEL DECK PLATING
FOUO Pg 2 of 3
CU PHASE DESCRIPTION (Cont.)
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1.4 Security Classification: None.
1.5 Initial Condition: None.
1.6 Contractor work start date:
1.7 Contractor work completion date:
2. PROCEDURE:
2.1 Accomplish the requirements of 009-032 of Ref. No. One, including Table 2, Line(s) 25, for each area listed in 1.3.1 and 1.3.2.
2.1.1 Accomplish the requirements of 009-026 of Ref No. One, including Attachment G, for installation of new peel and stick nonskid deck covering. Application of peel and stick nonskid deck covering must conform to MIL-PRF-24667, Type XI, Composition PS.
2.2 Notes:
2.2.1 Planner: Code 231A D. Nakagawa, 243-0969
2.2.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
2.2.3 JCN ES01-L021 is related to this TGI.
2.3 Government Furnished Material (GFM):
2.4 SRF-JRMC will provide the following service work: (TGI No. 38BC163406S02)
2.4.1 [C740] Crane and crane rigging service.
2.4.2 [X99E] Utility service, electrical.
2.4.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
2.4.4 [C106.1] Safety inspection for SRF-JRMC employees.
2.4.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.4.6 [C133] QA inspection for (G) symbol(s).
4/20/26
6/15/26
08-AUG-2025 0806
20.15.6.0.9333 (July 2025) (Continued) ICN: 38BC163406 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 02 PEEL AN STICK AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-113 USS JOHN FINN BC1
CU PHASE TITLE: F/O - REPLACE PEEL AND STICK NONSKID SYSTEM ON FWD 02 LEVEL DECK PLATING
FOUO Pg 3 of 3
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
2.1 PNTR , CARP , QA , SMTL 22/KE PC
CFM: for all paints, peel and stick nonskid, thinner, compressor and fuel oil, dryer for compressor, sampler/analyze.
22/MQ CS
Process Funding Document 10/CT OM
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 38BC163406 KEY OP: A01