TGI_38BC112201_A01_c0v0_Redacted.pdf

PDF 296 KB Posted

Attached to
USS JOHN FINN (DDG-113) FY26 6J1 CNO BUNDLE #1, Chief of Naval Operation Availability Yokosuka Japan
Solicitation number
N6264926RA009
Issued by

About this file

This WebAIM Short Form Task Group Instruction (TGI) details preservation and replacement work for the USS John Finn (DDG-113), specifically targeting the superstructure, platform, and nonskid deck covering. The work involves multiple preservation tasks across 03, 04, and 05 Level Weather areas, including 650 square feet of exterior platform surface, 175 square feet of deck plating, and one lot of composite panel work. Additional tasks include coating preservation for bulkheads and antenna foundation, with work to be performed between April 20, 2026, and June 15, 2026. SRF-JRMC will provide supporting services including crane rigging, utility services, safety inspections, and quality assurance inspections. The nonskid deck covering must conform to MIL-PRF-24667, Type XI, Composition PS specifications.

View the file

Other files

File Type Posted
N6264926RA0090008 SF 30.pdf PDF
Solicitation Amendment N6264926RA0090007 SF 30.pdf PDF
RFI Q7A7.rtf RTF text file
300-23-224.After Hours Hotwork Memo (002).pdf PDF
Solicitation Amendment N6264926RA0090007 SF 30.pdf PDF
Solicitation Amendment N6264926RA0090006 SF 30.pdf PDF
Solicitation Amendment N6264926RA0090004 SF 30.pdf PDF
Solicitation Amendment N6264926RA0090005 SF 30.pdf PDF
RFI Q6A6.rtf RTF text file
RFI Q5A5.rtf RTF text file
Solicitation Amendment N6264926RA0090003 SF 30.pdf PDF
Solicitation Amendment N6264926RA0090002 SF 30.pdf PDF
RFI Q4A4.rtf RTF text file
Solicitation Amendment N6264926RA0090001 SF 30.pdf PDF
RFI Q3A3.rtf RTF text file
RFI Q1A1.rtf RTF text file
RFI Q2A2.rtf RTF text file
Solicitation - N6264926RA009.pdf PDF
TGI_38BC186301_A01_c0v0_Redacted 22JUN.pdf PDF
TGI_38BC163404_A03_c0v0_Redacted.pdf PDF
Attachment (V) Source of Repair Instruction.pdf PDF
TGI_38BC116801A01_c1v1_Redacted.pdf PDF
TGI_38BC125106_A01_c0v0_Redacted.pdf PDF
TGI_38BC163406_A01_c0v0_Redacted.pdf PDF
Attachment (VI) Warranty Tracking Information.pdf PDF
Attachment (III) Request for Information Form.rtf RTF text file
TGI_38BC112313_A01_c0v0_Redacted.pdf PDF
TGI_38BC186502_A01_c0v0_Redacted.pdf PDF
TGI_38BC112311_A01_c0v0_Redacted.pdf PDF
TGI_38BC112312_A01_c0v0_Redacted.pdf PDF
Attachment (VIII) Contract Data Sheet 26RA009.pdf PDF
Attachment (II) Price Proposal Form N6264926RA009.xlsx XLSX spreadsheet
TGI_38BC154101_A01_c0v0_Redacted.pdf PDF
TGI_38BC125105_A01_c0v0_Redacted.pdf PDF
Attachment (IV) GFP_List_V3.xlsx XLSX spreadsheet
Attachment (VII) QASP 26RA009 Bun1.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

08-AUG-2025 0806

20.15.6.0.9333 (July 2025) ICN: 38BC112201 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 03 - 05 LVL WEATHER AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-113 USS JOHN FINN BC1

CU PHASE TITLE: F/O – ACCOMPLISH PSVTN OF SUPERSTR AND PLTF AND REPLT OF NONSKID DECK COVERING

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 4

ES01L024

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

TAKANASHI, TATSUNORI 231A 3152436238 28-JUL-2025

APPROVED BY: CODE: PHONE: DATE:

NAKAMURA, YUUJI 231A 3152436041 28-JUL-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

ES01-L024

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

122A2101

1 SCOPE/PURPOSE:

1.1 Title: Preservation of Superstructure and Platform and Replacement of Nonskid Deck Covering; accomplish

1.2 Location of Work:

1.2.1 03 Level Weather, Frames between 175 and 215, Port

1.2.2 04 Level Weather, Frames between 175 and 190, Port and Starboard (Stbd)

1.2.3 05 Level Weather, Frames between 180 and 192, Port and Stbd

1.3 Identification:

1.3.1 Quantity (650 SF), Exterior Surface of Platform 76 Feet – 5 Inches Above Base Line (ABL) and Platform 65 Feet – 8 Inches ABL, including stanchion and support

Remarks: The area except where nonskid deck covering system is installed

TGI Short Form

08-AUG-2025 0806

20.15.6.0.9333 (July 2025) (Continued) ICN: 38BC112201 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 03 - 05 LVL WEATHER AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-113 USS JOHN FINN BC1

CU PHASE TITLE: F/O – ACCOMPLISH PSVTN OF SUPERSTR AND PLTF AND REPLT OF NONSKID DECK COVERING

FOUO Pg 2 of 4

CU PHASE DESCRIPTION (Cont.)

1.3.2 Quantity (175 SF), Deck Plating of Platform 76 Feet – 5 Inches ABL and Platform 65 Feet – 8 Inches ABL, including vertical surface up to height of 4 inches from deck in and around peel and stick nonskid deck area

1.3.3 Quantity (One Lot), Composite Panel for Platform 76’ – 5” ABL and Platform 65 Feet – 8 Inches ABL

1.3.4 Quantity (5 SF in Total), Deteriorated Coating of Longitudinal Bulkhead, 03 Level, Frames between 193 and 213, Port Remarks: The area is surface where underside of louver

1.3.5 Quantity (9 SF in Total), Deteriorated Coating of Transvers Bulkhead, 03 Level to 05 Level, Frames between 186 and 189, Port and Starboard

1.3.6 Quantity (4 SF in Total), Deteriorated Coating of Foundation for Antenna 3-10B

1.4 Security Classification: None.

1.5 Initial Condition: None.

1.6 Contractor work start date:

1.7 Contractor work completion date:

2 PROCEDURE:

2.1 Accomplish the requirements of 009-032 of Ref. No. One, including Table 2, Line(s) One, for each area listed in 1.3.1.

2.2 Accomplish the requirements of 009-032 of Ref. No. One, including Table 2, Line(s) 23, for each area listed in 1.3.2.

2.2.1 Accomplish the requirements of 009-026 of Ref No. One, including Attachment G, for installation of new peel and stick nonskid deck covering. Application of peel and stick nonskid deck covering must conform to MIL-PRF-24667, Type XI, Composition PS.

2.3 Accomplish the requirements of 009-032 of Ref. No. One, including Table 2, Line(s) 83, for each area listed in 1.3.3.

2.4 Accomplish the requirements of 009-032 of Ref. No. One, including Table 2, Line(s) One, for each area listed in 1.3.4 through 1.3.6.

2.4.1 The preservation area must not exceed 10 square feet per one area.

2.5 Notes:

2.5.1 Planner: Code 231A T. Takanashi, 243-6238

2.5.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-6522-9560

2.5.3 JCN ES01-L024 is related to this TGI.

2.6 Government Furnished Material (GFM): None.

4/20/26

6/15/26

08-AUG-2025 0806

20.15.6.0.9333 (July 2025) (Continued) ICN: 38BC112201 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 03 - 05 LVL WEATHER AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-113 USS JOHN FINN BC1

CU PHASE TITLE: F/O – ACCOMPLISH PSVTN OF SUPERSTR AND PLTF AND REPLT OF NONSKID DECK COVERING

FOUO Pg 3 of 4

CU PHASE DESCRIPTION (Cont.)

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

2.7 SRF-JRMC will provide the following service work: (TGI No. 38BC112201S02)

2.7.1 [C740] Crane and crane rigging service.

2.7.2 [X99E] Utility service, electrical.

2.7.3 [X99M] Utility service, including water supply, steam supply and low pressure air supply except on-board blasting work.

2.7.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.7.5 [C106.2] Gas free inspection for SRF-JRMC employees.

2.7.6 [C133] QA inspection for (G) symbol(s).

08-AUG-2025 0806

20.15.6.0.9333 (July 2025) (Continued) ICN: 38BC112201 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 03 - 05 LVL WEATHER AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-113 USS JOHN FINN BC1

CU PHASE TITLE: F/O – ACCOMPLISH PSVTN OF SUPERSTR AND PLTF AND REPLT OF NONSKID DECK COVERING

FOUO Pg 4 of 4

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - N OR

G

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

2.1 PNTR , RGRS , CARP , QA 22/KE PC N

2.2 PNTR , CARP , QA 22/KE PC N

2.3 PNTR QA 22/KE PC N

2.4 PNTR , QA 22/KE PC N

Preservation Work CFM: all paints, grits, thinner, compressor and fuel oil, dryer for compressor, air conditioner, and misc such as consumable parts and covering material.

22/MQ CS N

Process Funding Document 10/CT OM N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 38BC112201 KEY OP: A01